Derosier v. New England Telephone & Telegraph Co.

130 A. 145, 81 N.H. 451, 1925 N.H. LEXIS 41
CourtSupreme Court of New Hampshire
DecidedJanuary 26, 1925
StatusPublished
Cited by32 cases

This text of 130 A. 145 (Derosier v. New England Telephone & Telegraph Co.) is published on Counsel Stack Legal Research, covering Supreme Court of New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Derosier v. New England Telephone & Telegraph Co., 130 A. 145, 81 N.H. 451, 1925 N.H. LEXIS 41 (N.H. 1925).

Opinions

I. It was the plaintiff's contention at the trial that injuries to a lineman by coming in contact with the defendant's telephone cable and the traction company's electricity were naturally to be apprehended from the usual and ordinary method of doing a lineman's work, and that it was therefore the defendant's duty to provide against that danger by installing a guard arm above the cable with which Derosier came in contact. In support of this position the plaintiff relied upon a printed rule adopted by the defendant and upon a similar provision in its contract with the traction company for the use of joint poles. Each provided for the maintenance of guard arms above the defendant's cables under circumstances therein prescribed. Reliance was also placed upon the earlier custom of the defendant to maintain such guard arms, of which it was claimed the rule and contract simply gave written expression.

There was evidence from which it could be found that, for some twelve or fifteen years prior to the accident, whenever the defendant's cables were attached directly to jointly used wooden poles within six feet below electric light wires supported by the same pole, it was the defendant's practice to maintain guard arms, parallel with and three fourths of an inch to an inch above the suspension wires supporting its cables. These arms, four feet long, four inches thick, and three and one half inches wide, were fastened to the pole by lags or bolts. The year last preceding the accident the defendant put into effect rules for the construction and maintenance of jointly used wooden pole lines, a material portion of which reads, "Where a suspension wire, carrying Class C. cable or wires, is attached directly to the pole and the suspension wire is less than seventy-two inches below the lowest Class B. attachment in the Class B. space, a wooden guard arm shall be attached to the pole immediately above and substantially parallel to such suspension wire. The guard arm shall be at least forty-eight inches in length and shall be securely fastened to the pole. On corner poles, where the cable turns, the guard arm shall be placed along the climbing side of the pole." The defendant's cable and wire were of Class C., and the light company's wires above were Class B. attachments. Contemporaneously with the adoption of these rules the defendant entered into a written agreement with the light company, a material provision of which reads, "Where the messenger wire is below the electric light lines it shall be placed upon *Page 455 the pole at a vertical distance of not less than four feet below the lowest cross-arm occupied by the Lighting Company. Where the messenger wire is below the electric light lines and at a distance not exceeding six (6) feet from the lowest cross-arm carrying those lines measured vertically to the messenger wire at the point of support, the Telephone Company shall place upon the pole immediately above the messenger wire, and substantially parallel but not in contact therewith, a standard wooden cross-arm not less than four (4) feet in length, which shall be fastened at its center to the pole by the equivalent of at least two standard cross-arm lag bolts."

The plaintiff offered the practice, rule and contract as evidence of the recognition by the defendant of the dangers of the situation, and as an admission that the protection of a guard arm in the manner provided by the rule was required for the safety of linemen in the situation Derosier was in at the time he was injured. Her contention was that the guard provided for by the rule was designed to minimize all the dangers that a lineman ran of coming in contact with an electric current and the defendant's cable at the same time; that the required guard, if installed, would have prevented the accident; and that the defendant's failure to install it was therefore the cause of Derosier's injury. On the other hand the defendant contended that the guard arm required by the rule was not designed to furnish protection against the danger which caused the injury to Derosier, but that its purpose was solely for the use of the lineman as a foot rest while he was working on the electric wires above, as a protection both to the lineman and to the defendant's wire and cable. The question thus raised as to the purpose of a guard arm under the contract, rule and custom of the defendant was submitted to the jury with instructions.

Notwithstanding that the construction of a contract or other written document primarily presents a question for the court, nevertheless, when the construction or application of the document involves the determination of questions of fact outside of the writing, the intention of the parties may be submitted to the jury upon proper instructions. Bartlett v. Hoyt,33 N.H. 151, 165, 166; Folsom v. Plumer, 43 N.H. 469, 472; Field v. Tenney,47 N.H. 513, 521; Hall v. Brown, 58 N.H. 93, 98; Robin v. Bartlett,64 N.H. 426, 428; Hill v. Carr, 78 N.H. 458, 460. In such case the rights of the parties can be abundantly protected by exceptions to the charge or refusal to charge. Whichever method is adopted, such construction is, however, reviewable by this court, when the writing and the evidence or facts are *Page 456 fully transferred, as they are here. Kidd v. Traction Co., 74 N.H. 160,170; Kendall v. Green, 67 N.H. 557, 562, 563; Emery v. Dana, 76 N.H. 483,486.

So far as the legal principles here under discussion apply equally to the contract and the rule, the two provisions will be treated as one and referred to as the rule. The rule requiring a guard arm above cables is valueless as evidence of the defendant's negligence unless it can be construed as an admission by the defendant of a duty owed the plaintiff, the failure of the performance of which resulted in his injury. Carr v. Electric Co., 70 N.H. 308, 310. If the required guard was designed only to protect linemen from the ordinary risk of double contact with the defendant's cable and the electric company's wires, manifestly it does not help the plaintiff, since the electric wires are required by the same rules to be forty inches above the defendant's suspension wire, and Derosier had not reached the danger zone. To avail the plaintiff here the purpose must have been much broader, or, to be explicit, it must have included the protection of linemen, while climbing poles, from unexpected dangers arising from escaped electric current.

While the rule does not explicitly define the purpose of the guard arm, such purpose seems reasonably clear.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McKenzie v. Sevier
West Virginia Supreme Court, 2020
Owens v. Republic of Sudan
412 F. Supp. 2d 99 (District of Columbia, 2006)
Meyers v. Epstein
282 F. Supp. 2d 151 (S.D. New York, 2003)
King v. Prudential Property & Casualty Insurance
684 F. Supp. 347 (D. New Hampshire, 1988)
Siciliano v. Capitol City Shows, Inc.
475 A.2d 19 (Supreme Court of New Hampshire, 1984)
Young v. Abalene Pest Control Services, Inc.
444 A.2d 514 (Supreme Court of New Hampshire, 1982)
Barrett v. Foster Grant Co.
321 F. Supp. 784 (D. New Hampshire, 1970)
Corson v. Liberty Mutual Insurance
265 A.2d 315 (Supreme Court of New Hampshire, 1970)
Seidel v. GREENBERG
260 A.2d 863 (New Jersey Superior Court App Division, 1969)
M. C. Carlisle & Co., Inc. v. Robert W. Cross
386 F.2d 672 (First Circuit, 1967)
Marshall v. Nugent
222 F.2d 604 (First Circuit, 1955)
Gibson v. Garcia
216 P.2d 119 (California Court of Appeal, 1950)
Hannah v. Gulf Power Co.
128 F.2d 930 (Fifth Circuit, 1942)
Atherton v. Rowe
195 A. 676 (Supreme Court of New Hampshire, 1937)
Smith v. Boston & Maine Railroad
177 A. 729 (Supreme Court of New Hampshire, 1935)
Brackett v. Bellows Falls Hydro-Electric Corp.
175 A. 822 (Supreme Court of New Hampshire, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
130 A. 145, 81 N.H. 451, 1925 N.H. LEXIS 41, Counsel Stack Legal Research, https://law.counselstack.com/opinion/derosier-v-new-england-telephone-telegraph-co-nh-1925.