Thompson v. Kroeger

380 S.W.2d 339, 1964 Mo. LEXIS 727
CourtSupreme Court of Missouri
DecidedJune 8, 1964
Docket50096
StatusPublished
Cited by8 cases

This text of 380 S.W.2d 339 (Thompson v. Kroeger) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thompson v. Kroeger, 380 S.W.2d 339, 1964 Mo. LEXIS 727 (Mo. 1964).

Opinion

HOLMAN, Judge.

Defendant, H. B. Deal Construction Company, was the general contractor engaged in the building of the Ballwin Plaza Shopping Center in St. Louis County. Defendant H. W. Kroeger (hereinafter generally referred to as defendant) had the subcontract to erect the steel on the project. The bricklaying work was done by another subcontractor, Steve Gorman Bricklaying Company. Plaintiff was employed by Gorman as a hodcarrier. On the morning of Julyl8, 1960, the bricklaying crew was working on an improvised scaffold which consisted of boards laid across steel ceiling joists that had been installed but not braced. Plaintiff sustained injuries in a fall which occurred when the joists deflected and gave way causing the boards and building materials thereon (as well as plaintiff) to fall to the ground. In this action the trial court sustained a motion for summary judgment in favor of defendant Deal. Upon a trial the jury returned a verdict in favor of the remaining defendant, H. W. Kroeger. Plaintiff has duly appealed from said judgments.

Plaintiff called as a witness Donald Peterson, one of defendant’s foremen. This witness testified that the accident occurred on a Monday morning at the southwest corner of the east wing of the building; that the ceiling joists in the building weigh approximately 500 pounds each; that most of the joists in that area had been set some time before that day but that the six joists next to the wall could not be set until certain construction had been completed; that on the morning in question he had a five-man crew operating a crane; that at 8 o’clock they set the six joists in question and then moved the crane to another part of the job and set a beam; that shortly thereafter he and another man went back to bridge the six joists (joists are bridged by attaching steel rods between them in the form of an “X”); that when he arrived at that place he found that the bricklaying crew had placed boards on the unbridged joists preparatory to working thereon; that *341 he told a laborer there to remove the boards but the man ignored his request; that he then went to the expediter for the general contractor and told him they couldn’t finish the work on the joists until the boards were removed and the expediter stated that “he would take care of it”; that the accident in which plaintiff was injured occurred shortly thereafter.

On cross-examination Mr. Peterson testified as follows: “Q. Had you ever talked whh this bricklaying crew on this job about using your bar joists as scaffolding? A. Previously we had told them not to do it. Q. How long before, Don? A. It seemed like every time we turned around they were doing it. And every time we would see it we would tell them * * *. Q. when you say tell them, did that include the bricklayers, the foremen, the laborers and everybody working with them? A. Well, usually the man that was doing it at the time would be told and the bricklaying foreman had been told. I told him and I know Fred had told him before.” The witness did not remember whether or not he told plaintiff personally not to put boards on the joists, although he remembered having seen plaintiff on the job.

Defendant Kroeger was also called as a witness by plaintiff. Mr. Kroeger testified that he was at the site of this project on Thursday before plaintiff was injured and the six joists in question were not in place at that time. He conceded that the specifications stated that “as soon as joists have been erected bridging shall be installed between them before the application of construction loads.” He stated, however, that it was the general custom to set joists as much as a week or two before they are bridged; that joists are not only required to be bridged but are welded at one end to the steel beam; that he agreed with the statement of the “Institute on Steel Joists” that bridging should be completed before construction loads are placed on the joists; that it is not safe to place loads on joists that have not been bridged and welded into place.

On cross-examination defendant stated that he never gave anyone permission to put a construction load on unbridged joists; that it was the custom on a job of this kind that steel erectors could not direct the bricklayers to stay off the joists; that it is the contractor who should tell the men where to work; that he had no control over the laborers employed by other subcontractors, although he could warn them not to work on unbridged joists and his men did that on this occasion.

P'amtiff testified that the six joists here involved were in place and they were working on them the Friday before he was hurt on Monday; that he had not noticed whether the joists were braced but stated that if he had looked he could have seen whether or not they were braced; that it was the custom to use joists as scaffolding in doing some of the bricklaying; that he never received any warning to get off of these particular joists; that if he had noticed that the joists were not braced he wouldn’t have worked on them; that on the morning of July 18 he started to work at 7:30; that the hodcarriers start at that time so they can have the materials on the scaffold ready for the bricklayers who start at 8; that about 9:30 “there was a ‘boom’, and the thing collapsed with us and the bricks and mortar and mortar boards and drinking water barrel piled up on us.” On cross-examination plaintiff stated that it was one of his jobs to build scaffolding and to see that it is safe. He also conceded that two days after the accident an investigator came to his home and that he told the investigator that he, plaintiff, had told his foreman that morning that the place they were working wasn’t safe and that the foreman talked to the general superintendent and told plaintiff that it was safe and plaintiff went ahead and worked thereon. Plaintiff attempted to explain those statements by saying he had been talking about the canopy they had been working on the week before.

*342 Leland Spotswood, an architect and registered engineer, was called as an expert' witness by plaintiff. He expressed the view that joists should always be bridged and welded before any construction load is placed thereon; that unbridged joists will hold considerable weight near the beam but are easily deflected near the center. He also agreed with the statement of the “Steel Joists Institute” that “as soon as joists are erected they should be bridged and fastened into place before application of loads.” He expressed the opinion that the average person in the construction field would not have known that unbridged joists were not strong. Upon cross-examination he stated that normally a steel subcontractor would have no right to issue orders to the bricklaying crew and that the general contractor should keep all workmen off of unbridged joists. He stated that if he saw some one on unbridged joists he would tell them to get off and if they did not do so he would report it to the general superintendent. This witness also 'stated that it was not unusual in the construction field to set joists and then use the equipment to set beams somewhere else before coming back and bridging the joists.

Elmer Wilson, one of the workmen in plaintiff’s crew, testified that the joists in question had been set the week before and they had worked on the boards placed thereon during that week; that it was customary to use steel joists for scaffolding and that no one had given him any warning that these joists were not safe to work on.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shaw v. Mega Industries, Corp.
406 S.W.3d 466 (Missouri Court of Appeals, 2013)
Smith v. Western Electric Co.
643 S.W.2d 10 (Missouri Court of Appeals, 1982)
Hannah v. Mallinckrodt, Inc.
633 S.W.2d 723 (Supreme Court of Missouri, 1982)
Ellis v. J. A. Tobin Construction Co.
455 S.W.2d 510 (Supreme Court of Missouri, 1970)
Downing v. Dondlinger & Sons Construction Co.
294 F. Supp. 104 (W.D. Missouri, 1968)
Bailey v. Morrison-Knudsen Company
411 S.W.2d 178 (Supreme Court of Missouri, 1967)
Barkley v. Mitchell
411 S.W.2d 817 (Missouri Court of Appeals, 1967)
Anderson v. Steurer
391 S.W.2d 839 (Supreme Court of Missouri, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
380 S.W.2d 339, 1964 Mo. LEXIS 727, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thompson-v-kroeger-mo-1964.