FINCH, Judge.

This is an appeal from a summary judgment entered by the trial court in favor of defendant. We have jurisdiction because the prayer of the petition sought $120,-000.00.

The plaintiff, Emil Anderson, a lather employed by the George Stroup Lathing Company, was injured when a scaffold collapsed. The scaffold and its boards were furnished by the defendant, John Steurer, Jr., a plastering contractor. In his fourth amended petition plaintiff sought damages for his personal injuries, alleging that defendant was guilty of several specific acts of negligence, particularly in connection with the furnishing of the plank that broke and precipitated plaintiff’s fall. Defendant pleaded contributory negligence, but also alleged that plaintiff was the employee of a subcontractor doing work on or about the premises where the principal contractor was doing work and was a statutory employee of this defendant. After certain requests for admissions by both parties and submission of interrogatories and the taking of various depositions, including depositions of defendant Steurer, George Stroup of the lathing company, and a representative of the general contractor on the job, defendant filed his motion for summary judgment un *841 der Civil Rule 74.04, V.A.M.R. In substance, the motion contended that there was no dispute as to any material fact, that plaintiff was a statutory employee of defendant, and that plaintiff’s exclusive remedy, in so far as defendant was concerned, was under the Workmen’s Compensation Act, in view of § 287.120 (all references are to RSMo 1959, V.A.M.S., unless otherwise indicated). Under that section an employer subject to the act is liable for compensation but is “released from all other liability therefor whatsoever, whether to the employee or any other person.”

Certain facts are not in dispute. The George Moeller Construction Company, hereinafter referred to as Moeller, had a general contract to construct a church for the Mount Tabor Evangelical and Reformed Church. Moeller entered into a written subcontract with John Steurer, Jr., hereinafter referred to as Steurer, for the lathing and plastering work on the church. Both Moeller and Steurer operated under the Workmen’s Compensation Act and Steurer furnished certificates of compensation insurance to Moeller. Another contractor, George Stroup Lathing Company, hereinafter referred to as Stroup, actually performed the lathing work on the job for Steurer. Steurer then did the plastering. The premises where the work was performed did not belong to Moeller, Steurer or Stroup. Stroup also operated under the Workmen’s Compensation Act and carried compensation insurance. Compensation ($8,659.29 plus medical expenses of $2,098.-19 up to November 14, 1963) was paid by that carrier to plaintiff, who then brought his suit against Steurer as a third party whose alleged negligence resulted in plaintiff’s injuries.

The case is briefed in this court by defendant on the theory that the proof was unassailable that Moeller was the general contractor, that Steurer was a subcontractor under Moeller to do the lathing and plastering, that Steurer in turn subcontracted the lathing to Stroup, and that plaintiff was an employee of Stroup. If this were true, then we would have presented squarely for decision the question of whether an intermediate subcontractor in such a direct chain of relationship would have the same exempt status as statutory employer from third party negligence actions as the general contractor occupies under the doctrine of the case of Bunner v. Patti, 343 Mo. 274, 121 S.W.2d 153. However, plaintiff strenuously asserts that there was a genuine issue as to the relationship between Steurer and Stroup. He contends that there was a basic issue of fact as to whether plaintiff’s employer, Stroup, was a subcontractor of defendant Steurer, or whether there was a joint adventure of these two contractors. This calls, first, for a careful analysis of the evidence before the trial court on that issue.

The evidence as to the actual relationship between Steurer and Stroup was as follows : Plaintiff’s fourth amended petition alleged that Stroup was a subcontractor doing lathing work and that Steurer was a subcontractor doing plastering work, and that both were hired by Moeller, the general contractor. This latter contention is denied by Steurer, and there was nothing in any of the depositions or admissions to indicate that Moeller hired or directly contracted with Stroup. Steurer, in his deposition, testified that customarily in their work the plastering contractor contracts for both lathing and plastering. He said that Stroup had been doing all of the lathing for him on his commercial jobs for several years. He would call on Stroup for a price for the lathing on a particular job, and Steurer then would bid the job with his bid covering both lathing and plastering. If Steurer’s bid was low, he would get the job. Stroup then would go ahead and do the lathing. Payment from the general contractor would come to Steurer in one check and he then would pay Stroup. Steurer testified that this was a subcontracting operation, and he had no right to control Stroup or his men. Stroup, in his deposition, testified that he had an oral *842 contract with Steurer to perform the lathing work on the Mount Tabor job, the agreement being made about one year before March 1, 1960. That would have been prior to the contract of June 2, 1959, between Moeller and Steurer. Stroup further testified that Steurer usually would call him before bidding a job, and Stroup would take the job off the plans and specifications and prepare an estimate. Steurer then would compile his estimate and put the estimates together and send in a bid. With reference to payment, Stroup said that the practice was for him to work a month, prepare an estimate and then send it to Steurer. He was to be paid in thirty days. Any time Steurer has been paid, Stroup has been paid. As a rule, he said, when Steurer isn’t paid by the general contractor, Stroup is not paid, although he had known of times when he pressured Steurer and the latter paid him before payment by the general contractor to Steurer. Stroup said that on this Mount Tabor job he would not have expected pay from Steurer if there had been no payment by Moeller to Steurer. Stroup testified further that if there were any complaints about his work or corrections to be made, Steurer would contact him and he then would handle his men.

Steurer contends that this evidence shows by unassailable proof that Stroup was a lathing subcontractor under Steurer. On the other hand, plaintiff contends that this is not true and that there is a genuine issue of fact as to whether there might be a joint adventure between Steurer and Stroup rather than a situation in which Stroup was a subcontractor of Steurer.

The rule is well estabished that we must view the record on motion for summary judgment in the light most favorable to the party against whom the judgment is rendered. Cooper v. Finke, Mo., 376 S.W.2d 225, 228 [2]. A summary judgment is a drastic remedy and great care should be exercised in its utilization. Cooper v. Finke, supra, 229 [3].

Is there unassailable proof of a subcontractor relationship ? Stroup testified that he had an oral contract with Steurer for the lathing. Steurer said that he had a subcontract with Stroup.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shaw v. Mega Industries, Corp.
406 S.W.3d 466 (Missouri Court of Appeals, 2013)
Thornsberry v. Thornsberry Investments, Inc.
295 S.W.3d 583 (Missouri Court of Appeals, 2009)
Butts v. Express Personnel Services
73 S.W.3d 825 (Missouri Court of Appeals, 2002)
Vatterott v. Hammerts Iron Works, Inc.
968 S.W.2d 120 (Supreme Court of Missouri, 1998)
Doe v. Yale University, No. Cv 90 0305365 S (Dec. 1, 1997)
1997 Conn. Super. Ct. 13776 (Connecticut Superior Court, 1997)
Kelley v. DeKalb Energy Co.
865 S.W.2d 670 (Supreme Court of Missouri, 1993)
Scott v. Edwards Transportation Co.
807 S.W.2d 75 (Supreme Court of Missouri, 1991)
West v. Posten Construction Co.
804 S.W.2d 743 (Supreme Court of Missouri, 1991)
Ballinger v. Gascosage Electric Cooperative
788 S.W.2d 506 (Supreme Court of Missouri, 1990)
Canady v. Crystal Development Corp.
756 S.W.2d 607 (Missouri Court of Appeals, 1988)
Rhodes v. Rogers
675 S.W.2d 107 (Missouri Court of Appeals, 1984)
Fisher v. Scott & Fetzer Co.
664 S.W.2d 662 (Missouri Court of Appeals, 1984)
Whited v. National Western Life Insurance Co.
526 S.W.2d 364 (Missouri Court of Appeals, 1975)
Howard v. Winebrenner
499 S.W.2d 389 (Supreme Court of Missouri, 1973)
Estate of Sample v. Travelers Indemnity Co.
492 S.W.2d 829 (Supreme Court of Missouri, 1973)
Scott v. Thornton
484 S.W.2d 312 (Supreme Court of Missouri, 1972)
Citizens State Bank of Nevada v. Wales
469 S.W.2d 750 (Missouri Court of Appeals, 1971)
Matthews v. City of St. Ann
457 S.W.2d 766 (Supreme Court of Missouri, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
391 S.W.2d 839, 1965 Mo. LEXIS 799, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anderson-v-steurer-mo-1965.