Duneland Properties, LLC v. Northern Indiana Public Service Co.

14 N.E.3d 95, 2014 WL 3739690, 2014 Ind. App. LEXIS 364
CourtIndiana Court of Appeals
DecidedJuly 30, 2014
DocketNo. 56A03-1308-PL-320
StatusPublished
Cited by4 cases

This text of 14 N.E.3d 95 (Duneland Properties, LLC v. Northern Indiana Public Service Co.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Duneland Properties, LLC v. Northern Indiana Public Service Co., 14 N.E.3d 95, 2014 WL 3739690, 2014 Ind. App. LEXIS 364 (Ind. Ct. App. 2014).

Opinion

OPINION

VAIDIK, Chief Judge.

Case Summary

In 1955 Northern Indiana Public Service Company (NIPSCO) acquired a 100-foot-wide easement for electrical lines in Porter County. In 2007 NIPSCO filed a complaint for a permanent injunction alleging that its easement — which went across propérty that was later determined to be held by Duneland Holdings, LLC — had been violated by the previous landowners by mining the sand on the easement, causing difficulties in maintaining and servicing its poles. The trial court ordered that the easement be relocated and that Duneland Holdings pay NIPSCO $245,858 for the costs of reconstructing the power lines on the new easement.

Duneland Holdings now appeals. First, it contends that NIPSCO’s failure to mitigate damages is a bar to relief. Second, it contends that the trial court erred in admitting Plaintiff’s Exhibit 5 — a material and labor estimate prepared by a longtime NIPSCO engineer for relocating the power lines onto the new easement — into evidence because it is hearsay. Because mitigation of damages is not a defense to liability and NIPSCO in fact mitigated its damages, this issue is not a bar to NIP-SCO’s recovery. In addition, experts may testify to opinions based on inadmissible evidence, provided that it is of the type reasonably relied upon by experts in the field. Here, NIPSCO’s engineer testified that he relied on data from other NIPSCO departments in arriving at his material and labor estimate. The trial court therefore did not abuse its discretion in admitting Plaintiffs Exhibit 5. We affirm the trial court.

Facts and Procedural History

NIPSCO is a public utility whose primary purpose is to furnish natural gas and electrical power to northern Indiana, including Porter County. In 1955 NIPSCO acquired a 100-foot>-wide easement on property in Porter County in order to install, maintain, operate, repair, and replace towers and poles for the transmission, distribution, and delivery of electrical power to the public. Appellee’s App. p. 6-[98]*987. Pursuant to that grant, NIPSCO built a 138,000-volt transmission circuit between substations near Crown Point and Valparaiso. NIPSCO’s easement passes along the southern edge of a sand mine located on a 374-acre tract of land.

In the 1970s Jerry Lambert became involved with this 374-acre tract of land when he formed a partnership with three other people to operate a sand-mining operation. NIPSCO’s easement was properly recorded, and the partners were aware of it. Later, during the 1990s, Lambert acquired all right, title, and interest in the 374-acre tract from the other partners and continued operating the sand mine as a sole proprietor.

In 1999 James Hayward, a NIPSCO engineer, was asked to address the property owner’s desire to remove sand near NIP-SCO’s easement. Hayward visited the property and prepared an estimate to move the power lines to a different location on the property in order to accommodate the property owner’s desire to mine sand on NIPSCO’s easement. Id. at 101. NIPSCO’s estimate was approximately $125,000. Tr. p. 66. Sand excavations did not begin at this time.

In 2000 Lambert created two business entities to further pursue sand mining from the tract of land: Duneland Properties, LLC (which owned the land) and Duneland Sand, Inc. (which operated the sand-mining business). Lambert and his son-in-law, John Durachta, each owned a 50% interest in the entities. Durachta acted as general manager of Duneland Sand until late 2003. During this time, Durach-ta directed the removal of sand from both the tract of land and NIPSCO’s easement. The mining took place over several months. In June 2003 NIPSCO’s attorney sent a letter to Durachta directing Dune-land Sand to cease and desist its sand mining on NIPSCO’s easement:

We are contacting you because NIPSCO has discovered that the Easement has been materially adversely violated by [Duneland Sand]. Specifically, excavation activity by, through or under [Dune-land Sand] encroaches along the Easement a distance of approximately 2,200 feet. The excavation activity has significantly compromised the structural integrity of four (4) structures and made it unsafe, and in certain cases impossible, to gain access to the structures with the equipment required to maintain and operate the Electric Transmission Facility. Moreover, the excavation activity has made it impossible for NIPSCO to gain access between the structures to maintain and operate the Electrical Transmission Facility....
The Electric Transmission Facility is a major facility and the adverse consequences of [Duneland Sand’s] excavation activity are significant. On behalf of NIPSCO, we demand that your company immediately stop, directly or by, through or under any third parties, any further excavation activity in the Easement.

Appellee’s App. p. 56-57. NIPSCO’s estimate, prepared in August 2003, showed that the cost of moving the power lines was now $155,389. Def.’s Ex. D.

Although Duneland Sand stopped mining NIPSCO’s easement for a period of time following its receipt of the letter from NIPSCO’s attorney, it resumed mining NIPSCO’s easement in 2006 because Lambert said the sand was “too valuable.” Ap-pellee’s App. p. 69. Then, in December 2006, Lambert, as President and Managing Member of Duneland Sand and Duneland Properties, respectively, entered into an agreement with Kevin Misch to sell both companies. Pursuant to the agreement, Misch assumed the obligation for the defense of any claim by NIPSCO for Dune-[99]*99land Sand’s and Duneland Properties’ alleged infringement of NIPSCO’s easement and agreed to hold both companies harmless. Id. at 13, 38. Eventually, Duneland Properties, Duneland Sand, Duneland Sand Enterprises, LLC, Duneland Holdings, LLC, David Lasco, and the Lasco Family Trust (“Duneland Entities”) became the responsible parties answerable to NIPSCO’s claims. See Appellee’s Br. p. 2. This was in part because Lambert sold his interests in Duneland Sand and Duneland Properties. Later, during the litigation, Lasco established Duneland Holdings and had the property transferred to it. Finally, Misch was removed from the litigation, which left Lasco as the principal behind the remaining defendants. Id. at 3.

In October 2007 NIPSCO filed a complaint for a permanent injunction alleging, among other things, that the then-relevant defendants, Duneland Sand and Duneland Properties, while operating a sand mine in Porter County, “encroached upon, wasted and damaged NIPSCO’s easement causing it property damage by changing grade and undermining the integrity of its power transmission facilities thereby jeopardizing the reliability of electrical service to the public.” Appellee’s App. p. 3. NIPSCO therefore requested the court to issue a mandatory injunction “directing the ... defendants to be jointly and severally responsible for fill and moving fill in a timely manner to and around the excavated areas around the NIPSCO towers per NIPSCO’s specifications” and “be permanently enjoined from encroaching upon or damaging the property interests of NIPSCO in the continued unencumbered use of its easement for electric transmission or distribution lines as is the subject of its original grant.” Id. at 3-4 (quotation omitted). The Duneland Entities then filed a cross-claim against Lambert.

In February 2011 the trial court ordered that the Duneland Entities were permanently enjoined from further encroaching or otherwise committing additional waste within NIPSCO’s easement. Appellants’ App. p. 24.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
14 N.E.3d 95, 2014 WL 3739690, 2014 Ind. App. LEXIS 364, Counsel Stack Legal Research, https://law.counselstack.com/opinion/duneland-properties-llc-v-northern-indiana-public-service-co-indctapp-2014.