DSG Evergreen Family Ltd. v. Town of Perry

2019 WI App 5, 925 N.W.2d 782, 385 Wis. 2d 514
CourtCourt of Appeals of Wisconsin
DecidedDecember 20, 2018
DocketAppeal No. 2017AP2352
StatusPublished

This text of 2019 WI App 5 (DSG Evergreen Family Ltd. v. Town of Perry) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
DSG Evergreen Family Ltd. v. Town of Perry, 2019 WI App 5, 925 N.W.2d 782, 385 Wis. 2d 514 (Wis. Ct. App. 2018).

Opinion

FITZPATRICK, J.

¶1 DSG Evergreen Family Limited Partnership appeals from an order of the Dane County Circuit Court dismissing DSG's claims against the Town of Perry. This case arises out of a partial taking of, and monetary compensation for, DSG's real estate by the Town, which was affirmed by this court. DSG Evergreen Family Ltd. Partnership v. Town of Perry , No. 2011AP492, unpublished slip op. (WI App Dec. 6, 2012) [hereinafter DSG I ].

¶2 The taking consisted of the portion of DSG's property which abutted County Highway Z, including a "field road" that provided the remainder of DSG's property with access to that highway. The Town's condemnation petition included an obligation of the Town to construct a new field road for DSG, "built to the same construction standards as the [old] field road." The Town has constructed a new field road for DSG after condemnation of the property and before this action was filed.

¶3 In this lawsuit, DSG makes two claims against the Town. First, DSG seeks a declaratory judgment that the Town was required to build the new field road so that it met statutory standards set forth in WIS. STAT . § 82.50 (2015-16)1 or, alternatively, to the standards in a Town ordinance. Second, DSG claims that the Town violated its obligation to construct the new field road for DSG set forth in the condemnation petition because the new field road did not meet the construction standards of DSG's previous field road.

¶4 The circuit court granted summary judgment in favor of the Town and dismissed DSG's claims. The court concluded that neither WIS. STAT . § 82.50 nor the Town's ordinances create a private right of action. The circuit court also determined that DSG's claim that the Town failed to meet its obligation under the condemnation petition was barred pursuant to the doctrine of claim preclusion. We conclude that neither § 82.50 nor the Town's ordinances provide a private right of action in favor of DSG in these circumstances, and the doctrine of claim preclusion bars DSG's second cause of action. We therefore affirm.

BACKGROUND

¶5 The parties have a lengthy and relatively complex litigation history, but we need not mention that history in detail. As background, we provide material facts and procedural history to the extent necessary to place our discussion of the parties' arguments within the proper context. The parties stipulated in the circuit court to a number of pertinent facts. Additional background is gleaned from the record and a prior decision of this court, and these facts are materially undisputed.

¶6 In February 2006, pursuant to WIS. STAT . § 32.06(7), the Town initiated an eminent domain action by filing a petition for condemnation proceedings describing a roughly 12-acre parcel belonging to DSG. The Town's purpose in seeking condemnation was to construct a public park to be known as the Hauge Log Church Historic District Park. The proposed taking was a partial one consisting of DSG's property abutting County Highway Z, with the remainder parcel of DSG's property not subject to condemnation consisting of about 80 acres. The proposed taking included a field road2 that, up to that time, provided DSG's remainder parcel with access to County Highway Z.

¶7 Under the terms of the condemnation petition, the Town was obligated to replace the old field road as noted:

The Town will replace the [old] field road on the 12.13 acre parcel to be acquired with a new field road from Highway Z along the northern boundary of the Hauge Church Park boundary to the western boundary of the proposed Park in order to provide access to the Owner's other lands in the Town of Perry and for park-related purposes subject to the Hauge Church Park Regulations. This field road will be built to the same construction standards as the [old] field road.

(Emphasis added.) The parties agree that: (a) the petition required the Town to build the new field road in a different location than the location of the old field road; and (b) the Town built the new field road in the location described in the petition.

¶8 In March 2008, the Town acquired title to the approximately 12-acre parcel. In February 2009, a jury trial determined just compensation owed to DSG from the Town for that taking. The parties entered a stipulation before the circuit court regarding that jury trial as follows:

The essential issue tried in the just compensation trial was the determination of the fair market value of the entirety of DSG's property before the Taking and the fair market value of DSG's property after the Taking assuming completion of the project for which the Taking occurred, including the construction of the new field road under the terms of the Petition .

(Emphasis added.) Thus, the parties agree that the jury was told that DSG would receive a new "field road built to the same construction standards as the [old] field road."

¶9 Of importance to the construction of the new field road, the parties further stipulated that:

During the [just compensation] trial, DSG introduced in evidence an engineering report from JSD Professional Services, Inc. ("JSD") dated November 17, 2008, a copy of which is attached to this stipulation as Exhibit F. There was no testimony during the trial regarding the scope of the Town's obligation under the Petition to construct a new field road.

Notably, the engineering report from DSG's expert states that the proposed new field road could not be equivalent to the old field road because of physical limitations and attributes of the area described in the petition where the new field road would be built. According to the engineering report, the new field road to be built by the Town would "not [be] equivalent with" the old field road because the location of the new field road involved "much steeper slopes, less width and significantly poorer intersection sight distance" than did the old field road. Additionally, the report states that the area where the new field road would be built lacked adequate space for storm water management facilities that would meet Town, County, and State requirements.3 The jury set the amount of just compensation for the taking at $312,500, and this court affirmed that award in DSG I .

¶10 In November 2009, the Town sent a letter to DSG indicating that it had finished construction of the new field road. DSG responded and alleged that the new field road was inferior to the old field road. Specifically, DSG complains that the new field road differs from the old field road in the following respects:

(1) Narrower average width than the old field road.
(2) Steeper maximum slope than the old field road.
(3) Lack of a pond for storm water detention.
(4) Lack of an emergency turn-out (the old field road included an emergency turn-out to allow for clear passage of vehicles traveling in opposite directions).
(5) Lack of a turn-around (the old field road had a turn-around area).

The Town does not dispute DSG's account of how the new field road now differs from the old field road.

¶11 In 2015, DSG initiated the present action against the Town. The circuit court granted partial summary judgment in favor of the Town, concluding that DSG did not have a private right of action under WIS. STAT.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Allen v. McCurry
449 U.S. 90 (Supreme Court, 1980)
Lecander v. Billmeyer
492 N.W.2d 167 (Court of Appeals of Wisconsin, 1992)
Schill v. Wisconsin Rapids School District
2010 WI 86 (Wisconsin Supreme Court, 2010)
Wisconsin Electric Power Co. v. Outagamie County
2008 WI App 75 (Court of Appeals of Wisconsin, 2008)
Grube v. Daun
563 N.W.2d 523 (Wisconsin Supreme Court, 1997)
McNeill v. Jacobson
198 N.W.2d 611 (Wisconsin Supreme Court, 1972)
Northern States Power Co. v. Bugher
525 N.W.2d 723 (Wisconsin Supreme Court, 1995)
Sweet v. Berge
334 N.W.2d 559 (Court of Appeals of Wisconsin, 1983)
Kruckenberg v. Harvey
2005 WI 43 (Wisconsin Supreme Court, 2005)
State Ex Rel. Cabott, Inc. v. Wojcik
177 N.W.2d 828 (Wisconsin Supreme Court, 1970)
Farr v. Alternative Living Services, Inc.
2002 WI App 88 (Court of Appeals of Wisconsin, 2002)
Lindas v. Cady
515 N.W.2d 458 (Wisconsin Supreme Court, 1994)
Yahnke v. Carson
2000 WI 74 (Wisconsin Supreme Court, 2000)
State v. Ginger M. Breitzman
2017 WI 100 (Wisconsin Supreme Court, 2017)
Thompson v. Milwaukee & St. Paul Railway Co.
27 Wis. 93 (Wisconsin Supreme Court, 1870)
McCord v. Sylvester
32 Wis. 451 (Wisconsin Supreme Court, 1873)
Milwaukee Electric Railway & Light Co. v. Becker
196 N.W. 575 (Wisconsin Supreme Court, 1923)
State ex rel. Wollner v. Schloemer
228 N.W. 487 (Wisconsin Supreme Court, 1930)
State ex rel. Wisniewski v. Rossier
238 N.W. 825 (Wisconsin Supreme Court, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
2019 WI App 5, 925 N.W.2d 782, 385 Wis. 2d 514, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dsg-evergreen-family-ltd-v-town-of-perry-wisctapp-2018.