Davidson & Case Lumber Co. v. Anderson

187 P. 872, 106 Kan. 213, 1920 Kan. LEXIS 488
CourtSupreme Court of Kansas
DecidedFebruary 7, 1920
DocketNo. 22,128
StatusPublished

This text of 187 P. 872 (Davidson & Case Lumber Co. v. Anderson) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Davidson & Case Lumber Co. v. Anderson, 187 P. 872, 106 Kan. 213, 1920 Kan. LEXIS 488 (kan 1920).

Opinion

The opinion of the court was delivered by

Johnston, C. J.:

This was an action of replevin brought by the Davidson and Case Lumber Company to recover the possession of the forms and material used in the construction of a concrete building, the right to possession being claimed under a chattel mortgage executed to the lumber company by R. A. Anderson and his wife. The Widmer Engineering Company claimed the right of possession under a provision of a building contract. It was found by the jury that the plaintiff was entitled to the possession of the property, and a judgment against the engineering company which had retained possession of the property was rendered, awarding the plaintiff damages in the surmof $4,100. The engineering company appeals.

It appears that a contract was let to the Selden-Breck Construction- Company to erect a ten-story hotel at Wichita, and that the company sublet the furnishing and installing of the forms and frames into which the concrete was to be poured, to the engineering company, and that company in turn sublet the furnishing and installation of the forms to R. A. Anderson. The contract with Anderson was executed on September 13, 1917. Shortly afterwards Anderson purchased the lumber and material for the forms from the lumber company, and on November 7, 1917, he began the work of making and installing the forms for the concréte construction. This work was continued until he had reached the fourth story, following the ordinary plan that when the concrete for the first story was poured and had hardened, the forms were removed and used for the story above. On March 2, 1918, and while at work on the fourth story, Anderson found himself in financial stress and unable to pay his workmen or go forward with the work. At that time he was owing the lumber company $3,700 for material used in his forms, and also $400 to a bank, which he [215]*215had. borrowed to carry on the work. The claim of the bank was assigned to the lumber company, and on March 5, 1918, Anderson executed a chattel mortgage on the forms and appliances he was using in the work to the lumber company. On the evening of March 2,.after the engineering company had been informed of Anderson’s default, it caused a notice to be served upon him to the effect that if Anderson did not proceed with the work, the engineering company would at the end of three days cause it to be performed by others, at the expense of Anderson. The lumber company served notice upon the Selden-Breck company and the engineering company that it deemed itself insecure and demanded possession of the property under its mortgage. The engineering company claimed the right to the possession of the same under its contract with Anderson, and refused to deliver possession. The present action was then brought, and the engineering company gave a redelivery bond, retaining possession of the forms and material, and has continued to use them throughout the construction of the hotel. The right to the possession of the property was the principal question involved in the controversy, and with it the extent of damages sustained by the plaintiff because of the detention and use of the property by the engineering company. In connection with the general verdict that the lumber company was entitled to the possession of the forms and appliances, the jury returned special findings to the effect that Anderson was in the possession of the property at the time the chattel mortgage was executed, that the lumber company had a special ownership in the property to the extent of $4,268.28, and found that the property had deteriorated in value since the commencement of the action, to the extent of $4,100. It is insisted by the engineering company that it had-a superior right to the possession of the property under section five of its contract with Anderson, which is as follows:

“5. Should the subcontractor at any time refuse or neglect to supply a sufficiency of properly skilled workmen, or of materials of the proper-quality, or fail in any respect to prosecute the work with promptness and diligence, or fail in the performance of any of the agreements herein contained, the contractor, with the approval of the architects, shall be at liberty, after three days’ written notice to the subcontractor, to provide any such labor or materials, and to deduct the cost thereof from any money then due or thereafter to become due to the [216]*216subcontractor under this contract; and if such refusal, neglect or failure is sufficient ground for such action the contractor shall also be at liberty to terminate the employment of the subcontractor for the said work and to enter upon the premises and take possession, for the purpose of completing the work included under this contract, of all materials, tools and appliances thereon, and to employ any other person or persons to furnish the work, and to provide the materials therefor; and in case of such discontinuance of the employment of the subcontractor he shall not be entitled to receive any further payment under this contract until the said work shall be wholly finished, at which time, if the unpaid balance of the amount to be paid under this contract shall exceed the expense incurred by the contractor in finishing the work, such excess shall be paid by the contractor to the subcontractor; but if such expense shall exceed such unpaid balance, the subcontractor shall pay the difference to the contractor. The expense incurred by the contractor as herein provided, either for furnishing materials or finishing the work, and any damage incurred through such default, shall be chargeable to the subcontractor.”

In pursuance of this provision the engineering company gave the following notice to Anderson:

“Mr. R. A. Anderson, St. Louis, Missouri.
“Dear Sir — This is to notify you, R. A. Anderson, that you have failed and neglected to fulfill the items of your agreement with the Widmer Engineering Company, of St. Louis, Mo., as contained in article 6 of your contract with the said Widmer Engineering Company. You have further admitted and represented to the said Widmer Engineering Company that you would be unable to continue under the said contract. It appears further that you will be unable to fulfill said contract.
“This, therefore, is a three days’ notice provided for in said article 5 in said contract, and you are further notified that unless you fulfill completely each item in said article 5 in said contract, with the said Widmer Engineering Company, that said company, after three days’ notice, expects to have said work performed and said materials furnished and said contract fulfilled in whatever particular you may fail, and that the expense for said work shall be charged against you and deducted from any money in the hands of the said Widmer Engineering Company owing to you.
“This notice is given as provided for in said contract and is sent by the approval of the architect for said building. '
“(Signed) E. V. Guyther,
“Widmer Engineering Company.”

It appears that the chattel mortgage had been executed and filed for record before the expiration of the time fixed by the notice. Under the facts, the lumber company had the superior right to the possession of the mortgaged property. [217]*217While the property was used on the hotel premises it comprised forms and appliances which did not enter into the construction of the building.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Titusville Iron Co. v. . City of New York
100 N.E. 806 (New York Court of Appeals, 1912)
Duplan Silk Co. v. Spencer
115 F. 689 (Third Circuit, 1902)
In re Shelly
235 F. 311 (D. New Jersey, 1916)
MacEvoy v. E. & Z. Van Raalte, Inc.
242 F. 251 (Third Circuit, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
187 P. 872, 106 Kan. 213, 1920 Kan. LEXIS 488, Counsel Stack Legal Research, https://law.counselstack.com/opinion/davidson-case-lumber-co-v-anderson-kan-1920.