Durfee v. Ocean State Steel, Inc.

636 A.2d 698, 1994 R.I. LEXIS 13, 1994 WL 20707
CourtSupreme Court of Rhode Island
DecidedJanuary 26, 1994
Docket93-507-Appeal
StatusPublished
Cited by40 cases

This text of 636 A.2d 698 (Durfee v. Ocean State Steel, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Durfee v. Ocean State Steel, Inc., 636 A.2d 698, 1994 R.I. LEXIS 13, 1994 WL 20707 (R.I. 1994).

Opinion

OPINION

MURRAY, Justice.

This case comes before us on the appeal of the defendant, Ocean State Steel, Inc. (Ocean State), an East Providence-based steel-manufacturing plant, from a Superior Court order finding it in contempt of a prior court order entered into by consent of both Ocean State and the Rhode Island Department of Environmental Management (DEM).

The facts that give rise to this dispute involve a consent agreement signed by the parties. The factors that led to the drafting *700 of that agreement are as follows: In December 1989 DEM notified Ocean State of its air-pollution violations. In January 1990 Ocean State submitted a plan to DEM that called for a program to remediate emissions, including the installation of certain air-pollution-control equipment. In April 1990 Ocean State notified DEM that the air-pollution-eontrol equipment would be installed and operational by June 1990. During May 1990 Ocean State informed DEM that it was unlikely that the air-pollution-control equipment would be operational until July 1990. Subsequently DEM issued a notice of violation to Ocean State, ordering it to achieve compliance with certain state pollution-control regulations by installing and making operational the air-pollution-control equipment by June 30, 1990.

In July 1990 DEM and Ocean State executed an administrative consent agreement in which Ocean State agreed to comply with specific state pollution-control regulations by having the air-pollution-control equipment operational by July 81,1990. The agreement stated in pertinent part that

“[i]f the air pollution control equipment is not operational by 31 July 1990 Ocean State shall cease operations that contribute to violations of Regulations 1, 3, and 7 until the air pollution control equipment is operational and in compliance with said regulations. ” (Emphasis added.)

In November 1990 DEM filed a complaint and request for injunctive relief against Ocean State to enforce the terms of the consent agreement. The complaint asserted that Ocean State had failed to install numerous pollution-control devices and had been emitting air contaminants from its East Providence location since November 1989. The DEM contended that these emissions violated the Rhode Island Clean Air Act, G.L.1956 (1989 Reenactment) chapter 23 of title 23, and the Rhode Island Department of Environmental Management Division of Air and Hazardous Materials Air Pollution Control Regulations 1, 3, and 7 (regulations) promulgated pursuant to the Rhode Island Clean Air Act. 1

The consent agreement was amended and adopted by the court in December 1990. That order provided in part that “[njothing in this order [absent certain modifications of air-pollution-control equipment installation dates] shall alter and change the rights, duties and obligations of the parties arising under the administrative [c]onsent [a]greement.” The order was further amended in July 1991 and January 1992. The final amended order, entered on January 7, 1992, provided that the two previous orders entered by the Superior Court on December 6, 1990, and July 22, 1991, “remain in full force and effect.”

The final order also required (1) that DEM issue an air-pollution-eontrol permit (permit) to Ocean State, (2) that Ocean State install all pollution-control equipment by August 15, 1992, (3) that if Ocean State failed to comply with the regulations or the terms of the permit, it was required to implement additional measures as outlined in an attached exhibit and submit a proposed schedule for the implementation of those measures, and (4) that Ocean State install an air-pollution monitoring station and allow DEM access to the station. An approval letter from DEM was attached to the order along with a list of permit conditions and emission limitations. These air-pollution-control permit conditions and limitations were separated into five distinct categories: (1) operating conditions and emission limitations (establishing opacity, production, particle emission, and gas-temperature limitations), (2) monitoring requirements (establishing monitoring requirements for specific air-pollution-control equipment), (3) record keeping and reporting (directing Ocean State to forward at least three different types of monthly air-pollution monitoring reports to DEM), (4) stack testing (directing Ocean State to stack-test with the appropriate notification, approval, and observation of *701 the stack-testing procedure by DEM), and (5) other requirements (outlining specific guidelines for the implementation and the operation of other miscellaneous pollution-control equipment). Our review of this addendum shows that Ocean State incurred very clear and specific responsibilities.

Ocean State did not comply with the final amended order, and in June 1993 DEM filed a petition to adjudge Ocean State in contempt. The DEM alleged that Ocean State had failed to comply with the final amended order, the regulations, and the terms of the permit. The DEM sought (1) a temporary injunction ordering a cessation of all steel production, (2) immediate compliance by Ocean State with the consent order, the Rhode Island Clean Air Act, and the regulations, and (3) miscellaneous fines and attorney’s fees.

At the outset we note that our review is limited to what occurred during the contempt hearing and therefore we do not specifically review any prior proceeding. The testimony at the July 1993 contempt hearing revealed the following: Terry Tuchon, an employee in the Division of Air Resources of DEM, testified that Ocean State was in violation of the opacity limitations as set forth in the permit, approximately sixty times from January to April 1993. Douglas McVay (McVay), a supervising engineer for DEM, testified that Ocean State had not performed the mandated “stake testing” as required by the permit. 2 McVay further testified that Ocean State had also failed to complete other pollution-monitoring activities and failed to submit timely reports to DEM as required by the permit.

McVay stated that the steel production process generates approximately thirty-nine pounds of steel dust for every ton of steel that is produced. In the air-pollution-control permit, Ocean State represented that its equipment would capture approximately thirty-eight pounds of the steel dust produced. In actuality, however, the equipment was collecting only twenty pounds of steel dust per ton of steel produced. The unfiltered remainder was being released into the atmosphere. McVay calculated that approximately 600,000 tons of steel dust had been emitted into the atmosphere between August and December 1992.

Ferguson Porter (Porter), president of Ocean State, testified that Ocean State expended $900,000 on emission-caption equipment. He admitted that he was disappointed with the filtering and performance capabilities of the emission-caption equipment. Porter stated that without any prompting from DEM, Ocean State attempted modifications to increase the capabilities of the emission-caption equipment. Porter testified that Ocean State chose not to perform the required stake testing because Ocean State realized that it would have failed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re N.D.
Supreme Court of Rhode Island, 2024
In re N.B., 22-75 (April 15, 2024)
Supreme Court of Rhode Island, 2024
Bennett v. Steliga
Supreme Court of Rhode Island, 2024
Charles A. Anton v. Philippe L. Houze
Supreme Court of Rhode Island, 2022
Patricia Botelho v. City of Pawtucket School Department
130 A.3d 172 (Supreme Court of Rhode Island, 2016)
Proulx v. Brookdale Living Communities Inc.
88 F. Supp. 3d 27 (D. Rhode Island, 2015)
Pearson v. Pearson
11 A.3d 103 (Supreme Court of Rhode Island, 2011)
Levinger v. Providence Watch Hospital
Superior Court of Rhode Island, 2010
Toegemann v. Rich
Superior Court of Rhode Island, 2010
Ayriyan v. Ayriyan
994 A.2d 1207 (Supreme Court of Rhode Island, 2010)
Sargent v. Sargent
Superior Court of Rhode Island, 2009
Now Courier, LLC v. Better Carrier Corp.
965 A.2d 429 (Supreme Court of Rhode Island, 2009)
City of Cranston v. Labor Relations Board
Superior Court of Rhode Island, 2008
State v. Lead Industries, Ass'n, Inc.
951 A.2d 428 (Supreme Court of Rhode Island, 2008)
Rodrigues v. DePasquale Building & Realty Co.
926 A.2d 616 (Supreme Court of Rhode Island, 2007)
Gorman v. Gorman
883 A.2d 732 (Supreme Court of Rhode Island, 2005)
Bucci v. Anthony, 94-2080 (r.I.super. 2004)
Superior Court of Rhode Island, 2004

Cite This Page — Counsel Stack

Bluebook (online)
636 A.2d 698, 1994 R.I. LEXIS 13, 1994 WL 20707, Counsel Stack Legal Research, https://law.counselstack.com/opinion/durfee-v-ocean-state-steel-inc-ri-1994.