Diana Ruiz Esparza v. the University of Texas at El Paso

CourtCourt of Appeals of Texas
DecidedMay 8, 2023
Docket08-22-00094-CV
StatusPublished

This text of Diana Ruiz Esparza v. the University of Texas at El Paso (Diana Ruiz Esparza v. the University of Texas at El Paso) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Diana Ruiz Esparza v. the University of Texas at El Paso, (Tex. Ct. App. 2023).

Opinion

COURT OF APPEALS EIGHTH DISTRICT OF TEXAS EL PASO, TEXAS

DIANA RUIZ ESPARZA, § No. 08-22-00094-CV

Appellant, § Appeal from the

v. § County Court at Law No. 3

THE UNIVERSITY OF TEXAS AT § of El Paso County, Texas EL PASO, § (TC# 2013DCV4283) Appellee.

OPINION

BACKGROUND

In this employment discrimination case, Appellant challenges the grant of a plea to the

jurisdiction in favor of Appellee. We affirm.

Factual and Procedural Background

In 1999, Appellant, Diana Ruiz Esparza (Esparza), was employed by Appellee, University

of Texas at El Paso (UTEP), as a Construction Supervisor in the Planning and Construction

Department of its V.P. Office of Business Affairs. Although her job title has changed over the

years from construction supervisor to staff designer, her duties remained the same. Esparza’s Performance and Disciplinary Actions

The following is a summary of Esparza’s job performance and disciplinary actions leading

to her ultimate termination:

• January 31, 2008: Written warning issued for missing two mandatory meetings.

• February 4, 2008: Esparza recommended for suspension after missing a third mandatory meeting on February 1, 2008.

• March 17, 2008: Esparza missed another mandatory meeting on March 17, 2008 and was given notice of suspension. Esparza was thereby suspended for three days.

• October 8, 2009: Written Warning issued for “unacceptable conduct” regarding several projects.

• March 10, 2010: Notice of intent to suspend employment for failing to attend a meeting, poor communication with a client, and inability to properly execute the technical aspects of a project.

• March 22, 2010: Notice of suspension issued.

• March 23–25, 2010: Esparza was again suspended for three days.

UTEP continued to employ Esparza and provided her with assistance, counsel, resources,

and guidance to help improve her performance. Esparza’s poor job performance persisted, and on

September 10, 2013, UTEP issued its intent to terminate employment. The basis of the intent to

terminate letter is as follows:

[P]ersistent and significant issues with several projects that have been assigned to you. Poor communication, dissatisfied clients, scheduling and budgetary issues, and your inability to comply with Health, Safety, Welfare and Accessibility code requirements have caused an enormous waste and expenditure of material, labor and resources, and required unnecessary rework and costly management intervention.

The letter further provided a factual synopsis of the more recent project setbacks Esparza produced,

which according to UTEP, directly impacted its ability to serve its customers and deliver timely

2 completed projects. The letter outlining Esparza’s repeated failures leading to her ultimate

termination is as follows:

1. Engineering – Installation of new glass doors for cSETR Lab - Room E211

Scope: Two pairs of glass doors were requested by the client to be installed to create secure areas to stage materials to be tested in the lab. Upon completion of the material testing, the rooms will be used as lab workstations.

Performance issues: Building, life safety, and accessibility codes were not reviewed prior to purchase of these doors. Greg McNicol and I had advised you during our monthly review meeting that a review of code requirements should be performed and reviewed with Robert Parker or me prior to the execution of the work. Instead you ordered the custom doors and they were manufactured based on your specifications. The doors you purchased did not comply with code requirements, but because of a planned event they nonetheless had to be installed. Consequently the client’s funds were squandered, the product delivered was grossly inadequate, instead of a project being completed, it produced more work and ultimately, a new set of doors will have to be purchased that comply with all code requirements.

2. Memorial Gym – Ticket Office Renovations for Auxiliary Support

Scope: You were tasked with the renovation of a ticket counter, and from the onset of this project the client was frustrated and believed that you were not listening to their requests and needs.

Performance issues: Due to the client’s frustration a meeting was held on April 29th between Rob Parker, Jerri Herrera, Lillian Gallegos and you to work out the difficulties. At that time the client continued to express frustration with your poor communication on this project. As a result of your performance and behavior on this project (and others) you were given a Written Warning on May 21, 2013, for your refusal to follow instructions and displaying a confrontational attitude toward our clients.

This project was originally assigned to you in January of 2013 and was originally scheduled to be completed in March. Due to your inability to complete the task, the project deadline was moved to the end of the summer and still, you failed to meet the critical August project deadline. It is glaringly apparent that neither informal discussions nor formal disciplines have improved your performance.

As a result of the client’s ongoing frustration and your blatant disregard of their required security needs, the client requested that our department assign another

3 staff member to manage the completion of this project. A Project Manager has been assigned to complete this project and to properly schedule the contractors to do their work while providing a secure environment where cash and other valuables are present in the space, again an action you fail to coordinate with the clients.

3. Chase Bank Building – Reconfiguration of meeting rooms for College of Business Executive MBA Program

Scope: Representatives of the Business School requested that you develop a cost and a plan to consolidate two conference spaces into a larger one at the CHASE building and to have this space available for classes beginning the Fall 2013 Semester.

Performance issues: This project has been active for eight months under your responsibility, and as of August 1, 2013 the users had not been provided an established viable solution or a budget. Because of this, classes scheduled to take place in this space had to be cancelled for the fall semester. Due to your inaction the Dean for the College of Business has now cancelled this project, due to the lack of progress.

I have, on numerous occasions, informed all of our staff, including you, to review any and all design solutions with me for approval prior to presenting final solutions to clients for their review and approval. On August 3, 2013, you presented a design solution to the client for this project without my prior review and/or approval.

Additionally, after our Departmental Reorganization meeting which occurred on July 29th, 2013 thru an email you informed the Dean, Assistant Dean and CAO of the College of Business Administration that “I want to take the opportunity to inform you that the Department of Planning and Construction was reorganized and I will be no longer doing project management, construction management, processing the paper work, provide estimate to clients, ordering furniture, coordinating with vendors, etc.” The statement you provided is inaccurate unprofessional, and inappropriate, and such misinformation should not have been communicated to the client, which only added to confusion as to the status of the project.

Your actions on these projects have resulted in requiring our department to assign other staff members to these projects to ensure that they are properly completed. During the past 10 months Rob Parker and I have tried to provide you with assistance, counsel, resources and guidance to help you improve your performance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Medina v. Ramsey Steel Co Inc
238 F.3d 674 (Fifth Circuit, 2001)
Evans v. The City of Houston
246 F.3d 344 (Fifth Circuit, 2001)
McDonnell Douglas Corp. v. Green
411 U.S. 792 (Supreme Court, 1973)
Texas Department of Parks & Wildlife v. Miranda
133 S.W.3d 217 (Texas Supreme Court, 2004)
Bland Independent School District v. Blue
34 S.W.3d 547 (Texas Supreme Court, 2000)
Prairie View A&M University v. Diljit K. Chatha
381 S.W.3d 500 (Texas Supreme Court, 2012)
Crutcher, Alexandrea v. Dallas Independent School District
410 S.W.3d 487 (Court of Appeals of Texas, 2013)
Diana Ruiz Esparza v. University of Texas at El Paso
471 S.W.3d 903 (Court of Appeals of Texas, 2015)
the University of Texas at El Paso v. Diana Ruiz Esparza
510 S.W.3d 147 (Court of Appeals of Texas, 2016)
Alamo Heights Independent School District v. Catherine Clark
544 S.W.3d 755 (Texas Supreme Court, 2018)
Mission Consolidated Independent School District v. Garcia
372 S.W.3d 629 (Texas Supreme Court, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Diana Ruiz Esparza v. the University of Texas at El Paso, Counsel Stack Legal Research, https://law.counselstack.com/opinion/diana-ruiz-esparza-v-the-university-of-texas-at-el-paso-texapp-2023.