Durland v. San Juan County

298 P.3d 757, 174 Wash. App. 1
Court of Appeals of Washington·Decided October 29, 2012·No. No. 67429-3-I·Published·Cited by 24 cases

Opinion

Spearman, A.C.J.

¶1 — Under the Land Use Petition Act (LUPA), chapter 36.70C RCW, a petition challenging a land use decision must be filed within 21 days of the issuance of the land use decision. Furthermore, a party may not collaterally challenge a land use decision for which the appeal period has passed through a challenge to a subsequent land use decision. The main question presented in this appeal is whether compliance plans between respondent San Juan County (County) and respondents Wesley Heinmiller and Alan Stameisen (Heinmiller and Stameisen will be referred to collectively as “Heinmiller”) were “land use decisions” under LUPA. If they were, the appellants, Michael Durland, Kathleen Fennel, and Deer Harbor Boatworks (collectively [6] Durland), are barred from raising certain issues in their LUPA petition because they did not bring a LUPA petition challenging the compliance plans within 21 days. Other issues on appeal and cross appeal are whether the County properly calculated the pitch for a proposed roof on Heinmiller’s barn, whether the County properly calculated the “living area” of an alternative dwelling unit (ADU) constructed inside the barn, and whether the superior court erred in awarding statutory costs to Durland.

¶2 We hold that the compliance plans in this case were not land use decisions because they were not final determinations that left nothing open to further dispute. We also hold that while the County did not err in calculating roof pitch because the relevant code provision did not specify how to measure pitch, the County did err in calculating living area because the relevant code provisions were not ambiguous and did not allow for exclusion of areas with a ceiling height below five feet. We find no abuse of discretion in the award of statutory costs to Durland.

FACTS

¶3 Durland owns property in Deer Harbor on Oreas Island, in San Juan County, which is currently used as a boatyard and marina. Heinmiller’s predecessor in interest, William G. Smith, owned the property adjacent to and south of the Durland property (Heinmiller property). In 1981, the County issued a building permit for a storage barn to Smith. The permit approved a barn that was to be built 10 feet from the property line shared with the Durland property.1 A barn was constructed that year. In 1990, Durland sought a conditional use permit and a shoreline permit. A property line survey revealed that the barn on the Heinmiller property was in fact located only 1.4 feet from the property line. To address this issue, Durland and Smith [7] executed a “Boundary Line Agreement and Easement” that prevented Durland from building within 20 feet of the barn.2

¶4 Around 1995, Heinmiller purchased the property from Smith. In 1997, he converted a portion of the barn to an ADU but did not secure any building or shoreline permits for this work, in violation of San Juan County Code (SJCC) requirements. In 2008, Heinmiller filed an application for an upland conditional use permit, seeking authorization to use the ADU as a vacation rental unit. Because of the application, the County became aware of the ADU conversion. In February 2008, the County issued a “notice of correction” to Heinmiller, requiring the ADU to be demolished.3

¶5 Heinmiller negotiated with the County regarding the notice of correction. The County agreed to allow him to seek after-the-fact permits for the ADU before requiring demolition. Accordingly, on April 25, 2008, Heinmiller and the County executed an agreed compliance plan. The compliance plan included a section titled “Correction of Violations and Compliance Schedule” that outlined what actions were necessary to bring the property into compliance with the SJCC. It also stated, in the “Background” section, that the County recognized that the private restrictive covenant brought the barn into conformance with the 10-foot setback requirement that applied when the barn was constructed.

¶6 One year later, on April 28, 2009, the County and Heinmiller executed a supplemental agreed compliance plan (supplemental compliance plan; both plans will be referred [8] to collectively as “compliance plans”). The supplemental compliance plan stated that Heinmiller could avoid the need for a shoreline substantial development permit and a conditional use permit if certain steps were taken, including reducing the height of the barn to 16 feet.4 Heinmiller planned to reduce the height of the barn by reconfiguring the peak of the gable roof to create a flat portion.

¶7 On June 4, 2009, Durland filed an administrative appeal of the supplemental compliance plan with the County. In a June 8, 2009 letter to Durland, the county planning director wrote:

I write to inform you that there is no administrative appeal process for a neighbor to challenge a Compliance Plan or Amended Compliance Plan. A Compliance Plan is a code enforcement tool that is available to the Administrator to assure compliance with the County Code and is authorized by SJCC 18.100.040(D). Code Enforcement is a matter between the County and the offender and is not subject to administrative appeal by a neighbor.

Clerk’s Papers (CP) at 3-4. On August 13, 2009, the county hearing examiner dismissed Durland’s appeal on the basis that it was filed one day late.

¶8 Heinmiller applied for a building permit, a change-of-use permit, and an ADU permit as contemplated by the compliance plans.5 The County approved the permits on November 23 and 24, 2009. On December 11, Durland filed [9] an administrative appeal challenging the permits. He raised the following issues:

1. Whether the permits are consistent with regulations regarding land developed in violation of local regulations.
2. Whether the barn complies with setback requirements.
3. Whether the barn complies with building width limitations for properties with shoreline frontage.
4. Whether the barn complies with waterfront setback requirements for accessory structures.
5. Whether the appropriate shoreline approvals, such as a shoreline conditional use permit, substantial development permit, or shoreline exemption have been obtained.
6. Whether the ADU complies with the living area limitation of 1,000 square feet.
7. Whether the barn complies with roof pitch requirements in the Deer Harbor Hamlet Plan.

See CP at 68-69.

Free access — add to your briefcase to read the full text and ask questions with AI

Durland v. San Juan County, 298 P.3d 757, 174 Wash. App. 1 (Wash. Ct. App. 2012).

298 P.3d 757 (Durland v. San Juan County) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Ladder Properties Llc, Et Ano V. City Of Snoqualmie
Court of Appeals of Washington, 2026
Terry Miller v. City of Richland
Court of Appeals of Washington, 2025
H4IT Properties, LLC v. Chelan County
Court of Appeals of Washington, 2024
Medical Lake Cemetery Ass'n v. Spokane County
Court of Appeals of Washington, 2023
Klickitat Land Preservation Fund v. Klickitat County
Court of Appeals of Washington, 2023
State v. Arbogast
506 P.3d 1238 (Washington Supreme Court, 2022)
Paul & Jennifer Clark, V. City Of Bainbridge Island
Court of Appeals of Washington, 2021
Scott Blomenkamp v. City Of Edmonds
Court of Appeals of Washington, 2019
James Chumbley v. Snohomish County
386 P.3d 306 (Court of Appeals of Washington, 2016)
Michael Durland v. San Juan County
Court of Appeals of Washington, 2016
State Of Washington, V Beckie L. Corey
Court of Appeals of Washington, 2015
In Re The Marriage Of: Victor M. Zandi, V Deanna M. Zandi
357 P.3d 65 (Court of Appeals of Washington, 2015)
Race Track, Llc v. King County
Court of Appeals of Washington, 2014
Shawn Greenhalgh, James Pfaff, V State Dept Of Corr
Court of Appeals of Washington, 2014
Greenhalgh v. Department of Corrections
324 P.3d 771 (Court of Appeals of Washington, 2014)