Drake Construction Co. v. Kemper House Mentor, Inc.

865 N.E.2d 938, 170 Ohio App. 3d 19, 2007 Ohio 120
CourtOhio Court of Appeals
DecidedJanuary 12, 2007
DocketNo. 2005-L-157.
StatusPublished
Cited by8 cases

This text of 865 N.E.2d 938 (Drake Construction Co. v. Kemper House Mentor, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Drake Construction Co. v. Kemper House Mentor, Inc., 865 N.E.2d 938, 170 Ohio App. 3d 19, 2007 Ohio 120 (Ohio Ct. App. 2007).

Opinion

Colleen Mary O’Toole, Judge.

{¶ 1} Drake Construction Company appeals from the summary judgment granted Kemper House Mentor, Inc. by the Lake County Court of Common Pleas. We reverse and remand.

{¶ 2} Drake is a general contractor in the construction industry. In July 2000, Drake entered into a contract with Kemper to build an assisted-living facility in Mentor, Ohio. This contract (the “primary contract”) was a U.S. Department of Housing and Urban Development (“HUD”) form, HUD-92442-A, which is a cost-plus contract. HUlT insured the building loan. The HUD form specified that the contract documents included the drawings and specifications, including the then current edition'of AIA (“American Institute of Architects”) Document A201, “General Conditions of the Contract for Construction,” and Form HUD-2554, “Supplementary Conditions of the Contract for Construction.” The HUD form provided that any provisions therein, or in the supplementary conditions, took precedence over inconsistent provisions in the AIA general conditions. It further provided that any changes in the drawings and specifications, terms of the contract, orders for extra work, or for alterations could be made only with the prior written approval of the Federal Housing Commissioner and Kemper’s lender, Banc One Capital Funding Corporation.

{¶ 3} Pursuant to the AIA general conditions, changes in the work under the primary contract could be accomplished by three methods: change order; construction change directive; or order for a minor change. A change order had to be in writing and signed by the architect, Kemper, and Drake. A change directive required only the agreement of the architect and Kemper. An order for a minor change could issue solely on the architect’s authority and was binding on both Kemper and Drake. Change directives and orders for minor changes also had to be in writing. The general conditions also provided that acceptance of final payment by Drake constituted a waiver of claims, except those previously made in writing and identified as unsettled at the time of final payment.

{¶ 4} The total amount to which Drake was entitled for work under the primary contract was limited to $3,761,299.

*21 {¶ 5} In return for its assistance, HUD evidently required certain changes or improvements outside the scope of the primary contract. To provide for these, Drake and Kemper entered into an “Off-Site Construction Contract” (the “secondary contract”) in May 2000., No HUD or AIA documents were referenced or incorporated in the secondary contract. The work under the secondary contract was to be completed by May 2001. Kemper agreed to pay Drake $112,790 under the secondary contract. The secondary contract contained no provision requiring change orders to be in writing.

{¶ 6} Drake claims that it quickly became apparent that there would be cost overruns. It alleges that there were deficiencies in the drawings provided by the architect and that the access road to the construction site had to be altered at great expense. It also claims that problems with the utilities caused cost overruns. Drake states that it discussed these problems with Kemper. Evidently, there are procedures whereby HUD’s approval can be obtained to cover such overruns, but Drake claims that Kemper promised to pay these expenses itself, to avoid the cumbersome HUD procedures.

{¶ 7} Drake sent monthly summaries of the alleged changes and cost overruns to a Doug Moltz, who had been retained by Kemper as project manager. These summaries contained a column containing descriptions of each proposed or completed change; a column entitled “Proposed Change,” evidently containing the cost for the change; a column entitled “Status,” often containing notations such as “Approved” or “Rejected”; a column entitled “Total Pending,” evidently showing the amount of monies expected by Drake for the particular item; a column entitled “Total Appr’d,” containing monetary figures; and a column entitled “Owner/Arch.” This last column rarely, if ever, contains any notation.

{¶ 8} In July 2002, Drake submitted a contractor’s requisition for the 14th and final HUD disbursement under the primary contract, in the amount of $225,763. This brought total payments to it under the primary contract to $3,761,299.

{¶ 9} In August, representatives of Drake, Kemper, and the architect attended a so-called “100% Draw Meeting,” evidently following a site inspection by HUD. A memorandum of this meeting signed by the HUD representatives indicates that there were no change orders under the primary contract.

{¶ 10} In the autumn of 2002, Drake submitted to Kemper a “contractor’s certificate of actual cost,” showing that Drake was owed $120,729.52 for cost overruns relating to the Mentor facility.

{¶ 11} Drake alleges that Kemper requested it to defer final payment for these overruns while Kemper pursued claims against the utilities contractor and the architect for the Mentor facility. Drake alleges that it provided Kemper with information in support of these claims.

*22 (¶ 12} Thereafter, Kemper refused to pay Drake any additional monies. On June 7, 2004, Drake filed the initial complaint in this action, alleging breach of contract relative to the primary contract and unjust enrichment. On August 9, 2004, Kemper filed a motion to dismiss or, alternatively, for summary judgment. Attached thereto was the affidavit of Betty Kemper, president of Kemper, stating affirmatively that Drake had been paid in full under the primary contract. Attached to this affidavit were the contract documents; the contractor’s requisition from July 2002 showing Drake’s application for the final disbursement from the HUD loan; and the HUD memorandum of the “100% Draw Meeting” from August 2002.

{¶ 13} On August 20, 2004, the trial court converted Kemper’s motion to dismiss to a motion for summary judgment. On September 14, 2004, Drake filed a motion to amend its complaint and a brief in opposition to Kemper’s motion. Alternatively to opposing the summary judgment motion, Kemper requested that the trial court deny that motion pursuant to Civ.R. 56(F). Attached to the brief in opposition was the affidavit of James Pinter, vice president and controller of Drake. Pinter alleged at paragraph 14 of this affidavit that if Betty Kemper or Doug Moltz were called to testify, they would admit “that the costs for the project exceeded the maximum amount set forth in the Primary Contract and that Kemper would be responsible to pay those amounts to Drake.” Attached to Pinter’s affidavit were several summaries of increased costs prepared by Moltz. That document, dated March 6, 2002, listed some 18 changes as “Owner requested and approved” totaling $31,477 in cost, as well as three items under “Owner responsibility” totaling $13,810.

{¶ 14} On September 20, 2004, Kemper filed its opposition to Drake’s motion to amend the complaint, as well as its reply brief in the summary judgment proceedings. Attached to the reply brief was a second affidavit by Betty Kemper, affirmatively stating that Drake had been paid the entire sum owed under the secondary contract.

{¶ 15} By a journal entry filed October 28, 2004, the trial court granted Drake leave to file its amended complaint by November 10, 2004. Drake did not file the amendment until December 20, 2004. Under its amended complaint, Drake alleged three causes of action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Castro v. Hero Havens, L.L.C.
Ohio Court of Appeals, 2026
Megalight, Inc. v. Reliable Final Mile Transport, L.L.C.
2025 Ohio 841 (Ohio Court of Appeals, 2025)
Wilmington Savs. Fund Soc. v. McHugh
2020 Ohio 4250 (Ohio Court of Appeals, 2020)
Fields v. Buehrer
2014 Ohio 1382 (Ohio Court of Appeals, 2014)
CitiMortgage, Inc. v. Guarnieri
2013 Ohio 4913 (Ohio Court of Appeals, 2013)
Beal Bank S.S.B. v. Means
2011 Ohio 5922 (Ohio Court of Appeals, 2011)
Penix v. Avon Laundry Dry Cleaners, 91355 (3-26-2009)
2009 Ohio 1362 (Ohio Court of Appeals, 2009)
Wells Fargo Bank v. Shingara, 2007-G-2764 (11-16-2007)
2007 Ohio 6154 (Ohio Court of Appeals, 2007)
Taylor v. Xrg, Inc., 06ap-839 (6-21-2007)
2007 Ohio 3209 (Ohio Court of Appeals, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
865 N.E.2d 938, 170 Ohio App. 3d 19, 2007 Ohio 120, Counsel Stack Legal Research, https://law.counselstack.com/opinion/drake-construction-co-v-kemper-house-mentor-inc-ohioctapp-2007.