Downes Swimming Pool, Inc. v. North Shore National Bank

464 N.E.2d 761, 124 Ill. App. 3d 457, 79 Ill. Dec. 857, 1984 Ill. App. LEXIS 1855
CourtAppellate Court of Illinois
DecidedMay 18, 1984
Docket83-1634
StatusPublished
Cited by19 cases

This text of 464 N.E.2d 761 (Downes Swimming Pool, Inc. v. North Shore National Bank) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Downes Swimming Pool, Inc. v. North Shore National Bank, 464 N.E.2d 761, 124 Ill. App. 3d 457, 79 Ill. Dec. 857, 1984 Ill. App. LEXIS 1855 (Ill. Ct. App. 1984).

Opinion

JUSTICE SULLIVAN

delivered the opinion of the court:

Plaintiff appeals from a judgment for defendant J. Roderick MacArthur (MacArthur) on his counterclaim for the cost of completing and repairing a swimming pool partly constructed by it, contending that (a) having breached the contract by wrongfully terminating it, MacArthur was not entitled to a setoff for the cost of completing the pool; and (b) the trial court erred in awarding damages for breach of warranty where the express warranty relied upon was conditioned on payment in full of the amount due under the contract.

On November 22, 1978, plaintiff and MacArthur entered into a contract for the construction of a swimming pool at MacArthur’s residence for $29,749, the estimated construction period to be “20 to 25 working days and in no event later than 10 days beyond completion of enclosure.” The parties eventually agreed upon a June 8, 1979, completion date, but the construction was still incomplete on October 1, 1979, when MacArthur informed plaintiff that it was to cease work on the project, that he would hire others to complete it, and that the cost thereof would be charged against any balance due plaintiff. At that time, MacArthur had made payments totalling $29,566.62. Plaintiff billed MacArthur for the balance due under the contract and for alleged extras, deducting from the bill credits for work which it had not completed. When no further payments were made, plaintiff commenced the instant action seeking foreclosure of its mechanic’s hen or, in the alternative, recovery on the contract. In their answer, defendants asserted that plaintiff had breached the contract and was therefore not entitled to any recovery, and MacArthur counterclaimed for the cost of completing the pool and for damages allegedly caused by plaintiff’s defective materials and workmanship.

At trial, witnesses for plaintiff testified that construction began in November 1978, with excavation of the site and installation of a concrete shell, but it was understood that no work could be done during the winter months, and that construction would resume in the spring. According to those witnesses, it was originally planned that the pool would be enclosed, necessitating coordination of plaintiff’s work with that of the contractors hired to build the enclosure. However, on April 18, 1979, plaintiff was notified that MacArthur had decided not to enclose the pool, and his architect, Thomas Hickey (Hickey), requested that construction resume immediately, since MacArthur wanted the pool ready for use that summer. It was explained to MacArthur that plaintiff’s work had been scheduled with the understanding that the pool would be enclosed, that its workers were then occupied with other scheduled work, and that, while they would return to MacArthur’s project as soon as possible, it was doubtful that work thereon could recommence until sometime in May. On May 4, 1979, plaintiff’s representative met with MacArthur and Hickey, and it was agreed that plaintiff would complete the work by June 8, 1979, provided that other contractors were on schedule with their work. At that time, the only work remaining to be done by plaintiff was installation of tiles on the floor and sides of the pool, plastering, placement of the pool equipment, and testing of the system.

Plaintiffs witnesses also testified that further delays which were beyond plaintiff’s control prevented completion of the project by June 8. The contractor hired by Hickey to do the concrete deck work around the pool did not complete its work until the first or second week of July, preventing plaintiff from plastering the pool until the middle of that month. Early in June, MacArthur decided to add a spa, and the equipment therefor was ordered but could not be placed until sometime in August when MacArthur and Hickey finally decided where the spa and pool equipment would be housed. After numerous changes, an equipment room was completed in August, and by the end of August all of the pool equipment was installed therein, but it was impossible to make the final connections because the necessary utility lines, which were to be installed by another contractor, were not yet in place. In September, the spa was completed, and all that remained was installation of a pool cover and testing of the system when plaintiff was notified by Hickey that MacArthur was terminating the contract and intended to hire others to complete it. MacArthur was billed for the work done, including extras not covered by the written contract, and credits were given for the work not done; i.e., installation of the pool cover, some incomplete electrical work, and installation of a valve. MacArthur refused to pay the bill, and plaintiff was not notified of any problems with the work nor given the opportunity to correct them.

Witnesses for defendants testified that the pool was originally planned as an outdoor pool, and that the reference in the contract to “enclosure” meant the enclosure of the pool equipment, not enclosure of the entire pool. There was some discussion of enclosing the pool in the early months of 1979, but the idea was abandoned when it appeared that the cost would be prohibitive. At a meeting in May, plaintiff’s representative was informed that MacArthur wanted the pool completed as quickly as possible, and he was assured that it would be done by June 8; however, the pool was not completed as promised, and plaintiff failed to comply with repeated demands that workers be sent to finish the project. Whenever such a demand was made, workmen would appear for a day or two, then no further work would be done for two or three weeks, until MacArthur or Hickey called and again insisted that plaintiff return to the jobsite. These witnesses denied that plaintiff’s work was delayed by other contractors, by the unavailability of parts and equipment, or by minor changes which MacArthur requested.

Defendants’ witnesses further testified that because of plaintiff’s repeated delays and failure to comply with demands that it resume work, MacArthur terminated the contract and hired others to complete the work in the spring of 1980. An architect engaged to supervise the completion stated that when he first saw the pool in late January 1980, it was not covered, there was water standing in the deep end of the pool, and the plaster finish was cracked, blistered, and peeling on all four walls. The damage could not be repaired by patching, and it was necessary to chip and sandblast the original plaster and apply a new coat of plaster. Other witnesses testified that the damage to the plaster was the result of improper application thereof to the concrete shell. They explained that plaster should be applied as soon as possible after the gunite shell (a concrete mixture applied by spraying) is in place to ensure a clean undersurface and proper bonding. In their opinion, since the plaster was not applied until more than six months after the concrete was installed, plaintiff should have sandblasted the concrete and applied an acid wash prior to plastering, or should have used a heavy acid wash and applied a bonding agent. Those witnesses also opined that mixing the plaster with dye, which was added to achieve a dark surface, compounded the problem by weakening the bonding of the plaster to the concrete.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

People v. Maron
2019 IL App (2d) 170268 (Appellate Court of Illinois, 2020)
In re 1555 Wabash LLC
493 B.R. 756 (N.D. Illinois, 2013)
Village of Evergreen Park v. Commonwealth Edison Co.
695 N.E.2d 1339 (Appellate Court of Illinois, 1998)
BD. OF DIRECTORS OF BLOOMFIELD CLUB RECREATION ASS'N v. Hoffman Group, Inc.
692 N.E.2d 825 (Appellate Court of Illinois, 1998)
Board of Directors v. Hoffman Group, Inc.
295 Ill. App. 3d 279 (Appellate Court of Illinois, 1998)
Adams v. Sussman & Hertzberg, Ltd.
684 N.E.2d 935 (Appellate Court of Illinois, 1997)
Berlak v. Villa Scalabrini Home for the Aged, Inc.
671 N.E.2d 768 (Appellate Court of Illinois, 1996)
Marc Development, Inc. v. Wolin
904 F. Supp. 777 (N.D. Illinois, 1995)
Schilli Leasing, Inc. v. Forum Insurance
628 N.E.2d 185 (Appellate Court of Illinois, 1993)
Harnischfeger Corp. v. Gleason Crane Rentals, Inc.
585 N.E.2d 166 (Appellate Court of Illinois, 1991)
Vicorp Restaurants v. Corinco Insulating Co.
584 N.E.2d 229 (Appellate Court of Illinois, 1991)
Veteran Supply Co. v. Swaw
548 N.E.2d 667 (Appellate Court of Illinois, 1989)
Harmon v. Dawson
530 N.E.2d 564 (Appellate Court of Illinois, 1988)
Northwest Water Commission v. Carlo v. Santucci, Inc.
516 N.E.2d 287 (Appellate Court of Illinois, 1987)
Boldon v. Chiappa
489 N.E.2d 6 (Appellate Court of Illinois, 1986)
Peters & Fulk Realtors, Inc. v. Shah
488 N.E.2d 635 (Appellate Court of Illinois, 1986)
Ellerby v. Spiezer
485 N.E.2d 413 (Appellate Court of Illinois, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
464 N.E.2d 761, 124 Ill. App. 3d 457, 79 Ill. Dec. 857, 1984 Ill. App. LEXIS 1855, Counsel Stack Legal Research, https://law.counselstack.com/opinion/downes-swimming-pool-inc-v-north-shore-national-bank-illappct-1984.