Wisconsin Electric Power Co. v. Outagamie County

2008 WI App 75, 752 N.W.2d 388, 311 Wis. 2d 746, 2008 Wisc. App. LEXIS 269
CourtCourt of Appeals of Wisconsin
DecidedApril 8, 2008
Docket2007AP1315
StatusPublished
Cited by2 cases

This text of 2008 WI App 75 (Wisconsin Electric Power Co. v. Outagamie County) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wisconsin Electric Power Co. v. Outagamie County, 2008 WI App 75, 752 N.W.2d 388, 311 Wis. 2d 746, 2008 Wisc. App. LEXIS 269 (Wis. Ct. App. 2008).

Opinion

BRUNNER, J.

¶ 1. Wisconsin Electric Power Company, d/b/a WE Energies (WEPCO), appeals a summary judgment dismissing its claims against Outag-amie County. Those claims revolved around WEPCO's private easement rights along a county highway and the costs of relocating its utility lines to accommodate a highway expansion. We affirm.

BACKGROUND

¶ 2. In the 1930s and 1950s, WEPCO obtained private easement rights from landowners to run utility lines along County Highway S in the Town of Liberty, *749 Outagamie County. The lines were located thirty-four feet from the centerline of the highway, just outside the highway right-of-way.

¶ 3. In 1964, the Town of Liberty adopted a County zoning ordinance that included what is now Outagamie County, WI, Okdinance § 17.40(3)(g) (1992):

Telephone, television, natural gas and power transmission lines may be constructed within the setback lines and additions to and replacements of existing lines may be made, provided that the utility owner first file with the County an agreement in writing that they will remove at their expense all new lines, additions and replacements constructed after the effective date of this paragraph, when such removal is necessary for the improvement of the highway.

Following the adoption of this ordinance, in 1966, WEPCO replaced its utility lines along the highway, placing the new lines in the same approximate location as the old ones, outside the right-of-way, but within the setback area. 1 However, "WEPCO never filed an agreement to pay relocation costs as required by the ordinance.

¶ 4. In 2004, the County advised WEPCO of its plan to expand Highway S and that WEPCO's utility fines would need to be moved to a new location within the right of way at WEPCO's expense. The County also began acquiring lands necessary to expand its right-of-way.

¶ 5. On January 25, 2005, WEPCO executed a document entitled "Conveyance of Rights in Land," *750 which purported to convey its private easements rights to the County and was recorded with the Outagamie County Register of Deeds. 2 That conveyance document included the following language:

The grantor reserves to itself the right to cross, traverse, or otherwise occupy these lands with the present and future overhead or underground transmission lines and appurtenant facilities and supporting structures in a manner ... which will not interfere with normal highway maintenance and operation, provided, however, that the costs of any relocation or alteration of the said transmission lines, appurtenant facilities, or supporting structures when required by the grantee for any reason, including accommodating expanded or additional highway facilities on or across said lands, will be paid by the grantee .... (Emphasis added.)

¶ 6. Construction on the highway expansion was planned to begin in May 2005. The construction project involved an $864,289 grant from the Wisconsin Department of Transportation. The grant was contingent upon the County resolving any claims associated with the project. In March 2005, WEPCO informed the County that it considered the costs of relocating its lines compensable and that it would not begin relocating its lines until the County agreed to pay those costs. The DOT threatened to withdraw advertisements to let materials for the project unless the County resolved WEPCO's claim by March 25, 2005.

¶ 7. On March 24, 2005, the County and WEPCO entered into an "Audit Agreement." The agreement *751 provided that the County would reimburse WEPCO for the costs of relocating its utility lines. However, the agreement contained an addendum stating:

We Energies claims to have certain easement rights within the existing highway right of way referenced by and in the Audit Agreement. Based upon We Energies claims of easement rights, We Energies requests compensation for removing and relocating its poles presently located within the said highway right of way. In the interest of enabling the pending highway construction project to proceed in and on the right of way referenced by and in this Audit Agreement, and based upon the presentation of the said We Energies claims, Outagamie County is willing to enter into this Audit Agreement. It is expressly understood by Outagamie County and We Energies that in the event it is later determined that the said We Energies claims were not well founded in law or fact, then and in that event, We Energies agrees that it will reimburse Outagamie County the amount of money Outagamie Counly paid We Energies to remove and relocate said utility poles ....

Thus, the addendum provided that WEPCO would have to return the relocation costs paid by the County if it was later determined that WEPCO's claims "were not well founded in law or fact."

¶ 8. WEPCO relocated its utility lines and sent invoices to the County totaling $309,103.94. The County refused to pay. WEPCO commenced this action against the County alleging breach of contract, among other claims, and seeking payment of the relocation costs.

¶ 9. The circuit court granted summary judgment to the County. The court concluded that the January 2005 conveyance of easement rights was void because WEPCO was responsible for paying the relocation costs under the ordinance. The court also concluded the audit agreement was enforceable and that the County *752 breached the agreement by not reimbursing WEPCO for its relocation costs. However, the court concluded that the County's failure to pay the relocation costs was only a de minimus breach because, ultimately, the County would be entitled to have the costs returned pursuant to the audit agreement's addendum.

DISCUSSION

¶ 10. The County frames the central issue as whether it can absorb WEPCO's relocation costs by contract when an ordinance explicitly requires WEPCO to pay those costs. The County contends any contract shifting those costs was void. 3 WEPCO asserts the ordinance is irrelevant and that this is simply a contract case. Further, absent the payment of its relocation costs, WEPCO contends the County effectively took WEPCO's easement rights without compensation.

¶ 11. We review grants of summary judgment de novo, applying the same methodology as the circuit court. Park Bancorp., Inc. v. Sletteland, 182 Wis. 2d 131, 140, 513 N.W.2d 609 (Ct. App. 1994). Summary judgment is appropriate if there are no genuine issues of material fact and the moving party is entitled to judgment as a matter of law. Wis. Stat. § 802.08. 4

¶ 12. A municipality is free to deny the validity of a contract that was beyond the municipality's power to make. Village of McFarland v. Town of Dunn, 82 Wis.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DSG Evergreen Family Ltd. v. Town of Perry
2019 WI App 5 (Court of Appeals of Wisconsin, 2018)
Town of Clayton v. CARDINAL CONST. CO., INC.
2009 WI App 54 (Court of Appeals of Wisconsin, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
2008 WI App 75, 752 N.W.2d 388, 311 Wis. 2d 746, 2008 Wisc. App. LEXIS 269, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wisconsin-electric-power-co-v-outagamie-county-wisctapp-2008.