Duncan v. Clary

254 P. 386, 123 Kan. 24, 1927 Kan. LEXIS 57
CourtSupreme Court of Kansas
DecidedMarch 12, 1927
DocketNo. 26,878
StatusPublished

This text of 254 P. 386 (Duncan v. Clary) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Duncan v. Clary, 254 P. 386, 123 Kan. 24, 1927 Kan. LEXIS 57 (kan 1927).

Opinion

The opinion of the court was delivered by

Johnston, C. J.:

John Duncan brought this action against the board of county commissioners of Bourbon county, alleging that they had wrongfully and maliciously taken possession of certain road machinery and equipment, property belonging to plaintiff, of the value of $23,235.50, and had converted it to their own use, and he prayed for the value of the property and also for damages. The Road Supply and Metal Company later intervened in the action claiming to be the owner of part of the property taken and used by the commissioners, and it asked judgment for the value of the same in the amount of $13,197. The case was tried by the court without a jury and judgment was given in favor of the board of county commissioners of Bourbon county against both the plaintiff and the intervener, from which they appeal.

In June, 1921, the board of county commissioners, after proper preliminary proceedings, duly ordered the improvement of three sections of highways within the county, and application was made for federal aid for each project, which was granted, and the roads were incorporated into the state system of highways. Advertisements for bids were duly made for the improvement of these roads, and when the bids came in those made by Frank Bechtelheimer were found to be the lowest, and the three contracts were awarded to him. Formal contracts were prepared and signed, which were of th.e standard form used in federal-aid projects. The contracts provided among other things when the work should be commenced, when completed, that the contractor should provide sufficient workmen and equipment and materials to insure the carrying on and completion of the work, and that if the work-was unsuitable and it was rejected the contractor was required to remove it and remake the road in accordance with the contract, and that if he failed in these respects, or if he became insolvent, or allowed a final judgment against him [26]*26to remain unsatisfied for 48 hours, or if he should make an assignment for the benefit of creditors:

. . or from any other cause whatsoever shall not carry on the work in an acceptable manner, the engineer shall give notice in writing to the contractor and his surety of such delay, neglect or default, specifying the same, and if the contractor, within a period of ten (10) days after such notice, shall not proceed in accordance therewith, then the board shall, upon written certificate from the engineer of the fact of such delay, neglect or default, and the contractor’s failure to comply with such notice, have full power and authority, without violating the contract, to take the prosecution of the work out of the hands of the contractor, appropriate or use any or all materials and equipment on the ground as may be suitable and acceptable, and may enter into an agreement for the completion of said contract according to the terms and provisions thereof, or use such other methods as in his opinion shall be required for the completion of said contract in an acceptable manner. All costs and charges incurred by the board, together with the costs of completing the work under contract, shall be deducted from any moneys due or which may become due said contractor. In case the expense so incurred by the board shall be less than the sums which would have been pa3^able under the contract if it had been completed by said contractor, then the said contractor shall be entitled to receive the difference, and in case such expense shall exceed the sum which would have been payable under the contract, then the contractor and the surety shall be liable to pay the county the amount of said excess.”

The contractor listed the machinery and equipment owned by him which he was to devote to the building of the road. Shortly after the execution of the contract, the machinery and other equipment was shipped to Bourbon county and work upon the different projects was begun. John Duncan, the plaintiff, came to Bourbon county as an employee and agent of Bechtelheimer, and exercised general supervision of the work, including the payment of expenses incurred. He became the general superintendent of construction upon each of the road projects, and had in his possession the plans and specifications which constituted a part of each contract and which contained the essential provisions of the contract involved in this litigation. He continued in that capacity until May, 1922, but defaults were made in the progress of the work, which resulted in the service of a notice upon the contractor and The Globe Indemnity Company, which w’as a surety on the contractor’s obligations. Before the lapse of the time fixed by notice the contractor undertook to correct the causes of his default by making an arrangement with certain Kansas City interests to finance the projects, and at that time one Paul McGeehan took charge of the construction of said projects and of [27]*27the equipment upon them. His control continued until July, 1922, at which time defaults 'continued and work upon the projects had practically ceased. A second notice of default upon the contractor and the indemnity company was given by the board, and after the lapse of time specified in the notice the cause of default had not been corrected, and the board on August 7, 1922, in accordance with the provisions of the contract, took possession of all the equipment located on the projects necessary to complete them, and proceeded with the construction of the roads, after adopting proper resolutions to that end. About August 14, 1922, John Duncan made demand on the appellees for the equipment which had been taken over by the board, claiming to own the same under a bill of sale of date April 10,1922, asserting that he was the owner of the property taken over. It was alleged that prior thereto a bank had a mortgage on the property from Bechtelheimer, that the bank foreclosed its mortgage and sold the property to Duncan after the foreclosure. It appears that before the work was completed The Globe Indemnity Company brought an action in the- federal court in which Duncan and The Road Supply and Metal Company, among others, were made parties. In that action a receiver was appointed, who took constructive possession of the property under the order of that court, but the receiver, finding the board in the possession of the property, arranged with it that the county should continue to use the property for the completion of the three projects. After the completion of the roads the receiver sold the property and reported his action to the federal court.

Duncan contended that the testimony clearly established his title to the property taken over by the board, that he acquired it from the bank which had a lien thereon and had possession of it before the default occurred, and that the board could not take the possession of property other than that owned and possessed by the contractor, and argues that it could not enforce its charge or lien upon property owned by third persons, and that he was a third party so far as the contracts between the board and the contractor were concerned.

In respect to the claim of The Road Supply and Metal Company, there was a claim by it that it had furnished machinery and equipment for the purpose of building these roads upon a rental propo- * sition, the contractor to pay ten cents a cubic yard of earth moved [28]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hauselt v. Harrison
105 U.S. 401 (Supreme Court, 1882)
Titusville Iron Co. v. . City of New York
100 N.E. 806 (New York Court of Appeals, 1912)
Wilds v. . Board of Education
125 N.E. 89 (New York Court of Appeals, 1919)
Duplan Silk Co. v. Spencer
115 F. 689 (Third Circuit, 1902)

Cite This Page — Counsel Stack

Bluebook (online)
254 P. 386, 123 Kan. 24, 1927 Kan. LEXIS 57, Counsel Stack Legal Research, https://law.counselstack.com/opinion/duncan-v-clary-kan-1927.