Dickmann v. Midwest Interstate Electrical Construction Co.

493 N.E.2d 33, 143 Ill. App. 3d 494, 97 Ill. Dec. 551, 1986 Ill. App. LEXIS 2220
CourtAppellate Court of Illinois
DecidedApril 30, 1986
DocketNo. 85-2227
StatusPublished
Cited by6 cases

This text of 493 N.E.2d 33 (Dickmann v. Midwest Interstate Electrical Construction Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dickmann v. Midwest Interstate Electrical Construction Co., 493 N.E.2d 33, 143 Ill. App. 3d 494, 97 Ill. Dec. 551, 1986 Ill. App. LEXIS 2220 (Ill. Ct. App. 1986).

Opinion

JUSTICE McNAMARA

delivered the opinion of the court:

Plaintiff, Lawrence Dickmann, appeals from an order of the trial court granting summary judgment in favor of defendant, Midwest Interstate Electrical Construction Company, on his one-count complaint alleging a cause of action under the Structural Work Act (Ill. Rev. Stat. 1979, ch. 48, par. 60 et seq.).

Plaintiff, a bricklayer, was injured on March 31, 1980, while working at a construction site in Chicago. He was employed by L. J. Graf, the masonry subcontractor at the site. Defendant was the general contractor for the construction project. The complaint alleges that defendant knowingly violated the Act when it failed to construct a scaffold so as to adequately protect plaintiff; failed to erect a scaffold using proper planking; failed to construct a scaffold with secured planking; and failed to provide proper scaffolding.

The contract between defendant and the owner of the property stated that defendant was responsible for all work specifically required of it, and that defendant would make a final inspection to insure completion of all contract requirements. Defendant was the general contractor and was in charge of all electrical work at the construction site. The contract stated that defendant would provide scaffolding for painters, but made no such provision for masonry work.

Defendant was installing an electrical service at the construction site. L. J. Graf, plaintiff’s employer, was to construct two brick walls for a room which would house electrical gear. Plaintiff was the only bricklayer at the site. L. J. Graf had no foreman there, and plaintiff received orders from his employer over the telephone. Plaintiff testified at his deposition that when he had a question he would ask defendant’s foreman at the site, Harry Hoye. Hoye testified at his deposition that he told plaintiff which wall was to go up first and where to start, but let plaintiff “take it from there.”

Plaintiff began working at the site one week before the accident occurred. In building the first wall, plaintiff used pipe scaffolding with 16-foot planks. The scaffolding was present at the site when plaintiff arrived, and was not owned by either of the parties. Hoye told plaintiff that when he built the second wall he could not block the gangway. Plaintiff replied that he only had the 16-foot planks. Plaintiff testified that Hoye then said: “Do what you can do with what you have got to work with.” Hoye testified that he did not recall this conversation, but that if plaintiff had blocked the gangway Hoye would have asked him not to do so. Plaintiff telephoned his employer several times during the week and requested shorter planks. None were provided. At this deposition, plaintiff also stated that Hoye knew “there was a problem or that [he] had asked for planks and *** didn’t have the right plank available.”

On the day of the accident, plaintiff began working on the second masonry wall. When the wall was approximately 56 inches high, plaintiff found a door and some two-by-four boards and proceeded to fashion a scaffold. Three to five minutes after plaintiff began using the scaffold, he moved in order to place a brick. The door slipped off the boards, and plaintiff fell backwards onto the door, injuring his back and neck. Plaintiff telephoned L. J. Graf to report the injury and to request an assistant. After the assistant arrived, plaintiff and he continued to use the same scaffold, but they nailed the door to the boards. After defendant filed its motion for summary judgment, the trial court heard oral arguments and granted defendant’s motion for summary judgment. The trial court found that there were no facts in the record to substantiate a wilful violation of the Act.

The goal of the Act is to provide workers in extrahazardous occupations with a safe place to work. (McNellis v. Combustion Engineering, Inc. (1974), 58 Ill. 2d 146, 151, 317 N.E.2d 573.) The Act is liberally construed in order to afford broad protection to working people. (58 Ill. 2d 146, 317 N.E.2d 573.) The Act generally requires all scaffolds to be erected and constructed in a safe, suitable and proper manner so as to adequately protect persons using the scaffolds. (Ill. Rev. Stat. 1979, ch. 48, par. 60.) To maintain an action under the Act, plaintiff must prove that he was engaged in or was passing under or by a structural activity; the activity was being performed with reference to a structure; a scaffold or other mechanical device was being used; a defect existed in the construction or use of the device; defendant had charge of the work; the defect proximately caused his injuries; and defendant wilfully violated the Act’s safety standards. (Rochan v. Commonwealth Edison Co. (1984), 123 Ill. App. 3d 844, 463 N.E.2d 921.) The questions of proximate cause and whether defendant wilfully violated the Act are at issue here.

The questions of proximate cause and wilful violations under the Act are ordinarily questions of fact for the jury. (Roedner v. Central Illinois Public Service Co. (1983), 117 Ill. App. 3d 81, 452 N.E.2d 842 (wilful violation); Rochan v. Commonwealth Edison Co. (1984), 123 Ill. App. 3d 844, 463 N.E.2d 921 (proximate cause).) They become questions of law only when the facts are not disputed and where there can be no difference in the judgment of reasonable persons on inferences to be drawn. St. John v. City of Naperville (1982) 108 Ill. App. 3d 519, 439 N.E.2d 12.

Plaintiff first contends that the trial court erred in granting summary judgment in favor of defendant because a genuine issue of material fact remains on the issue of wilful violation. We agree. The Act imposes liability for wilful violations of its provisions. (Simmons v. Union Electric Co. (1984), 104 Ill. 2d 444, 473 N.E.2d 946.) A wilful violation occurs when one having charge of the work knows that a dangerous condition exists on a scaffold or, by the exercise of reasonable care, could have discovered the existence of the dangerous condition. (Simmons v. Union Electric Co. (1984), 104 Ill. 2d 444, 473 N.E.2d 946; Moore v. Clearing Industrial District, Inc. (1978), 64 Ill. App. 3d 391, 380 N.E.2d 1063.) In the present case, plaintiff testified that defendant’s foreman, Hoye, instructed plaintiff not to block the gangway. When plaintiff replied that he had only the 16-foot planks, Hoye told him to use whatever materials he could. A question of fact remains as to whether this conversation took place and, if so, what inferences should be drawn from the conversation. A jury might reasonably infer that once Hoye told plaintiff to use any available materials, Hoye had a duty to make every effort to insure that plaintiff used proper materials in a safe manner.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
493 N.E.2d 33, 143 Ill. App. 3d 494, 97 Ill. Dec. 551, 1986 Ill. App. LEXIS 2220, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dickmann-v-midwest-interstate-electrical-construction-co-illappct-1986.