Dillingham Construction, N.A. v. Nadel Partnership, Inc.

64 Cal. App. 4th 264, 98 Daily Journal DAR 5576, 75 Cal. Rptr. 2d 207, 98 Cal. Daily Op. Serv. 4074, 1998 Cal. App. LEXIS 477
CourtCalifornia Court of Appeal
DecidedMay 27, 1998
DocketB111638
StatusPublished
Cited by14 cases

This text of 64 Cal. App. 4th 264 (Dillingham Construction, N.A. v. Nadel Partnership, Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dillingham Construction, N.A. v. Nadel Partnership, Inc., 64 Cal. App. 4th 264, 98 Daily Journal DAR 5576, 75 Cal. Rptr. 2d 207, 98 Cal. Daily Op. Serv. 4074, 1998 Cal. App. LEXIS 477 (Cal. Ct. App. 1998).

Opinion

Opinion

BARON, J.

Appellant the Nadel Partnership, Inc. (Nadel), an architecture firm, was found by a jury to be 10 percent liable for a discrete set of defects in a construction project which would cost $3,437,494 to repair. The cost of overall repairs to the project was estimated at up to $51 million by the plaintiff, who settled for a total of approximately $15 million paid by other defendants. On a cross-claim for indemnity brought by one of the settling defendants, the trial court allowed the jury to decide how much of the unallocated lump-sum settlement should be attributed to the defects for which Nadel was ultimately found responsible. The jury concluded that $4,658,677 of the $15 million settlement was reasonably paid toward those *268 claims. Based on the jury’s findings, the court ordered Nadel to pay cross-claimant $1,633,971 as its percentage share of the settlement entered into by the plaintiff and the settling defendants. 1

The trial court’s ruling meant that the cross-claimant was permitted to recover from nonsettling codefendant Nadel an amount in indemnity greatly in excess of that which the plaintiff could have recovered in actual damages from Nadel, based on the findings of the jury. Moreover, it was allowed to do so based on a finding that, despite having obtained a deep discount from plaintiff’s reported damages in the overall settlement, the settling defendants settled the one aspect for which Nadel was potentially responsible for in excess of $1 million more than it was worth. The evidence in support of the finding was the testimony of the attorney for cross-claimant, who was permitted to explain to the jury his understanding of how the settlement proceeds should be allocated.

Without deciding whether a good faith settlement in excess of actual damages can ever be determinative of a nonsettling defendant’s duty to indemnify, we conclude that, on the evidence before us, the cross-claimant cannot base its claim against Nadel on having paid more in settlement than plaintiff suffered in actual damages because: (1) the settling parties did not allocate settlement proceeds between those claims for which Nadel was potentially liable and those for which it was not; and, as a consequence, (2) the allocation was not subjected to a proper good faith determination under Code of Civil Procedure section 877.6. As a result, we further conclude that Nadel’s liability on the indemnity cross-claim is limited to 10 percent of $3,437,494, the amount found by the jury to represent its actual culpability.

Factual and Procedural Background

This case arises from the construction of a 416-unit luxury condominium project undertaken by developer Century Hill North Company (CHN). Respondent Dillingham Construction, N.A., Inc. (Dillingham) was the general contractor for phase I, consisting of buildings one, two, and three, and the Ray Wilson Company was the general contractor for phase II, consisting of buildings four, five, and six. The Century Park Place Condominium Association (the Association), representing the owners of the condominiums, brought suit against CHN, Dillingham, the Ray Wilson Company and others contending that there were defects in the design and construction of the condominiums. CHN and Dillingham cross-claimed against a number of *269 parties, including the large group of subcontractors involved in one or the other or both phases of the project, and appellant Nadel, which, along with Abraham Shapiro, was the architect for phase I. 2

1. The Settlement

After several years of litigation, most of the defendants and cross-defendants entered into a global settlement with the Association. Under the settlement agreement the Association settled with the “Developers/General Contractors” (identified as CHN, Watt Consolidated Partnership, Ocean Industries, Inc., Shapell Industries, Inc., Luxury Developers, Inc., Neu Properties, Inc., Dillingham, and the Ray Wilson Company) and a second group identified as “the Subcontractors.” 3

The total settlement amount was $15,220,659.07. CHN paid $3 million of this amount (or 19.71 percent) and Dillingham paid $4,165,000 (27.36 percent). The subcontractors group paid $4,908,009.07 (32.24 percent), and the $3,147,650 remainder (roughly 20 percent) was paid by the Ray Wilson Company. Under the terms of the settlement, the Association agreed to dismiss its entire complaint with prejudice, thereby freeing all potential defendants, settling and nonsettling, from further action by the plaintiff. CHN, Dillingham, and the Ray Wilson Company also agreed to mutually release each other and the settling subcontractors.

Dillingham took assignment of CHN’s cross-claim for indemnity and pursued that and its own claim for indemnity against nonsettling parties Nadel and Abraham Shapiro.

2. The Good Faith Determination

The settling parties moved for a good faith determination on the total amount of the settlement. In their moving papers, the parties revealed that the Association had prepared a repair estimate which showed a total cost to repair all defects of $51,777,886, of which $19,506,822 was designated to the category of “Architectural repairs[.]” In their moving papers, the parties asked the court to allocate the settlement contributions of CHN to buildings one through six and their associated common areas and appurtenances, and the $4,165,000 from Dillingham to buildings one through three and their *270 associated common areas and appurtenances." No other allocations were requested or discussed.

The trial court approved the good faith of the settlement, but stated in its minute order: “No allocation is being made at this time. It is the intention of the Court to proceed to a jury trial in which such an allocation will be made and if it takes thirty to forty-five days to reach a jury verdict, that is what will be done.”

Nonsettling subcontractor Lee Bolin petitioned for writ of mandate asking for an order from the trial court allocating the settlement proceeds between claims. The settling parties, including Dillingham, argued at that time that no allocation was necessary. The writ petition was summarily denied. (Lee Bolin & Associates, Inc. v. Superior Court (Aug. 9, 1996) B101898 [nonpub. opn.].)

3. The Evidence at Trial

The parties were in agreement that Nadel was only involved in phase I of the project, and that its culpability was limited to what are referred to as the “13 architectural defects” or “13 defects.”

To support the amount of damages actually suffered as the result of the 13 defects, Dillingham offered the testimony of its construction expert, Robert James, an architect who coordinated the work of the numerous experts retained by Dillingham, and who evaluated the plaintiff’s claims and the culpability of the various subcontractors.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

EFD USA v. Band Pro Film and Digital CA2/3
California Court of Appeal, 2026
Badr v. City of San Ramon
N.D. California, 2023
Scottsdale Ins. Co. v. Dickstein Shapiro LLP
389 F. Supp. 3d 794 (C.D. California, 2019)
City of Modesto v. The Dow Chemical Co.
California Court of Appeal, 2018
City of Modesto v. Dow Chemical Co.
California Court of Appeal, 2018
Raicevic v. Lopez CA4/1
California Court of Appeal, 2015
McMillin Companies, LLC v. American Safety Indemnity Co.
233 Cal. App. 4th 518 (California Court of Appeal, 2015)
In re A.R. CA4/3
California Court of Appeal, 2014
Res-Care Inc. v. Roto-Rooter Services Co.
753 F. Supp. 2d 970 (N.D. California, 2010)
Jhaveri v. Teitelbaum
176 Cal. App. 4th 740 (California Court of Appeal, 2009)
GACKSTETTER v. Frawley
38 Cal. Rptr. 3d 333 (California Court of Appeal, 2006)
Ehret v. Congoleum Corp.
73 Cal. App. 4th 1308 (California Court of Appeal, 1999)
Dillingham Const., NA v. NADEL PARTNERSHIP
75 Cal. Rptr. 2d 207 (California Court of Appeal, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
64 Cal. App. 4th 264, 98 Daily Journal DAR 5576, 75 Cal. Rptr. 2d 207, 98 Cal. Daily Op. Serv. 4074, 1998 Cal. App. LEXIS 477, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dillingham-construction-na-v-nadel-partnership-inc-calctapp-1998.