D.W. Wilburn, Inc. v. H&H Painting, LLC

Court of Appeals of Kentucky·Decided June 30, 2022·No. 2020 CA 000919·Unknown

Opinion

RENDERED: JULY 1, 2022; 10:00 A.M.

TO BE PUBLISHED

Commonwealth of Kentucky

Court of Appeals

NO. 2020-CA-0919-MR

D.W. WILBURN, INC. APPELLANT

APPEAL FROM FAYETTE CIRCUIT COURT v. HONORABLE LUCY A. VANMETER, JUDGE ACTION NO. 10-CI-05707

H&H PAINTING, LLC APPELLEE

OPINION

AFFIRMING

** ** ** ** **

BEFORE: COMBS, JONES, AND MCNEILL, JUDGES. JONES, JUDGE: D.W. Wilburn, Inc. (“Wilburn”), a general contractor, appeals an opinion and order of the Fayette Circuit Court which awarded damages in a bench trial to Wilburn’s former subcontractor, H&H Painting, LLC (“H&H”). After a thorough review of the record and the law, we affirm.

I. BACKGROUND

This dispute has a lengthy background and procedural history, and this is the third time the matter has been appealed to this Court. From approximately 2005 until 2010, H&H contracted with Wilburn to provide commercial painting services on several projects for which Wilburn served as the general contractor. Relevant to the current dispute, H&H provided painting services for three Wilburn projects: Leestown Middle School (“Leestown”), Morehead State University Center for Health, Education, and Research (“Morehead”), and the Caudill Middle School (“Caudill”). At some point in 2009, the working relationship between H&H and Wilburn became contentious. H&H stopped its work on the Leestown and Morehead projects on March 5, 2010, allegedly because Wilburn had not paid for the work it performed. Hoover v. D.W. Wilburn, Inc. (“Wilburn I”), Nos. 2013-CA-000835-MR, 2013-CA-000884-MR, 2014 WL 5064459, at *1 (Ky. App. Oct. 10, 2014), as modified (Jan. 9, 2015).

H&H subsequently filed suit against Wilburn in Fayette Circuit Court, asserting breach of contract, intentional infliction of emotional distress, intentional interference with a contractual relationship, and restraint of trade pursuant to KRS1 367.175. Wilburn I, 2014 WL 5064459, at *1. When the matter went to trial in January 2013, the trial court granted a directed verdict to Wilburn on all counts of

1 Kentucky Revised Statutes.

the complaint except for the breach of contract claim. Id. After finding that H&H had substantially performed on two of the three contracts, the jury returned a verdict in H&H’s favor regarding the Morehead and Leestown projects, awarding $83,086.00 and $38,800.00 on each project respectively. Id. The jury declined to award damages on the Caudill project after it determined that neither party substantially performed its duties. (Record (“R.”) at 576, 581.)

After the jury’s verdict, Wilburn moved the trial court for judgment notwithstanding the verdict, asserting H&H had failed to submit sufficient proof of its damages. The trial court granted the motion and set aside the jury’s verdict. Wilburn I, 2014 WL 5064459, at *1. In the first appeal, we held that the trial court erred when it vacated the verdict in toto where the jury found that the contract was breached, and that instead of disallowing all the damages, the trial court should have held a new trial to determine the amount of damages owed to H&H. Id. at *7.

Upon remand, the trial court conducted a second jury trial on December 18-19, 2017. Only two witnesses testified: James Hoover, one of the members of H&H, and Kimberly Blethen, an accountant employed by Wilburn. At the conclusion of the trial, the jury determined that H&H was entitled to no damages, and the trial court entered its judgment to that effect. Unfortunately, the trial court had “erroneously instructed the jury to determine whether H&H was entitled to damages.” H&H Painting, LLC v. D.W. Wilburn, Inc. (“Wilburn II”),

No. 2018-CA-000283-MR, 2019 WL 2070458, at *2 (Ky. App. May 10, 2019). Upon appeal, we held the instruction violated the law-of-the-case doctrine, as the issue of whether H&H was entitled to damages had already been determined at trial and upheld in the first appeal. Id. We reversed and remanded for a new trial, again specifying that the trial should be upon the sole issue of the amount of damages owed to H&H “for its work on the Leestown and Morehead projects.” Id. at *3.

By the time the case returned to the trial court for its third attempt at a resolution, the judicial landscape had shifted. The former presiding judge had retired, and the case now fell to Judge Lucy A. VanMeter. In its pretrial order entered on February 13, 2020, the trial court ordered the parties to submit simultaneous memoranda addressing the following items:

a. Plaintiff shall set forth the claims to be tried, an itemization of damages and set forth its theory of liability;

b. Defendant shall set forth its theory of the defense;

c. Each party shall identify the witnesses they intend to call at the trial of the case;

d. Each party shall set out any issues of law or evidence to be addressed by the Court prior to trial;

e. Each party shall tender proposed jury instructions;

f. Each party shall state whether they consent to a bench trial or wish to have the case tried by a jury;

g. Any other matters affecting the trial of the case[.]

(R. at 1083.) The trial court also directed each party to submit a response to the opposing party’s memorandum. In its memorandum, H&H asserted it was owed $97,758.89 for its work on the Morehead project, and $32,780.00 for the Leestown project. (R. at 1085.) For proof of these damages, H&H attached copies of pay requests it had submitted to Wilburn. (Id.) H&H also asserted that these damages were liquidated; therefore, it was entitled to both prejudgment and postjudgment interest from a date of the trial court’s discretion. (R. at 1085, 1092-95.)

In the context of the matter currently before this Court, Wilburn’s memorandum and response warrant our special attention. Wilburn’s memorandum stated, “H&H has yet to prove its damages resulting from the breach. That is the nature of Wilburn’s defense.” (R. at 1155.) The Wilburn memorandum further explained that the nature of its proof was to show that Wilburn “introduced proof as to what Wilburn was required to spend to complete H&H’s work, not for the purpose of attempting to recover any part of those expenditures, but instead to prove that H&H was not as far along as it contended.” (Id.) Additionally, the Wilburn memorandum asserted that it could identify “no other legal issues other than a ruling on Wilburn’s entitlement to setoff any overpayments made to H&H on the Caudill project.” (R. at 1156.) In its response to H&H’s memorandum, Wilburn contended H&H had not, thus far, proven it was entitled to any damages,

and so these damages could not be liquidated. (R. at 1162.) Wilburn then reiterated its argument that the costs to complete the projects were not submitted as a set-off, but rather to show that H&H had not completed as much work as it claimed. (R. at 1163.) Wilburn again definitively stated that “it should be entitled to a setoff for the amounts overpaid on Caudill. This is the only setoff claim Wilburn has made.” (Id.)

Following submission of the memoranda and responses, the parties agreed to a bench trial wherein the trial court would render judgment based on the evidence and testimony presented during the December 2017 jury trial. On May 8, 2020, the trial court issued its findings of fact, conclusions of law, and judgment. (R. at 1287.) The trial court noted the extensive history of the case and confined itself to considering only the amounts H&H should be compensated for Wilburn’s breach of the Leestown and Morehead contracts. (R. at 1289.) Of the two witnesses presented during the trial, the trial court specifically noted that Mr. Hoover was present at the job sites and was able to testify from personal knowledge about the amount of labor and materials H&H provided, the weekly payroll and pay requests he sent to Wilburn, and the percentage of work H&H completed. In contrast, Ms. Blethen admitted she was not at the job sites, had no knowledge regarding the percentage of work H&H completed, and had no direct knowledge regarding the quality of H&H’s work. (R. at 1290.)

Free access — add to your briefcase to read the full text and ask questions with AI

D.W. Wilburn, Inc. v. H&H Painting, LLC, (Ky. Ct. App. 2022).

D.W. Wilburn, Inc. v. H&H Painting, LLC (D.W. Wilburn, Inc. v. H&H Painting, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Reliable Mechanical, Inc. v. Naylor Industrial Services, Inc.
125 S.W.3d 856 (Court of Appeals of Kentucky, 2004)
Fischer v. Fischer
197 S.W.3d 98 (Kentucky Supreme Court, 2006)
Bowling v. Natural Resources & Environmental Protection Cabinet
891 S.W.2d 406 (Court of Appeals of Kentucky, 1995)
Nucor Corp. v. General Electric Co.
812 S.W.2d 136 (Kentucky Supreme Court, 1991)
Fratzke v. Murphy
12 S.W.3d 269 (Kentucky Supreme Court, 1999)
Commonwealth v. Anderson
934 S.W.2d 276 (Kentucky Supreme Court, 1996)
Eiland v. Ferrell
937 S.W.2d 713 (Kentucky Supreme Court, 1997)
McCloud v. Commonwealth
286 S.W.3d 780 (Kentucky Supreme Court, 2009)
Tennill v. Talai
277 S.W.3d 248 (Kentucky Supreme Court, 2009)
Moore v. Asente
110 S.W.3d 336 (Kentucky Supreme Court, 2003)
Brown v. Commonwealth
313 S.W.3d 577 (Kentucky Supreme Court, 2010)
Roadway Express, Inc. v. Don Stohlman & Associates, Inc.
436 S.W.2d 63 (Court of Appeals of Kentucky (pre-1976), 1968)
Owens-Corning Fiberglas Corp. v. Golightly
976 S.W.2d 409 (Kentucky Supreme Court, 1998)
Columbian Fuel Corporation v. Skidmore
214 S.W.2d 761 (Court of Appeals of Kentucky (pre-1976), 1948)
Oakley v. Oakley
391 S.W.3d 377 (Court of Appeals of Kentucky, 2012)
Smith v. Commonwealth
410 S.W.3d 160 (Kentucky Supreme Court, 2013)
Ford Contracting, Inc. v. Kentucky Transportation Cabinet
429 S.W.3d 397 (Court of Appeals of Kentucky, 2014)
Rumpel v. Rumpel
438 S.W.3d 354 (Kentucky Supreme Court, 2014)
Smothers v. Baptist Hospital East
468 S.W.3d 878 (Court of Appeals of Kentucky, 2015)