Developers Surety & Indemnity Co. v. Lipinski

2017 IL App (1st) 152658
Appellate Court of Illinois·Decided December 18, 2017·No. 1-15-2658·Published·Cited by 2 cases

Opinion

Digitally signed by Reporter of Decisions Reason: I attest to the Illinois Official Reports accuracy and integrity of this document Appellate Court Date: 2017.12.06 12:16:42 -06'00'

Developers Surety & Indemnity Co. v. Lipinski, 2017 IL App (1st) 152658

Appellate Court DEVELOPERS SURETY AND INDEMNITY COMPANY, an Iowa Caption Corporation, By and Through Its Underwriting Manager and Authorized Agent, Insco Insurance Services, Inc., a California Corporation, Plaintiff-Appellant, v. MARC S. LIPINSKI, Individually; DONNELLY, LIPINSKI & HARRIS, LLC, an Illinois Limited Liability Company; and RIORDAN, DONNELLY, LIPINSKI & McKEE, LTD., an Illinois Corporation, Defendants- Appellees.

District & No. First District, Second Division Docket No. 1-15-2658

Rule 23 order filed June 30, 2017 Motion to publish allowed August 18, 2017 Rehearing denied August 18, 2017 Opinion filed August 22, 2017

Decision Under Appeal from the Circuit Court of Cook County, No. 12-L-3758; the Review Hon. Raymond W. Mitchell, Judge, presiding.

Judgment Affirmed.

Counsel on Grasso Bass, P.C., of Hinsdale (Gary A. Grasso and Adam R. Bowers, Appeal of counsel), for appellant. Donohue Brown Matthewson & Smyth, LLC, of Chicago (John J. Duffy, Karen Kies De Grand, and Michael G. Carney, of counsel), for appellees.

Panel JUSTICE NEVILLE delivered the judgment of the court, with opinion. Presiding Justice Hyman concurred in the judgment and opinion. Justice Mason specially concurred, with opinion.

OPINION

¶1 Developers Surety and Indemnity Company (DSI) filed a complaint for legal malpractice against Marc S. Lipinski. After years of litigation, DSI admitted that insurance had compensated it for all losses it suffered due to the alleged malpractice. DSI argued that under the collateral source rule, Lipinski should not benefit from DSI’s insurance, so the insurance should not affect the award of damages. DSI admitted that it owed to its insurers all damages it recovered from Lipinski. The trial court held that the collateral source rule did not apply in legal malpractice actions. Because DSI could not prove any damages from the alleged malpractice, the court dismissed the complaint. ¶2 In this appeal, we hold that section 2-403 of the Code of Civil Procedure (Code) (735 ILCS 5/2-403 (West 2012)) required DSI to name its insurers, the real parties in interest, as plaintiffs. Because the plaintiffs violated section 2-403, we affirm the dismissal of the complaint.

¶3 BACKGROUND ¶4 The Underlying Litigation ¶5 The University of Chicago hired IRB Construction Partners (IRB) to act as general contractor to construct a building for the university. IRB subcontracted some of the work to F.E. Moran, Inc. (Moran), and Moran, in turn, subcontracted some of its work to 3D Industries, Inc (3D). 3D paid a premium to DSI, and DSI issued performance and payment bonds, guaranteeing to Moran, as obligee, that 3D, as principal, would complete its work. ¶6 In early May 2005, 3D’s employees walked off the job, leaving 3D’s work incomplete. DSI assigned Moran’s claim on the bonds to its claims handler, Daniel Berge. DSI retained the law firm of Riordan, Donnelly, Lipinski & McKee, Ltd., as surety counsel, and Lipinski served as counsel to DSI for Moran’s claim. ¶7 On May 25, 2005, Lipinski sent Berge an e-mail informing Berge that Moran had hired workers to complete 3D’s work. DSI hired Steve Carlino as an expert to estimate the cost for completion of 3D’s work. On June 2, 2005, Hal Emalfarb, attorney for Moran, sent a letter to Lipinski, saying: “FE Moran’s initial estimate of the cost to complete the 3D Industries, Inc. work is $792,594.00 (estimate to follow). In addition the unpaid suppliers total $582,905.85 *** and the union may be owed over $100,000 for total obligations to complete 3D’s

-2- contractual obligations of $1,421,499.85[ ] against a subcontract balance of $478,496.24[ ] leaving a possible deficit estimated (to be reviewed) at $943,003.61[ ] of 3D’s outstanding obligations under the bonded subcontract. *** [D]emand is again made on the surety to pay the unpaid suppliers *** and to cash flow the labor to complete the work. *** *** [T]he surety’s failure to timely respond will be in bad faith as determining a supplier’s payment bond claim should take less th[a]n an hour especially since your principal swore under oath [t]he amounts due each supplier. *** FE Moran has been forced against its will to take over 3D’s obligations to perform the bonded subcontract. Is the surety looking for a replacement contractor? Does the surety agree to fund the bonded incomplete subcontract work by consenting to placing 3D’s employees and other Union laborers on its payroll? The delay in a decision is not without substantial financial harm to FE Moran.” ¶8 Carlino estimated that Moran would need to spend about $200,000 to complete 3D’s work. Because Moran had paid 3D $478,496.24 less than the amount it agreed to pay 3D if 3D completed its work, according to Carlino, 3D and DSI owed Moran nothing and Moran still owed 3D a substantial amount for the work 3D had completed before it stopped working. ¶9 In September 2005, 3D filed a complaint against Moran, charging Moran with breaching their contract by failing to make payments when due. 3D claimed that Moran’s failure to pay left 3D with inadequate funds to pay its employees, leading 3D’s employees to walk off the job. ¶ 10 Moran responded with a letter to DSI setting out its out of pocket expenses due to 3D’s failure to complete its work and DSI’s failure to meet its obligations under the bonds. Berge sent Moran a letter formally denying Moran’s claims on the bonds in November 2005. ¶ 11 Moran answered 3D’s complaint and filed a counterclaim against 3D for breach of contract and fraud. Moran added a third-party claim against DSI for failure to fulfill its duties as surety and for acting in bad faith when it denied Moran’s claims. Moran’s attorney drafted a settlement agreement in November 2005. The parties did not reach a settlement at that time. DSI and Moran engaged in extensive discovery and trial preparation from 2005 through 2009. ¶ 12 In 2010, DSI’s general counsel decided to bring in another law firm to help with preparing 3D Industries, Inc. v. F.E. Moran, Inc., No. 05-CH-15386 (Cir. Ct. Cook Co.) (3D v. Moran), for trial. The new law firm, Tressler LLP, prepared an extended report, dated June 2010, explaining its analysis of the litigation. According to Tressler, 3D had very weak evidence to support its claim that Moran breached the contract. Moran had strong evidence that 3D breached the contract, and Moran had strong support for almost all of its settlement demand for about $5 million. Tressler also found that “there is a risk that Moran may prevail against [DSI] under the statutory bad faith count. *** [DSI] may have difficulty [proving] that, to the extent it relied on Carlino’s report, that such reliance was justified or at least not misplaced.” Tressler recommended an “aggressive settlement strategy,” with “the settlement range of this matter to be in the area $3,500,000-$4,000,000.” ¶ 13 In August and September 2010, DSI, Moran, and other affected parties settled all the claims in 3D v. Moran. DSI paid Moran $3.7 million.

-3- ¶ 14 Legal Malpractice Litigation ¶ 15 On April 6, 2012, DSI filed a complaint for legal malpractice, naming as defendants (1) Lipinski; (2) the law firm of Riordan, Donnelly, Lipinski & McKee, Ltd.; and (3) the law firm of Donnelly, Lipinski & Harris, LLC, for whom Lipinski worked in 2010. DSI alleged that Lipinski breached his duties as an attorney and that, because of Lipinski’s failures, DSI lost the opportunity to settle 3D v. Moran in 2005 at a price far less than the $3.7 million DSI eventually paid.

Free access — add to your briefcase to read the full text and ask questions with AI

Developers Surety & Indemnity Co. v. Lipinski, 2017 IL App (1st) 152658 (Ill. Ct. App. 2017).

2017 IL App (1st) 152658 (Developers Surety & Indemnity Co. v. Lipinski) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Developers Surety & Indemnity Co. v. Lipinski
2017 IL App (1st) 152658 (Appellate Court of Illinois, 2017)