Double L Construction, Inc. v. Mitchell

182 S.W.3d 509, 2005 Ky. LEXIS 366, 2005 WL 3131454
CourtKentucky Supreme Court
DecidedNovember 23, 2005
Docket2005-SC-0036-WC
StatusPublished
Cited by14 cases

This text of 182 S.W.3d 509 (Double L Construction, Inc. v. Mitchell) is published on Counsel Stack Legal Research, covering Kentucky Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Double L Construction, Inc. v. Mitchell, 182 S.W.3d 509, 2005 Ky. LEXIS 366, 2005 WL 3131454 (Ky. 2005).

Opinions

[511]*511OPINION OF THE COURT

An Administrative Law Judge (ALJ) determined that an injury to the claimant’s eye while performing carpentry resulted in a period of temporary total disability (TTD) that ended when he was released to return to his usual job as a carpenter. The Workers’ Compensation Board (Board) reversed the award on the ground that the claimant continued performing his concurrent, part-time janitorial job without interruption. Robertson v. United Parcel Service, 64 S.W.3d 284 (Ky.2001). Convinced that the Board misconstrued Robertson, the Court of Appeals determined that Central Kentucky Steel v. Wise, 19 S.W.3d 657, 659 (Ky.2000), controlled and reinstated the award. Although we agree that the claimant was entitled to TTD based on his temporary inability to perform carpentry and affirm in that regard, our reasoning is different.

The claimant was born in 1951 and was a high school graduate. He had spent his entire career as a carpenter in the construction business. In 2001, he began working for the defendant-employer. His injury occurred on January 6, 2003, when a nail struck by a co-worker flew up and hit the claimant in his left eye, lacerating the cornea and causing various complications. The claimant underwent three surgeries, the last of which was the implantation of a permanent acrylic intraocular lens. His physician prescribed corrective lenses and released him to return to work on August 18, 2003.

In addition to his full-time work as a carpenter, the claimant worked fifteen hours per week as a janitor. He had done so for Sky-Brite Corp. and its predecessor since 1995. The job involved emptying trash cans throughout Kroger’s corporate headquarters. He explained that he took the second job to be certain that he could pay child support because construction work is seasonal. He testified that child support was deducted from his earnings with Sky-Brite; therefore, he did not take time off from the job when he injured his eye.

Medical evidence indicated that Dr. Karp performed the two initial surgeries and released the claimant to return to light-duty work on March 3, 2003. Concerned about the stitches that remained in his eye, the lifting required in the carpentry job, and effects of exposure to dust, the claimant did not return to carpentry. Dr. Karp’s records indicate that the claimant telephoned on the following day to report that he had sought treatment elsewhere.

On March 4, 2003, the claimant sought treatment with Dr. Meyer, who noted that although the eye appeared to be healing well, some sutures were loose and some of the knots were exposed. He removed the loose sutures and over several weeks removed those that remained. On March 25, he took the claimant off work altogether. He performed the lens implant on May 5. When deposed on June 18, he stated that he thought the claimant had reached MMI, but he did not release him to return to work until August 18, 2003.

Dr. Meyer assigned a 8% AMA impairment, attributing a 1% impairment to loss of vision and a 7% impairment to difficulty with loss of contrast sensitivity, glare, and difficulty with vision in certain lighting. Like Dr. Meyer, Dr. Eiferman assigned a 1% AMA impairment for loss of vision. He added an additional 3% impairment for other factors such as those described by Dr. Meyer.

The parties stipulated that the claimant’s average weekly wage from carpentry was $536.00. Taking into account concurrent earnings of $107.31 per week for the janitorial work, they stipulated that his combined average weekly wage was $643.31. They also stipulated that the em[512]*512ployer paid voluntary TTD benefits at the rate of $357.35 per week from January 8, 2003, through March 3, 2003, for a total of $2,807.75. Among the contested issues was whether the employer overpaid or underpaid TTD.

When testifying at the hearing on September 25, 2003, the claimant stated that he had not returned to carpentry. He explained that he had refrained from doing so “to let my eye have plenty of time to heal” and that he continued to have increased sensitivity to sunlight, cold temperatures, and dust. He stated that the employer paid TTD benefits in the amount of $357.35 “every Friday afternoon” until March 3, 2003. He also stated that it made two subsequent benefit payments, on March 14 and 21, 2003, but that the total payments were not more than $2,800.00.

The employer asserted that it did not owe additional TTD. Furthermore, it relied on Robertson v. United Parcel Service, supra, in asserting that the claimant was not entitled to the TTD he received because he had worked continuously for Sky-Brite after his injury. It argued that Robertson stands for the principle that Chapter 342 views concurrent employments as though they are parts of one job. Thus, a worker whose injury temporarily prevents him from working a full day has only a temporary partial disability, which is not compensable. On that basis, the employer asserted that it was entitled to credit its voluntary TTD payments against the claimant’s permanent partial disability award.

The ALJ acknowledged that the claimant continued to perform janitorial work despite his injury but noted that Dr. Meyer did not release him to return to work until August 18, 2003. Concluding that the injury prevented him from performing his usual work as a construction carpenter until that time, the ALJ awarded TTD at the rate of $428.87 per week from the date of the injury until August 18, 2003, followed by permanent income benefits that were based on the 3% impairment Dr. Eiferman assigned. In a petition for reconsideration, the claimant pointed out that Dr. Eiferman had actually assigned a 4% impairment, consequently the ALJ granted the petition and amended the award. ■

Until December 12, 1996, Chapter 342 did not define temporary total disability. Addressing the absence of a statutory definition, the court explained in W.L. Harper Construction Company v. Baker, 858 S.W.2d 202 (Ky.App.1993), that temporary benefits are appropriate until the worker’s condition has stabilized and is not expected to improve with further treatment. At that point, any fingering disability may be viewed as being permanent. Noting that Kentucky did not recognize the concept of temporary partial disability,'the court determined that TTD benefits are appropriate until further medical treatment will not improve the worker’s condition or until the worker is able to return to some type of work.

The employer bases its arguments on two statutes. As enacted effective December 12, 1996, KRS 342.0011(ll)(a) governs the duration of a TTD award. It provides as follows:

“Temporary total disability” means the condition of an employee who has not reached maximum medical improvement from an injury and has not reached a level of improvement that would permit a return to employment.

KRS 342.140

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Disabled American Veterans v. Joan Sears
Court of Appeals of Kentucky, 2026
Lsc Communications v. Artie Winchester
Kentucky Supreme Court, 2024
Ronald Livers v. Westrock
Court of Appeals of Kentucky, 2024
Glenn Davis v. Blendex Company
Kentucky Supreme Court, 2021
Xenia R. Myers v. Merit Electronic, LLC
Court of Appeals of Kentucky, 2020
Raymond Bryant v. Jessamine Car Care
Kentucky Supreme Court, 2019
Trane Commercial Systems v. Delena Tipton
481 S.W.3d 800 (Kentucky Supreme Court, 2016)
Jeff Pace v. Kentucky Darby Coal Co., Inc.
Kentucky Supreme Court, 2016
zappos.com v. Sonia S. Mull
Kentucky Supreme Court, 2015
Livingood v. Transfreight, LLC
467 S.W.3d 249 (Kentucky Supreme Court, 2015)
Bowerman v. Black Equipment Co.
297 S.W.3d 858 (Court of Appeals of Kentucky, 2009)
Miller v. Square D Co.
254 S.W.3d 810 (Kentucky Supreme Court, 2008)
Double L Construction, Inc. v. Mitchell
182 S.W.3d 509 (Kentucky Supreme Court, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
182 S.W.3d 509, 2005 Ky. LEXIS 366, 2005 WL 3131454, Counsel Stack Legal Research, https://law.counselstack.com/opinion/double-l-construction-inc-v-mitchell-ky-2005.