Developers Surety & Indemnity Co. v. Lipinski

2017 IL App (1st) 152658
CourtAppellate Court of Illinois
DecidedAugust 24, 2017
Docket1-15-2658
StatusUnpublished
Cited by2 cases

This text of 2017 IL App (1st) 152658 (Developers Surety & Indemnity Co. v. Lipinski) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Developers Surety & Indemnity Co. v. Lipinski, 2017 IL App (1st) 152658 (Ill. Ct. App. 2017).

Opinion

2017 IL App (1st) 152658

No. 1-15-2658

August 22, 2017

SECOND DIVISION

IN THE

APPELLATE COURT OF ILLINOIS

FIRST DISTRICT

DEVELOPERS SURETY AND INDEMNITY ) Appeal from the Circuit Court COMPANY, an Iowa Corporation, By and ) Of Cook County. Through Its Underwriting Manager and ) Authorized Agent, Insco Insurance ) Services, Inc., a California Corporation, ) No. 12 L 3758 ) Plaintiff-Appellant, ) The Honorable ) Raymond W. Mitchell, v. ) Judge Presiding. ) MARC S. LIPINSKI, Individually; ) DONNELLY, LIPINSKI & HARRIS, LLC, ) an Illinois Limited Liability Company; and ) RIORDAN, DONNELLY, LIPINSKI & ) McKEE, LTD., an Illinois Corporation, ) ) Defendants-Appellees. )

JUSTICE NEVILLE delivered the judgment of the court, with opinion.

Presiding Justice Hyman concurred in the judgment.

Justice Mason specially concurred in the judgment, with opinion.

OPINION

¶1 Developers Surety and Indemnity Company (DSI) filed a complaint for legal

malpractice against Marc S. Lipinski. After years of litigation, DSI admitted that insurance

had compensated it for all losses it suffered due to the alleged malpractice. DSI argued that No. 1-15-2568

under the collateral source rule, Lipinski should not benefit from DSI’s insurance, so the

insurance should not affect the award of damages. DSI admitted that it owed to its insurers

all damages it recovered from Lipinski. The trial court held that the collateral source rule did

not apply in legal malpractice actions. Because DSI could not prove any damages from the

alleged malpractice, the court dismissed the complaint.

¶2 In this appeal, we hold that section 2-403 of the Code of Civil Procedure (Code) (735

ILCS 5/2-403 (West 2012)) required DSI to name its insurers, the real parties in interest, as

plaintiffs. Because the plaintiffs violated section 2-403, we affirm the dismissal of the

complaint.

¶3 BACKGROUND

¶4 The Underlying Litigation

¶5 The University of Chicago hired IRB Construction Partners (IRB) to act as general

contractor to construct a building for the university. IRB subcontracted some of the work to

F.E. Moran, Inc. (Moran), and Moran, in turn, subcontracted some of its work to 3D

Industries, Inc (3D). 3D paid a premium to DSI, and DSI issued performance and payment

bonds, guaranteeing to Moran, as obligee, that 3D, as principal, would complete its work.

¶6 In early May 2005, 3D’s employees walked off the job, leaving 3D’s work incomplete.

DSI assigned Moran’s claim on the bonds to its claims handler, Daniel Berge. DSI retained

the law firm of Riordan, Donnelly, Lipinski & McKee as surety counsel, and Lipinski served

as counsel to DSI for Moran’s claim.

No. 1-15-2568

¶7 On May 25, 2005, Lipinski sent Berge an email informing Berge that Moran had hired

workers to complete 3D’s work. DSI hired Steve Carlino as an expert to estimate the cost for

completion of 3D’s work. On June 2, 2005, Hal Emalfarb, attorney for Moran, sent a letter to

Lipinski, saying:

“FE Moran’s initial estimate of the cost to complete the 3D Industries, Inc. work

is $792,594.00 (estimate to follow). In addition the unpaid suppliers total

$582,905.85 *** and the union may be owed over $100,000 for total obligations

to complete 3D’s contractual obligations of $1,421,499.85[ ] against a

subcontract balance of $478,496.24[ ] leaving a possible deficit estimated (to be

reviewed) at $943,003.61[ ] of 3D’s outstanding obligations under the bonded

subcontract.

*** [D]emand is again made on the surety to pay the unpaid suppliers ***

and to cash flow the labor to complete the work. ***

*** [T]he surety’s failure to timely respond will be in bad faith as

determining a supplier’s payment bond claim should take less th[a]n an hour

especially since your principal swore under oath [t]he amounts due each

supplier. ***

FE Moran has been forced against its will to take over 3D’s obligations to

perform the bonded subcontract. Is the surety looking for a replacement

contractor? Does the surety agree to fund the bonded incomplete subcontract

work by consenting to placing 3D’s employees and other Union laborers on its

payroll? The delay in a decision is not without substantial financial harm to FE

Moran.”

¶8 Carlino estimated that Moran would need to spend about $200,000 to complete 3D’s

work. Because Moran had paid 3D $478,496.24 less than the amount it agreed to pay 3D if

3D completed its work, according to Carlino, 3D and DSI owed Moran nothing and Moran

still owed 3D a substantial amount for the work 3D had completed before it stopped working.

¶9 In September 2005, 3D filed a complaint against Moran, charging Moran with breaching

their contract by failing to make payments when due. 3D claimed that Moran’s failure to pay

left 3D with inadequate funds to pay its employees, leading 3D’s employees to walk off the

job.

¶ 10 Moran responded with a letter to DSI setting out its out of pocket expenses due to 3D’s

failure to complete its work and DSI’s failure to meet its obligations under the bonds. Berge

sent Moran a letter formally denying Moran’s claims on the bonds in November 2005.

¶ 11 Moran answered 3D’s complaint and filed a counterclaim against 3D for breach of

contract and fraud. Moran added a third-party claim against DSI for failure to fulfill its duties

as surety and for acting in bad faith when it denied Moran’s claims. Moran’s attorney drafted

a settlement agreement in November 2005. The parties did not reach a settlement at that time.

DSI and Moran engaged in extensive discovery and trial preparation from 2005 through

2009.

¶ 12 In 2010, DSI’s general counsel decided to bring in another law firm to help with

preparing 3D Industries, Inc. v. F.E. Moran, Inc., No. 05-CH-15386 (Cir. Ct. Cook Co.) (3D

v. Moran), for trial. The new law firm, Tressler LLP, prepared an extended report, dated June

2010, explaining its analysis of the litigation. According to Tressler, 3D had very weak

evidence to support its claim that Moran breached the contract. Moran had strong evidence

that 3D breached the contract, and Moran had strong support for almost all of its settlement

demand for about $5 million. Tressler also found that “there is a risk that Moran may prevail

against [DSI] under the statutory bad faith count. *** [DSI] may have difficulty [proving]

that, to the extent it relied on Carlino’s report, that such reliance was justified or at least not

misplaced.” Tressler recommended an “aggressive settlement strategy,” with “the settlement

range of this matter to be in the area $3,500,000-$4,000,000.”

¶ 13 In August and September 2010, DSI, Moran, and other affected parties settled all the

claims in 3D v. Moran. DSI paid Moran $3.7 million.

¶ 14 Legal Malpractice Litigation

¶ 15 On April 6, 2012, DSI filed a complaint for legal malpractice, naming as defendants (1)

Lipinski, (2) the law firm of Riordan, Donnelly, Lipinski & McKee , and (3) the law firm of

Donnelly, Lipinski & Harris, LLC, for whom Lipinski worked in 2010. DSI alleged that

Lipinski breached his duties as an attorney and that, because of Lipinski’s failures, DSI lost

the opportunity to settle 3D v. Moran in 2005 at a price far less than the $3.7 million DSI

eventually paid.

¶ 16 Lipinski asked in discovery for information concerning DSI’s recovery from reinsurers

for the payments it made in 3D v. Moran.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Piasa Armory, LLC v. Raoul
Illinois Supreme Court, 2025
Developers Surety & Indemnity Co. v. Lipinski
2017 IL App (1st) 152658 (Appellate Court of Illinois, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
2017 IL App (1st) 152658, Counsel Stack Legal Research, https://law.counselstack.com/opinion/developers-surety-indemnity-co-v-lipinski-illappct-2017.