Sears, Roebuck & Co. v. Enco Associates, Inc.

372 N.E.2d 555, 43 N.Y.2d 389, 401 N.Y.S.2d 767, 1977 N.Y. LEXIS 2473
CourtNew York Court of Appeals
DecidedDecember 21, 1977
StatusPublished
Cited by231 cases

This text of 372 N.E.2d 555 (Sears, Roebuck & Co. v. Enco Associates, Inc.) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sears, Roebuck & Co. v. Enco Associates, Inc., 372 N.E.2d 555, 43 N.Y.2d 389, 401 N.Y.S.2d 767, 1977 N.Y. LEXIS 2473 (N.Y. 1977).

Opinion

OPINION OF THE COURT

Jones, J.

We hold that, inasmuch as the relationship between *393 Sears, Roebuck as property owner and Enco Associates as architects had its genesis in the contract between them, in an action commenced more than three but less than six years after the completion of the ramp system with respect to which the architects’ services were rendered, the owner may recover contract damages against the architects either on the theory of breach of a particular contract provision or on the theory of failure to exercise due care in the performance of the contract services.

On the present motion to dismiss the complaint we accept the factual allegations set forth in the complaint as amplified by the bill of particulars. It is alleged that on May 15, 1967 Sears, Roebuck, owner, and Enco Associates, Inc., a firm of architects, entered into a contract under which the architects were to design and to supervise the construction of a system of ramps to provide ingress and egress for a parking deck to be constructed over Sears, Roebuck’s White Plains store. The contract contemplated an elaborate system of exposed ramps with snow-melting pipes to assure ease of snow removal. Defendant corporation held itself out to have architects and engineers qualified to design and to supervise the construction of the ramps and to provide appropriate design, mechanical and electrical engineering services. The architect-engineers prepared the plans and specifications and supervised the construction of the ramp system. Work on the project was commenced in 1967 and was completed in the spring of 1968.

In early May, 1970 cracks appeared in the ramps that endangered the structural integrity of the ramp system. It was alleged that the cracks were due to improper design of the snow-melting pipes contained in the ramps in that the architects had failed to include expansion joints and had provided for monolithic pouring of concrete for the ramps.

The complaint sets forth three separately stated causes of action. In the first liability is grounded on allegations of "the carelessness and negligence of defendant in preparing the design and engineering, plans and specifications of the said ramps”. It is alleged that the cost of removal of the existing ramps and the cost of construction of proper ramps will be $1,000,000, and that in the course of removal of the defective ramps the owner will lose the business of customers resulting in loss of anticipated profits of $350,000.

The second cause of action contains a claim for breach of *394 implied warranty of fitness for the purposes intended and claims damages in the lump sum of $1,350,000.

The third cause of action, with prior allegations incorporated by reference, alleges that the architects contracted to provide design; normal structural, mechanical and electrical engineering services and that they breached the contract by neglect or lack of professional care and in improperly designing the ramps, all to the owner’s damage in the sum of $1,350,000.

The action was commenced in June, 1972. After service of the answer and the bill of particulars, defendant architects moved under CPLR 3211 (subd [a], pars 5, 7) to dismiss the complaint on the grounds that the action was barred by the applicable three-year Statute of Limitations and that the second cause of action for breach of implied warranty failed to state a cause of action. Special Term granted the motion, concluding that, while the first cause of action was for professional malpractice, the second for breach of implied warranty and the third for breach of contract, in essence Sears, Roebuck’s claim was one for professional malpractice and as such was barred by the applicable three-year Statute of Limitations. Additionally Special Term dismissed the second cause of action on the ground that no cause of action lies against an architect for breach of implied warranty. The Appellate Division affirmed and we granted leave to appeal. We conclude that the order of the Appellate Division should be modified to the extent of denying the motion to dismiss as to the first and third causes of action.

The disposition in this case is governed by our recent decision in Matter of Paver & Wildfoerster (Catholic High School Assn.) (38 NY2d 669). We had previously held in Sosnow v Paul (36 NY2d 780) that owners’ claims against architects arising out of alleged defective construction of buildings, however verbally classified, accrue for purposes of all Statutes of Limitations on completion of construction. Thus, here any claims Sears, Roebuck has against Enco Associates accrued in 1968. Although the issues in Paver were presented in the context of arbitration, we expressly recognized the command of CPLR 7502 (subd [b]) that the Statute of Limitations to be applied by the courts in arbitration is the same as that in judicial proceedings (38 NY2d 669, 672, 673-674).

As we observed in Paver; the choice of applicable *395 Statute of Limitations is properly related to the remedy rather than to the theory of liability. "[T]he general principle [is] that time limitations depend upon, and are confined to, the form of the remedy” (38 NY2d 669, 672). We took note, however, of the cases in our courts in which the choice of Statute of Limitations had turned on what was termed the "reality” or the "essence” of the particular theory of liability on which the plaintiff relied. We observed that "many of these cases were decided in the context of causes of action to recover damages for direct or underlying personal injury”, and recognized that different policy considerations were involved and often different results reached in actions for damages to property or pecuniary interest only (38 NY2d 669, 675). In particular we held that the rule of Webber v Herkimer & Mohawk St. R. R. Co. (109 NY 311)—a personal injury action —and the cases in its wake should not be blanketed to cover all cases; that in Paver it should not be extended to a case arising in arbitration (38 NY2d 669, 675-676). But as noted above, CPLR 7502 (subd [b]) commands that, when the courts invoke a Statute of Limitations, its period in arbitration and in judicial proceedings shall be the same.

Without intending to disturb the holdings in the line of cases that deal with claims for personal injuries for malpractice on the part of members of one of the professions and acknowledging the Legislature’s general address to malpractice claims (CPLR 214, subd 6), 1 we reaffirm our holding in Paver that claims by owners against architects arising out of the performance or nonperformance of obligations under contracts between them are governed by the six-year contract Statute of Limitations (CPLR 213, subd 2), except with respect to the issue of damages as described below.

*396

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Whealon v. Gramercy Park Residence Corp.
184 N.Y.S.3d 751 (Appellate Division of the Supreme Court of New York, 2023)
Liberty Sq. Realty Corp. v. The Doe Fund, Inc.
2021 NY Slip Op 07082 (Appellate Division of the Supreme Court of New York, 2021)
Board of Educ. of Palmyra-Macedon Cent. Sch. Dist. v. Flower City Glass Co., Inc.
2018 NY Slip Op 3056 (Appellate Division of the Supreme Court of New York, 2018)
Wilson v. Dantas
128 A.D.3d 176 (Appellate Division of the Supreme Court of New York, 2015)
Wikiert v. City of New York
128 A.D.3d 128 (Appellate Division of the Supreme Court of New York, 2015)
797 Broadway Group, LLC v. Stracher Roth Gilmore Architects
123 A.D.3d 1250 (Appellate Division of the Supreme Court of New York, 2014)
Farage v. Ehrenberg
124 A.D.3d 159 (Appellate Division of the Supreme Court of New York, 2014)
Malmsteen v. Berdon, LLP
369 F. App'x 248 (Second Circuit, 2010)
Balta v. AYCO COMPANY, LP
626 F. Supp. 2d 347 (W.D. New York, 2009)
MATTER OF ARBITRATION BETWEEN KLIMENT & McKINSEY & CO.
821 N.E.2d 952 (New York Court of Appeals, 2004)
Weiss v. La Suisse
313 F. Supp. 2d 241 (S.D. New York, 2004)
Weiss v. La Suisse, Societe D'Assurances
293 F. Supp. 2d 397 (S.D. New York, 2003)
Shumsky v. Eisenstein
750 N.E.2d 67 (New York Court of Appeals, 2001)
Chase Scientific Research, Inc. v. Nia Group, Inc.
749 N.E.2d 161 (New York Court of Appeals, 2001)
De Kwiatkowski v. Bear Stearns & Co., Inc.
126 F. Supp. 2d 672 (S.D. New York, 2000)
Brothers v. Florence
739 N.E.2d 733 (New York Court of Appeals, 2000)
Vasile v. Dean Witter Reynolds Inc.
20 F. Supp. 2d 465 (E.D. New York, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
372 N.E.2d 555, 43 N.Y.2d 389, 401 N.Y.S.2d 767, 1977 N.Y. LEXIS 2473, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sears-roebuck-co-v-enco-associates-inc-ny-1977.