Denison Mines (USA) Corporation v. KGL Associates

2016 UT App 171, 381 P.3d 1167, 819 Utah Adv. Rep. 7, 2016 Utah App. LEXIS 178, 2016 WL 4255019
CourtCourt of Appeals of Utah
DecidedAugust 11, 2016
Docket20150049-CA
StatusPublished
Cited by2 cases

This text of 2016 UT App 171 (Denison Mines (USA) Corporation v. KGL Associates) is published on Counsel Stack Legal Research, covering Court of Appeals of Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Denison Mines (USA) Corporation v. KGL Associates, 2016 UT App 171, 381 P.3d 1167, 819 Utah Adv. Rep. 7, 2016 Utah App. LEXIS 178, 2016 WL 4255019 (Utah Ct. App. 2016).

Opinion

Opinion

CHRISTIANSEN, Judge:

¶1 KGL Associates Inc. (KGL) appeals from the order of the district court confirming an arbitration award in favor of Denison Mines Corporation and Denison White Mesa LLC (collectively, Denison). We affirm.

BACKGROUND

¶2 This case arises from a breach of contract action. In October 2009, Denison contracted with KGL to construct a mill tailings cell at the White Mesa Mill near Blanding, Utah, for a lump sum of $4,339,350. During construction, Denison issued several change orders, which increased KGL’s compensation by approximately $724,000. Denison also accelerated payments and advanced money to KGL to assist KGL with its cash flow problems. After Denison refused to issue additional change orders that KGL proposed, KGL unilaterally terminated the parties’ contract, abandoned the project prior to completion, and acquired a lien on Denison’s property. Additionally, KGL filed a lis pendens against Denison’s property.

¶3 Before KGL walked off the project, Denison had.paid or advanced KGL-all but $454,000 of the approximately $5,063,000 adjusted contract price. Moreover, when KGL walked off the project, it was more than $2 million in arrears in its payments to subcontractors and suppliers, triggering further lien and bond claims against Denison and its property. Denison settled with these subcontractors and suppliers for roughly $1,860,000 and spent approximately $355,000 completing the project.

¶4 Ultimately, Denison and KGL agreed to submit their dispute to binding arbitration, and on August 23, 2013, they entered into an agreement to arbitrate (the Arbitration Agreement). Among other things, the Arbitration Agreement provided that the arbitrator would “have until December 31, 2013 to render his interim award, in the form of a brief written, reasoned award, not to exceed 5 pages in length.” The Arbitration Agreement also provided:

The Arbitrator shall decide which party is the prevailing party ... and shall, consistent therewith, award arbitrator’s fees, costs and expenses, reasonable' attorney’s fees and costs to the prevailing party. Proof of attorney’s fees and other costs recoverable by the prevailing party shall follow the Arbitrator’s interim award on the merits.... The final award shall be issued no later than 30 days after the submission of proof of attorney’s fees -and costs, but no later than February 28, 2014.

¶5 The parties’ dispute encompassed nine claims by Denison for affirmative relief, three claims by KGL for affirmative relief, and multiple affirmative defenses by both *1171 parties. At the conclusion of the arbitration hearing, the arbitrator informed the parties that it might take him more than five pages to provide a reasoned award due to the magnitude of the case. Neither party objected. In addition, the parties agreed to extend the deadline for the arbitrator to issue his interim award (the Interim Award) to January 10, 2014.

¶6 On January 10, 2014, the arbitrator advised the parties that he was having computer difficulties and that he would not be able to issue the Interim Award until January 11. Neither party objected to the delay. On January 11, the arbitrator issued a nineteen-page Interim Award, explaining that the “Award exceeded] counsel’s requested page limitation due to the complexity of some issues which require[d] elaboration.” 2 Among other things, the arbitrator determined that KGL had mismanaged its work on the project, had abandoned the project, and' had materially breached the parties’ contract. Therefore, the arbitrator determined that Denison’s “completion actions and decisions were justified” and that Denison was entitled to its reasonable costs of completion after KGL’s abandonment of the project. In addition, the arbitrator rejected KGL’s fraud in the inducement defense and concluded that KGL had not demonstrated it was entitled to a monetary award. The arbitrator then awarded damages and interest to Denison totaling $3,989,654, subject to Denison submitting ‘Verified statements based on generally accepted accounting principles to confirm those amounts [the arbitrator] tentatively allowed” and to “confirm[] that the costs in the records total said amounts and that they do not arise from other causes.”

¶7 On January 30, 2014, KGL objected to the Interim Award and the arbitrator’s request for verification, arguing that the arbitrator lacked the authority to reopen the hearing or to request additional evidence “related to the underlying claims presented for resolution at the hearing.” KGL asserted that the Interim Award did not comply with the Arbitration Agreement, because it failed to resolve all of the issues submitted for resolution. In addition, KGL asked the arbitrator to modify the Interim Award to reject Denison’s • claims and to find that KGL was the prevailing party. On February 7, Denison responded to KGL’s objections and argued that its damages claims were supported by the evidence from the arbitration hearing and that additional information was unnecessary. Nevertheless, in response to the arbitrator’s request, Denison provided a “Verification Statement” and declarations from three hearing witnesses.

¶8 On February 28, 2014, the arbitrator issued his final award (the Final Award), changing none .of the prevailing-party determinations or the amount of damages or interest awarded to Denison in the Interim Award. Furthermore, as contemplated by the Arbitration Agreement, the Final Award included an additional award to Denison for attorney fees and costs, bringing the total award to $4,820,043.99. That same day, the arbitrator issued an “Arbitrator Ruling on KGL Objections and Other Considerations,” wherein he removed his request in the Interim Award for verification by Denison. The arbitrator stated that he had “reconsidered the record,” that it was “sufficient in and of itself,” and that he had not considered Deni-son’s response to his request for verification. Denison then filed a motion in the district court to confirm the Final Award, and KGL filed a counter-motion to have the Final Award vacated.

¶9 Among other things, KGL contended that the Interim Award was untimely because (1) the Interim Award failed to “offer a brief, reasoned decision” on two of. KGL’s three change-order claims; (2) the arbitrator “did not issue a final Award on the merits” of Denison’s claims in the Interim Award because he asked for verification of Denison’s damages; and (3) the arbitrator inappropriately reopened the hearing “for the submission of additional evidence by Denison, but not KGL.” KGL also asserted that the arbitrator demonstrated evident partiality in favor of Denison. After a hearing, the district court confirmed the Final Award. The court concluded that KGL’s objection to the timeli *1172 ness of the Interim Award did not warrant vacatur of the Final Award, that the arbitrator did not exceed his authority or exhibit evident partiality in favor of Denison, and that the arbitrator conducted the arbitration process “fairly and honestly and in a manner that respected and did not prejudice .the substantial rights of either KGL or Denison.” KGL timely appealed.

ISSUES AND STANDARDS OF REVIEW

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shipp v. Peterson
2021 UT App 25 (Court of Appeals of Utah, 2021)
Rogers v. Red Boots Invs.
2020 NMCA 028 (New Mexico Court of Appeals, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
2016 UT App 171, 381 P.3d 1167, 819 Utah Adv. Rep. 7, 2016 Utah App. LEXIS 178, 2016 WL 4255019, Counsel Stack Legal Research, https://law.counselstack.com/opinion/denison-mines-usa-corporation-v-kgl-associates-utahctapp-2016.