Duplan Silk Co. v. Spencer

115 F. 689, 53 C.C.A. 321, 1902 U.S. App. LEXIS 4238
CourtCourt of Appeals for the Third Circuit
DecidedMay 7, 1902
StatusPublished
Cited by14 cases

This text of 115 F. 689 (Duplan Silk Co. v. Spencer) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Duplan Silk Co. v. Spencer, 115 F. 689, 53 C.C.A. 321, 1902 U.S. App. LEXIS 4238 (3d Cir. 1902).

Opinion

GRAY, Circuit Judge.

This was an action of trover, called under the Pennsylvania practice act of 1887 an action of trespass. It was brought by the defendant in error, as trustee in bankruptcy of the estate of Bennett & Rothrock, who were contractors and builders, against the Duplan Silk Company, charging the conversion of certain chattels, consisting principally of lumber, iron work, nails, cement, brick and sundry builder’s utensils, of which a complete schedule is given in plaintiff’s statement. There is little or no dispute about the essential facts-in the case, as disclosed by the evidence. They are substantially as follows:

Bennett & Rothrock were builders, and, as such, entered into a written contract with the Duplan Silk Company, bearing date August 30, 1899, to erect a silk mill for the defendant at Hazleton, Pa., providing all materials and performing the work mentioned in the specifications and shown in the drawings prepared by the architect. By this contract, it was provided that the sum to be paid by the owner to the contractor, for said work and materials, should be $76,000, payable in installments as the work progressed to' certain specified stages, the first installment being $5,000 and the remaining ones $10,000 each. On the same day, a supplemental contract, according to the form of contract recommended for general use by the American Institute of Architects, was executed between the parties.

About December 15, 1899, when the excavations and foundation walls and piers had been completed, and the brick walls partly built, work on the building was lagging. Although, according to the terms of the contract, only the first installment of $5,000 had become due, and it had been paid, Rothrock, one of the contractors, came to Emory J. Lipps, general manager of the Duplan Silk Company, and through whom, as its agent, the building contract was made, and asked whether certain moneys could not be advanced beyond what the contract called for. Lipps told him that, personally, he could not advance any money, but that if he presented his case to the board of directors of the Duplan Silk Company, they might be willing to do so. Accordingly, on December 16th, there was a meeting in New York City, between Rothrock and those representing the company, at which Rothrock stated that he was very short of money, and that unless he could get some from the company in advance, he could not pay for the material he had ordered, and the men would put him into bankruptcy. They had already made him a payment of $5,000 and no [691]*691other installment was then due. The testimony of Lipps, as to the transaction between the parties, proceeds as follows:

“We had a meeting in New York City, and upon the promise of Mr. Rothroek that he would at once put more men at work and continue the work, if we advanced him $15,000, he would at once go to work and complete the building. Of course he could not complete it in the time that was specified, but he claimed that he had so much material on the ground that we were fully covered by advancing him that money. We knew that material was there, and we consequently gave him the $15,000. That was on December 16th. * * * Q. So the amount you had paid to the fifteenth of December was 820,000, although he was entitled to but $5,000? A. Yes, sir; he was entitled to $5,000 when the excavations were done, and $10,000 when the brick walls were complete. The brick wall is only a very small part of the building, because the building is a one-story building’. The valuable part is the interior work. We had advanced him $5,000, and we advanced him $15,000 more. He argued that we would be perfectly safe in doing so, as he had the materials on the ground.”

After this money was advanced, work was continued for a short time, and by Christmas, or a day or two thereafter, it was practically abandoned. On the 13th of January, 1900, Bennett & Rothroek, on their own petition, were adjudicated bankrupts, and W. H. Spencer, defendant in error, was duly appointed and qualified as trustee of their estate. The chattels in controversy were scheduled among their assets, and there were numerous judgments against them, and executions issued thereon, when the petition was filed and the adjudication made.

On January 11, 1900, certain letters from the Duplan Silk Company were sent to and received by Bennett & Rothroek, and, as they appear in the record, are as follows:

“South Bethlehem, January 11, 1900.
“Messrs. Bennett & Rothroek, Williamsport, Pa. — Gentlemen: We hereby notify you that oh account of your failure or inability to prosecute the work on our silk-mill building at Hazleton, Pa., according to our contract, dated August 30, 1899, we hereby terminate the said contract, and we will enter and take possession of above-named premises on Monday, January 15, 1900, for the purpose of completing the work comprehended under said contract in accordance with provisions made therein.
“Yours truly, Duplan Silk Company,
“E. J. Lipps, General Manager.”
“South Bethlehem, January 11, 1900.
“Duplan Silk Company, New York City, N. Y.: I, the undersigned, acting as overseer and contractor for the architects of the Duplan Silk Company building, in course of construction at Hazleton, Pennsylvania, do hereby certify that the contractors, Bennett & Rothroek, of Williamsport, Pa., through their failure since January 8, 1900, to prosecute the work on said buildings in accordance with their contract with said Duplan Silk Company, under date of August 30, 1899, have given just cause for the owners to terminate said contract as provided for therein. E. J. Lipps.”
“South Bethlehem, January 11, 1900.
“Messrs. Bennett & Rothroek, Williamsport, Pa. — Dear Sirs: Inclosed we send you a notification forwarded to us by Mr. E. J. Lipps, who acts as contractor and overseer for the architects in the construction of the mill at Hazleton. Yours truly, Duplan Silk Company.”

It is admitted by counsel for plaintiff in error that these letters were intended to be pursuant to the fifth article of the supplemental contract, which provides as follows:

[692]*692“Art. 5.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dannel v. Wilson-Weesner-Wilkinson Co.
109 F.2d 364 (Sixth Circuit, 1940)
Middle Georgia Lumber Co. v. Hunt
186 S.E. 714 (Court of Appeals of Georgia, 1936)
In re Sullivan
21 F.2d 834 (D. Massachusetts, 1927)
Duncan v. Clary
254 P. 386 (Supreme Court of Kansas, 1927)
Zehner v. Southern Surety Co.
272 F. 954 (Third Circuit, 1921)
In re Puget Sound Engineering Co.
270 F. 353 (W.D. Washington, 1920)
Davidson & Case Lumber Co. v. Anderson
187 P. 872 (Supreme Court of Kansas, 1920)
In re P. J. Sullivan Co.
254 F. 660 (Second Circuit, 1918)
In re P. J. Sullivan Co.
247 F. 139 (N.D. New York, 1918)
MacEvoy v. E. & Z. Van Raalte, Inc.
242 F. 251 (Third Circuit, 1917)
Sullivan v. Myer
137 Tenn. 412 (Tennessee Supreme Court, 1916)
In re Shelly
235 F. 311 (D. New Jersey, 1916)
In re A. P. Wilson & Co.
176 F. 652 (E.D. Pennsylvania, 1910)
Atchison, T. & S. F. Ry. Co. v. Hurley
153 F. 503 (Eighth Circuit, 1907)

Cite This Page — Counsel Stack

Bluebook (online)
115 F. 689, 53 C.C.A. 321, 1902 U.S. App. LEXIS 4238, Counsel Stack Legal Research, https://law.counselstack.com/opinion/duplan-silk-co-v-spencer-ca3-1902.