Dyrdal v. Enbridge (U.S.), Inc.

738 F. Supp. 2d 927, 2010 U.S. Dist. LEXIS 95954, 2010 WL 3704184
CourtDistrict Court, D. Minnesota
DecidedSeptember 14, 2010
DocketCiv. 10-1970 (RHK/LIB)
StatusPublished
Cited by1 cases

This text of 738 F. Supp. 2d 927 (Dyrdal v. Enbridge (U.S.), Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dyrdal v. Enbridge (U.S.), Inc., 738 F. Supp. 2d 927, 2010 U.S. Dist. LEXIS 95954, 2010 WL 3704184 (mnd 2010).

Opinion

MEMORANDUM OPINION AND ORDER

RICHARD H. KYLE, District Judge.

INTRODUCTION

This action arises out of a $40,000 arbitration award in favor of Petitioners Dono *928 van and Anna Dyrdal (“the Dyrdals”) and against Respondent Enbridge (U.S.), Inc. (“Enbridge”). The Dyrdals have filed a Petition asjdng the Court to modify the award by (1) adding $8,666 in interest and (2) “correcting” it to clarify that it does not include certain types of damages. They ask the Court to then confirm the so-modified award. Enbridge has responded, inter alia, by moving to dismiss for lack of subject-matter jurisdiction. For the reasons that follow, its Motion will be granted.

BACKGROUND

In 2004, the Dyrdals, farmland owners in Pennington County, Minnesota, commenced arbitration proceedings against Enbridge, a petroleum pipeline company, claiming that Enbridge’s pipelines were damaging their crops. The Dyrdals sought arbitration pursuant to a January 17, 1950 agreement between Enbridge’s predecessor and the previous owners of the farmland, which provided that pipelines would be buried such that “they will not interfere with the ordinary cultivation” of the land. (Petition Ex. A.) The pipeline company agreed to pay for “any damage to crops, fences and timber which may arise from laying, maintaining, operating or removing said lines,” and the parties agreed to arbitrate any dispute as to the amount of such damages. (Id.)

A three-arbitrator panel was selected, and on November 22, 2004, the Dyrdals filed a Statement of Claim with the panel seeking $102,958 in crop damage and “additional damage to [their] soil and land,” plus injunctive relief requiring Enbridge to lower one of its pipelines. (Id. Ex. G (emphasis added).) The panel subsequently ruled, however, that only damages to “crops, fences and timber” were within the arbitration clause and any other claim for relief was beyond its jurisdiction. Accordingly, the Dyrdals were ordered to file a new Statement of Claim listing only damages falling within these three categories. (Id. Ex. I.) In response, they filed an Amended Statement of Claim removing any claim for “additional” damages or injunctive relief; yet, the revised claim sought $105,976 (more than the initial claim), plus $40,286 in accrued interest. (Id. Ex. J.)

The matter proceeded to a hearing before the panel from November 30 to December 3, 2009. On February 4, 2010, the panel awarded the Dyrdals $40,000. (Id. Ex. L.) The award consists of a single paragraph and provides no reasoning or other basis for its result.

The Dyrdals then moved the panel to clarify that the award concerned crop damages only and excluded the “additional” damages they had sought in their initial Statement of Claim. The panel denied that Motion by Order dated March 24, 2010, stating that the award “requires no such clarification.” (Id. Ex. N.) In its Order, however, the panel did, in fact, clarify the scope of its award. Although it recognized that its jurisdiction extended only to damages for crops, fences, and timber, it expressly noted that the Dyrdals had proffered at the arbitration hearing evidence of their “additional” damages (which concerned soil compaction, routing, ditch construction, and other items), all of which “allegedly manifested in crop damage.” (Id.) Hence, the panel stated that its award “contemplated all matters underlying and incidental to ultimate damage to crops[,] which damage was reflected in the dollar amounts of crop loss sought by [the] Dyrdals and granted in part and denied in part by the ... award.” (Id.) In other words, the panel appears to have considered in its award the “additional” items for which the Dyrdals initially had sought damages in their November 2004 Statement of Claim.

*929 On May 5, 2010, the Dyrdals filed the instant Petition seeking modification of the award (1) to reflect that it does not include any “additional” damages, which were ostensibly beyond the panel’s jurisdiction, and (2) to include pre-arbitration interest of $8,666, which the panel purportedly failed to award. As “corrected,” they ask the Court to confirm the award and enter judgment in their favor for $48,666.

The following day, the Court issued an Order (Doc. No. 6) sua sponte raising concerns about the existence of subject-matter jurisdiction over the Petition. In particular, the Court noted that the Petition purported to invoke jurisdiction under the Federal Arbitration Act (the “FAA”), 9 U.S.C. § 1 et seq., “but it has long been recognized that the FAA ‘does not create any independent federal-question jurisdiction.’ Moses H. Cone Mem’l Hosp. v. Mercury Constr. Corp., 460 U.S. 1, 25 n. 32, 103 S.Ct. 927, 74 L.Ed.2d 765 (1983); accord, e.g., Advance Am. Servicing of Ark., Inc. v. McGinnis, 526 F.3d 1170, 1173 (8th Cir.2008).” (Doc. No. 6 at 3.) Stated differently, “even when a petition is brought under the Federal Arbitration Act[,] ... a petitioner seeking to confirm or vacate an arbitration award in federal court must establish an independent basis for federal jurisdiction. Carter v. Health Net of Cal., Inc., 374 F.3d 830, 833 (9th Cir.2004) (emphasis added).” (Id.) The Petition, however, asserted no federal claim, and the amount requested was less than $75,000, the threshold for diversity jurisdiction.

In light of these concerns, the Court considered ordering the parties to brief whether subject-matter jurisdiction existed. Given the relatively small amount of the arbitration award, however, the Court ordered them instead to conduct an expedited settlement conference. Before that settlement conference occurred, the Dyrdals filed an “Amended Petition/Complaint for Declaratory Judgment and Injunctive Relief.” (See Doc. No. 8.) While continuing to seek modification and then confirmation of the arbitration award, they also purported to add in this newly filed document a claim under the Hazardous Liquid Pipeline Safety Act of 1979 (“HLPSA”), Pub.L. No. 96-129, 93 Stat. 1003 (1979). 1 The Dyrdals apparently filed this Amended Petition (with a federal claim) to allay the Court’s jurisdictional concerns.

On June 14, 2010, then-Chief Magistrate Judge Erickson 2 conducted the Court-ordered settlement conference, which proved unsuccessful. As presaged by the Court’s May 6, 2010 Order, however, Enbridge has now moved to dismiss for lack of subject-matter jurisdiction. In response, the Dyrdals have conceded that they improperly added their claim under the HLPSA, and they have agreed to dismiss that claim without prejudice. (Pet. Mem.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
738 F. Supp. 2d 927, 2010 U.S. Dist. LEXIS 95954, 2010 WL 3704184, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dyrdal-v-enbridge-us-inc-mnd-2010.