Diocese of Rochester v. R-Monde Contractors, Inc.

148 Misc. 2d 926, 562 N.Y.S.2d 593, 1989 N.Y. Misc. LEXIS 892
CourtNew York Supreme Court
DecidedNovember 30, 1989
StatusPublished
Cited by4 cases

This text of 148 Misc. 2d 926 (Diocese of Rochester v. R-Monde Contractors, Inc.) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Diocese of Rochester v. R-Monde Contractors, Inc., 148 Misc. 2d 926, 562 N.Y.S.2d 593, 1989 N.Y. Misc. LEXIS 892 (N.Y. Super. Ct. 1989).

Opinion

OPINION OF THE COURT

David O. Boehm, J.

This case presents an issue of apparent first impression in this State; whether an architect, who allegedly failed to make adequate periodic inspections during construction and thereby failed to learn of defects in the work, is immune from liability by virtue of a contract provision stating that he will not be responsible for the contractor’s acts or omissions.

In these consolidated actions plaintiffs, the Diocese of Rochester, New York, and St. Theodore’s Church of Gates, New York, seek to recover damages sustained at the church after a fire which, it is claimed, was caused by the faulty installation of insulation around light fixtures. The actions are brought against the general contractor, R-Monde Contractors, Inc.; the architect, Starks Wurzer Patterson Romeo Architects, P. C. (Architect), and several subcontractors. On this motion the Architect seeks summary judgment dismissing the complaint and the cross claims against it.

In 1981 the Architect was retained by St. Theodore’s Church to provide architectural services in connection with the renovation of its church. Among other things, the renovation involved installation of insulation above the church ceiling. The contract between St. Theodore’s Church and the Architect was the standard form agreement prepared by the American Institute of Architects, which required the Architect to prepare design and construction documents for the renovation project. The contract also imposed certain obligations on the Architect during the construction phase of the project. Subparagraph 1.5.4 of the contract provides: "The Architect shall visit the site at intervals appropriate to the stage of construction * * * to become generally familiar with the progress and quality of the Work and to determine in general if the Work is proceeding in accordance with the Contract Documents. However, the Architect shall not be required to make exhaustive or continuous on-site inspections to check the quality or quantity of the Work. On the basis of such on-site observations as an architect, the Architect shall keep the Owner informed of the progress and quality of the [928]*928Work, and shall endeavor to guard the Owner against defects and deficiencies in the Work of the Contractor”.

Based on its observations at the worksite the Architect was obligated to issue certificates of payment in such amounts as it determined were owing to the contractor (subpar 1.5.7). In this regard, subparagraph 1.5.8 provides: “The issuance of a Certificate of Payment shall constitute a representation by the Architect to the Owner, based on the Architect’s observations at the site as provided in subparagraph 1.5.4 and on the data comprising the Contractor’s Application for Payment, that the Work has progressed to the point indicated; that, to the best of the Architect’s knowledge, information and belief, the quality of the Work is in accordance with the Contract Documents * * * and that the Contractor is entitled to payment in the amount certified”.

Although the Architect had an obligation to make such on-site inspections and possessed the authority to reject work that did not conform to the contract documents (subpar 1.5.12), subparagraph 1.5.5 provides that the architect, “shall not have control or charge of and shall not be responsible for construction means, methods, techniques, sequences or procedures, or for safety precautions and programs in connection with the Work, for the acts or omissions of the Contractor, Subcontractors, or any other persons performing any of the Work, or for the failure of any of them to carry out the Work in accordance with the Contract Documents”.

The complaint against the Architect alleges causes of action for breach of contract, negligence, and breach of express and implied warranties. Included in plaintiffs’ bill of particulars are allegations that the Architect failed to provide proper data, specifications and drawings to those who installed the insulation and electrical components; failed to adequately supervise and inspect such installations; failed to ensure adherence with all industry and trade standards involving such installations; failed to recognize and take appropriate precautions against the risk of fire; failed to undertake sufficient on-site observations of the work and keep plaintiffs informed of the progress; and failed to appreciate and advise plaintiffs of the potential for insulation overheating.

In opposing the Architect’s motion, plaintiffs have submitted an affidavit from Frank J. Mollura, an electrical and mechanical engineer, who investigated the cause of the fire. According to Mollura, combustible cellulosic insulation was installed too [929]*929close to the recessed light fixtures in violation of the NEC code, and did not allow the heat generated by the fixtures to escape, ultimately causing the fire.

The Architect does not dispute Mollura’s conclusions, but contends that it was not hired to supervise or inspect the quality of the work done nor did it undertake such a responsibility, that its contract made it not responsible for the construction methods used by the contractor, and that R-Monde, the general contractor, was solely responsible for supervising and directing the work. It is the Architect’s further position that it had no knowledge of the way the insulation was installed; that it did not supervise or inspect the installation of insulation; that because of the narrow confines of the attic area it would have been physically impossible to inspect the work at the extremities of the attic and extremely difficult to inspect the remainder; and that it did not have personnel sufficiently skilled or experienced in the field of insulation installation.

Generally, a person who contracts with an architect and who alleges that the architect has breached the obligation to properly design and supervise the construction, may sue for breach of contract and negligence (Sears, Roebuck & Co. v Enco Assocs., 43 NY2d 389). However, an architect is not subject to an action for breach of warranty (supra, at 398; see also, Milau Assocs. v North Ave. Dev. Corp., 42 NY2d 482) and, therefore, plaintiffs warranty claims are dismissed.

The Architect’s contention that its contract did not impose a duty to inspect is contrary to the express language of its agreement. Although the Architect was not obliged to supervise the construction work or to make exhaustive or continuous on-site inspections, it was, nevertheless, required to visit the site periodically in order to be familiar with the progress and quality of the work, to determine generally if the work was proceeding in accordance with the contract documents, to keep plaintiffs informed about the progress and quality of the work, and to guard the plaintiffs against defects in the work. The Architect’s obligation to issue certificates of payment required him to be familiar with both the quantity and quality of the work done. Generally, the primary object of these provisions is " 'to impose the duty or obligation on the architects to insure to the owner that before final acceptance of the work the building would be completed in accordance with the plans and specifications’ ” (Welch v Grant Dev. Co., [930]*930120 Misc 2d 493, 498, quoting Day v National U.S. Radiator Corp., 241 La 288, 304,128 So 2d 660, 666).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wax NJ-2, LLC v. JFB Construction & Development
111 F. Supp. 3d 434 (S.D. New York, 2015)
Capstone Enterprises of Port Chester, Inc. v. Board of Education Irvington Union Free School District
106 A.D.3d 856 (Appellate Division of the Supreme Court of New York, 2013)
306 East 61st Street Corp. v. 303 East 60th Street Associates
184 A.D.2d 346 (Appellate Division of the Supreme Court of New York, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
148 Misc. 2d 926, 562 N.Y.S.2d 593, 1989 N.Y. Misc. LEXIS 892, Counsel Stack Legal Research, https://law.counselstack.com/opinion/diocese-of-rochester-v-r-monde-contractors-inc-nysupct-1989.