Diamond Match Co. v. Aetna Casualty & Surety Co.

213 P. 56, 60 Cal. App. 425, 1923 Cal. App. LEXIS 29
CourtCalifornia Court of Appeal
DecidedJanuary 11, 1923
DocketCiv. No. 2482.
StatusPublished
Cited by2 cases

This text of 213 P. 56 (Diamond Match Co. v. Aetna Casualty & Surety Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Diamond Match Co. v. Aetna Casualty & Surety Co., 213 P. 56, 60 Cal. App. 425, 1923 Cal. App. LEXIS 29 (Cal. Ct. App. 1923).

Opinion

*426 BURNETT, J.

The action was brought to recover on an undertaking executed by defendant to secure the payment by W. R. Zumwalt to plaintiff of the amount due for lumber and building material furnished to said Zumwalt for the construction of a public school building in Corning, Tehama County, and plaintiff recovered judgment for the sum of $6,553.54, with interest thereon from March 11, 1921, the date of the filing of the complaint. (Vi16 appeal is from the judgment and the contentions of appe lant are, first, that the complaint is fatally defective; second, that the findings do not support the judgment; and third, that interest should not have been allowed until the judgment was rendered.

The particular point as to the complaint is that there is no allegation that the under ¡aking was executed by defendant, and it is claimed that, although no demurrer was filed, the question goes to the sufficiency of the statement of a cause of action and can be raised at any time. Appellant relies upon San Francisco S. Co. v. Aetna I. Co., 7 Cal. App. 98 [93 Pac. 888], and similar decisions. In the first of these it was said: “It is elementar;! that in order to state a cause of action against a surety u()on an undertaking, the complaint must in some way allege dr show that the defendant executed or delivered the unde?taking.”

On the other hand, it is the conte fition of respondent that this fact sufficiently appears to witiistand a general demurrer or, at any rate, a cause of action is stated under the Public Works Bond Act of March 27, 1897 (Stats. 1897 p. 201), as amended in 1911 (Stats. 1911, p. 1422); and attention is called to the various allegations of the complaint setting out the corporate capacity of the parties, the fact that a contract in writing was executed on February 11, 1920, by said Zumwalt and said school district for the erection of a public school building; that said contract was duly recorded; that said Zumwalt “before entering upon the performance of said work duly filed with the said board of trustees ... a bond of which the following is a true and correct copy” (the bond being set out in full); that said bond was in the sum of not less than one-half of the total amount payable to the said W. R. Zumwalt by the terms of said contract, and that it was duly approved by said board of trustees before being filed; that plaintiff sold to said Zumwalt lumber and building materal of the value *427 of $16,507.33 to be used and which were used in said building, the amount paid and the balance still due on said claim were also alleged; that the work was finished on January 15, 1921, and that the notice of completion was filed in the county recorder’s office on January 20, 1921; that on December 17, 1920, plaintiff filed with said board of trustees its verified statement of claim against the contractor and “that ninety days have not elapsed since the completion and acceptance of said building or since the filing of said verified claim.”

Whether there should have been an additional specific allegation that said undertaking was executed by defendant it is unnecessary to decide for the reason that it is entirely apparent .that, under the peculiar facts of the ease, appellant was not prejudiced by the absence of such allegation and it should not be permitted to raise the objection now. This will appear from the following statement: The default of defendant was entered for its failure to appear, but thereafter on motion the default was set aside and an answer was filed in which the .only issue tendered was as to the amount due to plaintiff from said Zumwalt, defendant claiming that it was $6,431.18 instead of $7,158.54 as claimed by plaintiff. Thereafter, on June 15, 1921, an amendment to the answer was filed, stating the amount due to be $6,297.68 and praying “that plaintiff take judgment for no greater sum than the sum of $6,297.68.” Another amendment was subsequently filed after trial in which it was claimed that Zumwalt was entitled to a credit of $234.10 for work done by him which should have been done by plaintiff. Since a copy of the undertaking was set out in the complaint, the case is one for the application of section 447 of the Code of Civil Procedure, providing: “When an action is brought upon a written. instrument, and the complaint contains a copy of such instrument, or a copy is annexed thereto, the genuineness and due execution of such instrument are deemed admitted, unless the answer denying the same be verified.”

Herein there was no denial of the same, the only denial being, as we have seen, as to the exact amount which was due. Appellant claims that the section furnishes a rule of evidence but not of pleading. If we concede that it is thus correctly characterized, it cannot be disputed that the sitúa *428 tion is the same in effect as if the appellant had admitted or stated in open court that said undertaking was genuine and was duly executed. Indeed, in view of said exhibition of the bond and the only denial of the answer as to the amount due, the court was called upon to try only that one issue and appellant is in the same situation as though it had admitted that such was the only controversy in the case. Under such circumstances the practical and sensible rule in-the interest of the expeditious administration of justice precludes an appellant from successfully maintaining on appeal that one of the material issues was not sufficiently presented by the complaint. Indeed, the case is the -same in principle as though there was an agreed statement of all the material facts except the single one to which we have referred.

This phase of the matter is governed by the principle announced in such cases as Cushing v. Pires, 124 Cal. 663 [57 Pac. 572]; Throop v. Weaver, 180 Cal. 335 [181 Pac. 55]; Slaughter v. Goldberg, Bowen & Co., 26 Cal. App. 318 [147 Pac. 90]; Boyle v. Coast Improvement Co., 27 Cal. App. 714 [151 Pac. 25]; Rupert v. Hunter, 40 Cal. App. 96 [180 Pac. 638].

In the first of these it is said: “It is true that the objection that the complaint does not state a cause of action may be -successfully made for the first time on appeal, but the appellate court will not be over zealous to find a defect in a complaint that the appellant himself failed to discover until the case had been decided against him on its merits.”

In the second, the court declares: “Appellants also make the point that the cross-complaint does not state a cause of action, their criticism really being that the cause of action pleaded is not a proper matter for cross-complaint. Conceding this to be true, they cannot here raise the point as they joined issue upon said cross-complaint and went to trial without demurring or objecting.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shellenberger v. Baker
281 P. 1102 (California Court of Appeal, 1929)
People v. McDonald
255 P. 180 (California Supreme Court, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
213 P. 56, 60 Cal. App. 425, 1923 Cal. App. LEXIS 29, Counsel Stack Legal Research, https://law.counselstack.com/opinion/diamond-match-co-v-aetna-casualty-surety-co-calctapp-1923.