Donald P. Lulich v. The Sherwin-Williams Company, a Corporation

992 F.2d 719, 1993 U.S. App. LEXIS 10058, 1993 WL 135832
CourtCourt of Appeals for the Seventh Circuit
DecidedApril 30, 1993
Docket92-2380
StatusPublished
Cited by7 cases

This text of 992 F.2d 719 (Donald P. Lulich v. The Sherwin-Williams Company, a Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Donald P. Lulich v. The Sherwin-Williams Company, a Corporation, 992 F.2d 719, 1993 U.S. App. LEXIS 10058, 1993 WL 135832 (7th Cir. 1993).

Opinion

*720 BAUER, Chief Judge.

Donald Lulich asks this court to reverse an order of the district court granting summary judgment in favor of The Sherwin-Williams Company (“SWC”). Because we conclude that genuine issues of material fact exist, we reverse the district court judgment and remand for further proceedings.

I.

In May of 1987, SWC signed a contract with Fred P. Berglund & Sons, Inc. (“Berg-lund”) which provided for the construction of a boiler house at SWC’s industrial facility, a twenty-acre parcel of land housing several SWC buildings. SWC retained Berglund and two other subcontractors 1 to construct the boiler house according to plans drafted and designed by SWC’s Design Department. To oversee and coordinate the construction project, SWC employed George Martin, a division engineer with more than thirty years experience in the supervision of construction projects. Martin’s duties included the “oversight of project design, determination of whether construction was carried out according to specifications, verif[ication of] the completion of work phases, and [the] ... approval] of interim payments to contractors.” Lulich v. The Sherwin-Williams Company, 792 F.Supp. 1106 (N.D.Ill.1992) (unpublished order). SWC also employed Walter Golat as the maintenance superintendent. Golat inspected the entire industrial facility including the boiler house construction site on a daily basis. Golat’s duties typically included the disconnection of utilities during construction and the approval and oversight of work involving high heat because of the presence of volatile, heat-sensitive chemicals at the facility-

To supervise the boiler house construction site, Berglund employed Dave Kordeck as the boiler house project superintendent. Kordeck managed the entire boiler house project and ensured that construction proceeded according to schedule. In addition, Berglund appointed a project manager, Norman Berglund, to address any problems that might arise during construction. Berglund also assigned a carpenter, Donald Lulich, to the boiler house project. Lulich’s assignment required that he use a scissors-lift 2 as a support to mark plumb lines on the ceiling of a SWC building. The scissors-lift was located three feet away from an unbarricad-ed and unprotected six-inch deep trench. On May 21,1987, while operating the scissors-lift at the boiler house site, Lulich suffered physical injuries when the lift fell into the adjacent trench and rolled onto its side.

Lulich subsequently sued SWC in state court alleging both a violation of the Illinois Structural Work Act, 740 ILCS 150/9 (1992) (formerly Ill.Rev.Stat. ch. 48, para. 69) (the “Act”), 3 and common law negligence. Pursuant to 28 U.S.C. § 1441(a), SWC removed the case to the United States District Court for the Northern District of Illinois based on diversity jurisdiction. Shortly thereafter, SWC filed a motion for summary judgment, asserting that SWC did not “hav[e] charge” of the work as required by the Act and further that it did not maintain sufficient control over the work to subject itself to liability for the alleged negligence. The district court agreed with SWC and entered judgment accordingly. Lulich appeals.

*721 II.

We review de novo a district court order granting summary judgment; that is, we determine anew whether any genuine issues of material fact exist and whether the moving party is entitled to judgment as a matter of law. Anderson v. Liberty Lobby, 477 U.S. 242, 249-52, 106 S.Ct. 2505, 2510-12, 91 L.Ed.2d 202 (1986). We draw all inferences in favor of the nonmoving party. Id. In the present case, Lulich argues that issues of material fact, pertaining to both the negligence and the Structural Work Act claims, exist with regard to SWC’s control over the construction of the boiler house. We agree.

A. The Illinois Structural Work Act Claim

In order to establish liability under the Illinois Structural Work Act, a plaintiff must demonstrate that the defendant had charge of either the overall construction work or the specific project which caused plaintiffs injuries. Fisher v. Crippen, 144 Ill.App.3d 239, 98 Ill.Dec. 183, 493 N.E.2d 1204, 1206 (1986), cited in, Savic v. United States, 918 F.2d 696, 699 (7th Cir.1990). Whether the defendant “had charge” of the work or worksite is typically a question for the jury. Burger v. Prairie Development, Ltd., 218 Ill.App.3d 814, 161 Ill.Dec. 467, 578 N.E.2d 1113, 1115 (1st Dist.1991); Gannon v. Chicago, Milwaukee, St. Paul & Pacific Railway Co., 22 Ill.2d 305, 175 N.E.2d 785, 787 (1961).

Illinois courts balance multiple factors when deciding whether a defendant “had charge” of work or a worksite. Fitzpatrick v. Perry Drugs Co., 213 Ill.App.3d 529, 157 Ill.Dec. 639, 572 N.E.2d 1103, 1105 (1st Dist. 1991). These factors include, but are not limited to, whether the owner:

(1) supervised and controlled the work; (2) retained the right to supervise and control the work; (3) constantly participated in the ongoing activities at the construction site; (4) supervised and coordinated the subcontractors; (5) took responsibility for safety precautions at the jobsite; (6) had authority to issue change orders; (7) had the right to stop the work; (8) owned the equipment at the work site; (9) was familiar with construction customs and practices; and, (10) was in a position to insure worker safety or alleviate equipment deficiencies or improper work habits.

Id.; accord Chance v. City of Collinsville, 112 Ill.App.3d 6, 67 Ill.Dec. 747, 445 N.E.2d 39, 42 (1983). Significantly, Illinois courts have found that a company’s retained authority to stop or control work to ensure worker safety alone is sufficient to constitute “having charge.” Kjellesvik v. Commonwealth Edison Co., 73 Ill.App.3d 773, 29 Ill.Dec. 559, 392 N.E.2d 116, 120 (1st Dist.1979) (citing Larson v. Commonwealth Edison Co., 33 Ill.2d 316, 211 N.E.2d 247, 252 (1965)).

We find that Lulich presented enough evidence of SWC’s control over the project to raise a genuine issue of material fact with respect to whether SWC “had charge” of the boiler house construction project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Axen v. Ockerlund Construction Co.
666 N.E.2d 693 (Appellate Court of Illinois, 1996)
King v. State Board of Elections
979 F. Supp. 582 (N.D. Illinois, 1996)
Cromer v. Joseph Behr & Sons, Inc.
845 F. Supp. 572 (N.D. Illinois, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
992 F.2d 719, 1993 U.S. App. LEXIS 10058, 1993 WL 135832, Counsel Stack Legal Research, https://law.counselstack.com/opinion/donald-p-lulich-v-the-sherwin-williams-company-a-corporation-ca7-1993.