E. O. Dorsch Electric Co. v. Plaza Construction Co.

413 S.W.2d 167, 1967 Mo. LEXIS 948
CourtSupreme Court of Missouri
DecidedApril 10, 1967
Docket52411
StatusPublished
Cited by77 cases

This text of 413 S.W.2d 167 (E. O. Dorsch Electric Co. v. Plaza Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
E. O. Dorsch Electric Co. v. Plaza Construction Co., 413 S.W.2d 167, 1967 Mo. LEXIS 948 (Mo. 1967).

Opinion

STOCKARD, Commissioner.

By its petition plaintiff sought damages in the amount of $21,086.30 for negligence. The trial court entered summary judgment for defendants and plaintiff has appealed.

Plaintiff alleged in its petition that as a subcontractor it had “installed under a contract with the general contractor, various kinds of electrical material” in buildings known as the St. Louis Plaza Project in the City of St. Louis, and that following such installation and “while defendants were engaged in erecting and constructing the brick and concrete on said buildings, said defendants, their agents and servants, negligently and carelessly damaged and destroyed certain parts of the electrical work and material which had been previously installed in said buildings by plaintiff, causing said work, labor and material to be unfit for use, which required plaintiff to and it did replace the same, all to the damage of plaintiff in the sum of $21,086.30.”

In answer to a request for admissions pursuant to Civil Rule 59.01, V.A.M.R., plaintiff admitted that “the electrical material originally installed and the work and labor originally required to install the same, was installed under one or more” of four contracts, attached to the request for admissions, and subsequently identified, but it further stated that after the execution of the contracts they were “changed and modified by agreement of the parties.” No explanation was made as to what the asserted changes and modifications consisted.

Thereafter, defendants filed a motion for summary judgment on the theory that pursuant to the provisions of the applicable contracts plaintiff did not own and had no interest in or duty to restore any electrical material or work allegedly damaged by the negligence of defendants, that plaintiff had a contract right to full payment for any repair or replacement work done by it at the request of the general contractor, and that for these reasons as a matter of law plaintiff did not and could not sustain any damage as the result of the alleged negligence. Defendants filed an affidavit in support of their motion for summary judgment to which were attached the four subcontracts referred to in plaintiff’s answer to the request for admissions, and to which were also attached four groups of instruments, three instruments in each group applicable to each of the subcontracts. Each group of instruments pertain to the construction of a separate project, and the corresponding instruments in each group are similar. We shall refer to the terms of but one subcontract and the terms of the three instruments referred to therein.

Instrument “B” was a “cost plus” construction contract between First Plaza Redevelopment Corporation as “Owner” and Plaza Construction, Inc. as “Contractor” for “all the materials and * * * work within the property lines, shown on the drawings and specifications.” Instrument “C” was a deed of trust between the Owner and Manufacturers Trust Company with the Mercantile Trust Company being named as Trustee. Instrument “A — 1” was an agreement between Owner and Paul Tish-man General Contractor, Inc., and Fruin-Colnon Contracting Company, operating as a joint venture and referred to as “Agents,” wherein it was provided that Agents were in effect to represent the Contractor in the performance of the contract with authority to negotiate subcontracts. Instrument “A” was a subcontract between Agents and plaintiff wherein it was provided that plaintiff was to perform certain electrical work provided for in the contract between Owner and Contractor, and was one of the contracts referred to in the re *169 quest for admissions and plaintiff’s answer thereto. All of these instruments were attached to and incorporated as a part of defendants’ motion for summary judgment, and although plaintiff stated in its answer to the request for an admission that Instrument “A” had been “changed and modified by agreements of the parties,” at the hearing on the application for summary judgment plaintiff filed no affidavit and offered no proof to the effect that the terms of any of the instruments attached to the application for summary judgment were not as therein set forth.

The trial court found that the “terms of the contract are not in dispute,” and further found the facts as follows: “The contract gave the defendants the right to occupy any portion of the work ‘which has been either partially or fully completed’ by the subcontractor, and it further provided ‘The subcontractor shall not be responsible for any damage thereto that is due to or caused by the negligence of the contractor or agents during such period of use.’ The contract makes full provisions for any work required to be done other than that specifically set out therein. In view of the above, it would appear that under the pleadings, exhibits and affidavits, there is no issue presented, and that the defendant^] [are] entitled to judgment.”

On this appeal plaintiff asserts that the trial court erred in sustaining defendants’ motion for summary judgment because “there were, under the pleadings and affidavits, many fact issues to be determined.” Defendants, on the other hand, contend that summary judgment was properly entered “because the written contracts between plaintiff and defendants establish conclusively that plaintiff did not own and had no interest in or duty to restore the work allegedly damaged by the negligence of defendants, that plaintiff had a contract right to full payment for any repair or replacement work done by it, and that plaintiff did not and could not sustain any damage by reason of the alleged negligence of defendants.”

Prior to considering the applicable provisions of the contracts, we shall set forth briefly the basic rules relating to entering summary judgment.

Summary judgment is authorized where, but only where, the “pleadings, depositions, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that any party is entitled to a judgment as a matter of law.” Civil Rule 74.-04(c), V.A.M.R. In addition to the above, it is further provided that “In no case shall a summary judgment be rendered on issue triable by jury or the court without a jury unless the prevailing party is shown by unassailable proof to be entitled thereto as a matter of law.” Civil Rule 74.04(h), V.A. M.R. “As its name indicates, a summary judgment is an extreme and drastic remedy and great care should be exercised in utilizing the procedure,” Cooper v. Finke, Mo., 376 S.W.2d 225, 229, and the appellate court, as well as the trial court, must view the record on summary judgment in the light most favorable to the party against whom the judgment is rendered. Anderson v. Steurer, Mo., 391 S.W.2d 839, 842.

In this case the motion for summary judgment is based upon the pleadings, which incorporated the contract documents by reference, and the admissions of plaintiff in its answer to the request for admissions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kathryn J. McKay v. Gary Michael Peloza
Missouri Court of Appeals, 2022
Spencer v. Hartford Cas.
556 S.W.3d 679 (Missouri Court of Appeals, 2018)
Henson v. City of Springfield
524 S.W.3d 142 (Missouri Court of Appeals, 2017)
Vicki Lynn Street v. Edward Harris and Mary Lou Harris
505 S.W.3d 414 (Missouri Court of Appeals, 2016)
Painter v. City of Humansville
467 S.W.3d 278 (Missouri Court of Appeals, 2015)
Bank of America, N.A. v. Reynolds
348 S.W.3d 858 (Missouri Court of Appeals, 2011)
Ehrhardt v. Herschend
294 S.W.3d 58 (Missouri Court of Appeals, 2009)
Robert Baum v. Helget Gas Products, Inc.
440 F.3d 1019 (Eighth Circuit, 2006)
Arakaki v. SCD-Olanani Corp.
129 P.3d 504 (Hawaii Supreme Court, 2006)
Derges v. Hellweg
128 S.W.3d 186 (Missouri Court of Appeals, 2004)
Mothershead v. Greenbriar Country Club, Inc.
994 S.W.2d 80 (Missouri Court of Appeals, 1999)
Easy Returns Midwest, Inc. v. Schultz
964 S.W.2d 450 (Missouri Court of Appeals, 1998)
Zerebco v. Lolli Bros. Livestock Market
918 S.W.2d 931 (Missouri Court of Appeals, 1996)
Landes v. State Farm Fire & Casualty Co.
907 S.W.2d 349 (Missouri Court of Appeals, 1995)
Hornbeck v. All American Indoor Sports, Inc.
898 S.W.2d 717 (Missouri Court of Appeals, 1995)
Twitty v. State Tax Commission of Missouri
896 S.W.2d 680 (Missouri Court of Appeals, 1995)
Hamilton Hauling, Inc. v. Avenue Auto Wrecking, Inc.
883 S.W.2d 540 (Missouri Court of Appeals, 1994)
Southwest Bank of Polk County v. Hughes
883 S.W.2d 518 (Missouri Court of Appeals, 1994)
National Equity Resources Corp. v. Montgomery
872 S.W.2d 533 (Missouri Court of Appeals, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
413 S.W.2d 167, 1967 Mo. LEXIS 948, Counsel Stack Legal Research, https://law.counselstack.com/opinion/e-o-dorsch-electric-co-v-plaza-construction-co-mo-1967.