Draper MacHine Works, Inc. v. Department of Natural Resources

815 P.2d 770, 117 Wash. 2d 306, 1991 Wash. LEXIS 335
CourtWashington Supreme Court
DecidedSeptember 5, 1991
Docket57499-5
StatusPublished
Cited by24 cases

This text of 815 P.2d 770 (Draper MacHine Works, Inc. v. Department of Natural Resources) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Draper MacHine Works, Inc. v. Department of Natural Resources, 815 P.2d 770, 117 Wash. 2d 306, 1991 Wash. LEXIS 335 (Wash. 1991).

Opinion

Brachtenbach, J.

The issues in this case concern the Department of Natural Resources' statutory authority to collect rent for use of state-owned waterways and Draper Machine Works' right to maintain a marina in such a waterway. The trial court concluded the Department of Natural Resources (DNR) has no authority to enter into rental agreements for use of waterways and therefore declared void a lease of waterway between Draper Machine Works (respondent) and DNR. It further held that respondent has an equitable right to occupy the *309 waterway and therefore entered a summary judgment order to that effect in favor of respondent. We reverse and remand.

In 1896 respondent's predecessor bought uplands (land above high tide) and tidelands (lands between ordinary high and extreme low tide) from the State. These lands were located on the south side of Salmon Bay. Salmon Bay is a body of water that runs generally east-west between Puget Sound on the west and Lake Union on the east. At that time, Salmon Bay was connected to Puget Sound. See Bilger v. State, 63 Wash. 457, 460, 116 P. 19 (1911). Respondent's predecessor's tidelands extended north, out to a waterway line which had been established in 1894. On the other (north) side of the waterway line was the Salmon Bay waterway which had been established by the State to provide unimpeded navigation through the bay. Coterminous with the waterway line was a federal pier-head line which was established at essentially the same time and served essentially the same function as the waterway line relative to unimpeded navigation. This unimpeded navigation was necessary because the state and federal governments had decided to run the Lake Washington Ship Canal through Salmon Bay and Lake Union.

The ship canal was eventually completed and in 1949 the federal government moved the federal pierhead line north of its prior location, so that the federal pierhead line was no longer coterminous with the state waterway line. The federal government does not dredge landward of its pierhead lines. 33 U.S.C. § 628 (1988). This left a stretch of waterway between the waterway line and the federal pierhead line (referred to herein as the intervening waterway) which was no longer being dredged and which was no longer considered by the federal government to be necessary for navigation in the ship canal.

*310 Respondent, which had purchased the abutting tidelands 1 and uplands from its predecessor in 1945, sought to purchase this intervening waterway area in 1957. The State refused to sell. In 1959 respondent tried again, this time seeking to lease the intervening waterway. The State, through DNR, agreed and entered into a 10-year "lease" of "unplatted tidelands" with respondent which was renewed in 1969. This renewal expired in 1984. Respondent has constructed boat moorage facilities on its own tidelands and on this intervening area of the waterway (mostly on the waterway).

In 1979 DNR sought an increase in rent to bring the rent for the intervening waterway up to fair market rental. Respondent objected, stopped paying rent, and filed an action in 1980 seeking quiet title to the intervening waterway and return of rent "wrongfully" paid to DNR. DNR counterclaimed seeking to compel respondent to pay its rent, and moved for summary judgment dismissal of respondent's claim. In 1983 the King County Superior Court granted partial summary judgment to DNR, holding that the State, not respondent, owned the intervening waterway. The only issue left open was DNR's counterclaim for unpaid rent.

In 1984, respondent filed a "Reply and Request for Additional Relief ". In this pleading it asserted, ostensibly as defenses to DNR's counterclaim, additional rights to relief which had not been pleaded in its original complaint. Namely, it asserted that it had an equitable "right *311 of access" across the waterway under Commercial Waterway Dist. 1 v. Permanente Cement Co., 61 Wn.2d 509, 512-13, 379 P.2d 178 (1963), which in effect gave it the right to occupy the waterway with its moorage slips. It also asserted that the "leases" it had entered into with DNR were not authorized by statute and were therefore void. It therefore again sought return of the rent it had already paid DNR.

In 1990 respondent moved for summary judgment on these grounds, and also sought denial of DNR's counterclaim for unpaid rent. DNR filed a cross motion for summary judgment on the "right to occupy" issue. The trial court granted respondent's motion and denied DNR's. In granting respondent's motion, however, the trial court only allowed respondent to recover the rent it had paid for the 3 years prior to 1984. This was because the court felt the action to recover the improperly paid rent was an action on an unwritten contract and therefore covered by the 3-year statute of limitations, and respondent's claim for refund of the improperly collected rents dated from the 1984 "Reply and Request for Additional Relief" rather than the 1980 complaint.

DNR appealed the trial court's decision as to the invalidity of the lease and respondent's "right of access". Respondent cross-appealed the trial court's application of the 3-year statute of limitations and its use of 1984 as the date from which the statute began to run. Certification to this court was accepted.

The parties raise a number of issues. Because of our disposition of this case, however, we need only address two of them: whether DNR has authority to collect rent under RCW 79.93.010 and .040, and whether respondent's "right of access" claim is properly before us on the facts of this case. Both of these questions are questions of law which we review de novo on appeal of a summary judgment order. DuVon v. Rockwell Int'l, 116 Wn.2d 749, 753, 807 P.2d 876 (1991).

*312 I

DNR's Authority To Collect Rent: RCW 79.93.040

Respondent argues that RCW 79.93.010 precludes DNR from collecting rent for respondent's occupation of the disputed portion of the waterway. RCW 79.93.010 provides in pertinent part:

It shall be the duty of the department of natural resources simultaneously with the establishment of harbor lines and the determination of harbor areas in front of any city or town, or as soon thereafter as practicable, to . . .
. . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Douglass v. Shamrock Paving, Inc.
Washington Supreme Court, 2017
Northlake Marine Works, Inc. v. Department of Natural Resources
138 P.3d 626 (Court of Appeals of Washington, 2006)
Olivine Corp. v. United Capitol Insurance
105 Wash. App. 194 (Court of Appeals of Washington, 2001)
Olivine Corp. v. United Capitol Ins. Co.
19 P.3d 1089 (Court of Appeals of Washington, 2001)
Jones v. Sisters of Providence in Washington, Inc.
140 Wash. 2d 112 (Washington Supreme Court, 2000)
Jones v. Sisters of Providence in Wash.
994 P.2d 838 (Washington Supreme Court, 2000)
Smoke v. City of Seattle
902 P.2d 678 (Court of Appeals of Washington, 1995)
State v. Danner
900 P.2d 1126 (Court of Appeals of Washington, 1995)
State v. Angulo
893 P.2d 662 (Court of Appeals of Washington, 1995)
Washington Mutual Savings Bank v. Department of Revenue
893 P.2d 654 (Court of Appeals of Washington, 1995)
Ticor Title Insurance Co. of California, Inc. v. Nissell
871 P.2d 652 (Court of Appeals of Washington, 1994)
Bour v. Johnson
864 P.2d 380 (Washington Supreme Court, 1993)
Tollycraft Yachts Corp. v. McCoy
858 P.2d 503 (Washington Supreme Court, 1993)
Food Services of America v. Royal Heights, Inc.
850 P.2d 585 (Court of Appeals of Washington, 1993)
Public School Employees v. Sunnyside School District
849 P.2d 1287 (Court of Appeals of Washington, 1993)
Our Lady of Lourdes Hospital v. Franklin County
842 P.2d 956 (Washington Supreme Court, 1993)
Washburn v. Beatt Equipment Co.
840 P.2d 860 (Washington Supreme Court, 1992)
Bird-Johnson Corp. v. Dana Corp.
833 P.2d 375 (Washington Supreme Court, 1992)
Cossel v. Skagit County
834 P.2d 609 (Washington Supreme Court, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
815 P.2d 770, 117 Wash. 2d 306, 1991 Wash. LEXIS 335, Counsel Stack Legal Research, https://law.counselstack.com/opinion/draper-machine-works-inc-v-department-of-natural-resources-wash-1991.