Delidakis Construction Co. v. City of New York

9 Misc. 3d 517
CourtNew York Supreme Court
DecidedAugust 1, 2005
StatusPublished
Cited by1 cases

This text of 9 Misc. 3d 517 (Delidakis Construction Co. v. City of New York) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Delidakis Construction Co. v. City of New York, 9 Misc. 3d 517 (N.Y. Super. Ct. 2005).

Opinion

OPINION OF THE COURT

Karia Moskowitz, J.

In this dispute over delays at a municipal construction site, defendant City of New York moves, pursuant to CPLR 3211 (a) (1), (2), (5) and (7), to dismiss the fourth and fifth causes of action of plaintiff contractor’s complaint on the ground that the claims are time-barred. In addition, the City argues that the fourth cause of action is based on the equitable doctrine of quantum meruit and, therefore, requires dismissal, because there exists a valid written contract governing the subject matter of the parties’ dispute.

In February 1994, plaintiff Delidakis Construction Co., Inc. was the winning bidder for a public improvement construction project involving the replacement of the Victory Boulevard Pedestrian Bridge over the Staten Island Rapid Transit Line, Department of Transportation (DOT) contract No. HRBC002. There is no dispute that the project was substantially completed as of May 31, 1999, and plaintiff concedes that its claim accrued on that date. Plaintiff commenced this action on October 21, 2004. The first three causes of action of plaintiffs complaint, not at issue on this motion, seek payment for extra work in the amount of $213,696. The fourth cause of action asserts that plaintiff supplied additional labor, materials, equipment and services under the contract and thus is entitled to an “equitable adjustment” (complaint 1i 19) in the amount of $2,656,674. The City’s failure to compensate plaintiff for this additional work allegedly constitutes a breach of the contract. The fifth cause of action seeks damages in the same amount for delays in the performance of plaintiffs work that the City caused.

The City argues that the fourth and fifth causes of action are barred by a contractual four-month statute of limitations. The City relies on article 53 of a section of the contract called the “Agreement,” that states in pertinent part as follows:

[519]*519“No action shall lie or be maintained, against the City by the Contractor upon any claims based upon this Agreement unless such action be commenced within four (4) months after the date of filing in the office of the Comptroller of the City of the certificate for the final payment hereunder, or within four (4) months of the termination or conclusion of this Agreement, or within four (4) months after the accrual of the Cause of Action, whichever first occurs.” (Frade affirmation, exhibit A-3, at 00250.)

Plaintiff argues that, although the contract provided for a completion time of 456 calendar days, the City failed to design, administer and manage the construction project properlyxThisx resulted in an additional four years to complete the project, subjecting plaintiff to substantial additional costs and expenses. According to the affidavit of plaintiffs president, Bob Delidimitriou, “constant changes and corrections by the City to the design and drawings, unforeseen conditions, the City’s failure to appropriately coordinate work of other contractors and other projects, and inclement weather conditions” caused the delays. (Delidimitriou affirmation 1i 5.) Mr. Delidimitriou further avers that the City acknowledged the delays on several occasions and granted some of plaintiffs requests for time extensions.

Plaintiff contends that the contract consists of various documents, including the proposal for bids, plaintiffs bid, the technical specifications and the agreement. The four-month statute of limitations is contained in article 53 of the agreement and applies to “claims based on this Agreement.” Because plaintiffs claims for delay damages are allegedly based on the contract, not the agreement, plaintiff argues that the four-month statute of limitations does not apply, relying on the holding of the United States Court of Appeals for the Second Circuit when it construed the identical provision of a New York City construction contract in Perini Corp. v City of New York (Pulaski Bridge) (178 F3d 90 [2d Cir 1999]).

Perini involved the reconstruction of the Pulaski Bridge. In that case, the contractor argued that its third and fourth causes of action, seeking compensation from the City for the extensive delays on the project, were based on a federally-mandated “Suspensions Clause” located in an addendum to the construction contract and on violations of fundamental obligations not found in the agreement. The Second Circuit accepted the [520]*520contractor’s argument,1 because article 53 uses the term “Agreement” as opposed to the term “Contract,” and article 1 of the agreement “carefully distinguishes between the ‘Agreement,’ the ‘Contract’ and ‘Addenda.’ ” (178 F3d at 94.) “Given the language expressly denoting the Agreement as ‘part’ of the Contract, we may infer that a contract provision that specifically refers to the Agreement does not encompass the Contract in its entirety.” (Id.) The Second Circuit ruled that, to the extent that the scope of this provision is ambiguous, it must be interpreted against the City (id. at 94-95). At the same time it stated that the “plain language limits its scope to actions ‘based upon this Agreement,’ ” and that it could not ignore this “ ‘unmistakable and decisive’ language.” (Id. at. 95, quoting Sassi v Jersey Trucking Serv., 283 App Div 73, 76 [1st Dept 1953].)

Perini is not binding precedent on this court. While a lower federal court’s interpretation of the Federal Constitution or a federal statute may be considered persuasive or useful authority (People v Kin Kan, 78 NY2d 54, 59-60 [1991]; New York R.T. Corp. v City of New York, 275 NY 258, 265 [1937], affd 303 US 573 [1938]), Perini involves only the interpretation of a municipal construction contract. Nor does the First Department’s decision in Sassi v Jersey Trucking Serv. (supra), that involved the interpretation of the words “happening of the loss” in an insurance policy, compel the result reached in Perini.2

Article 1 of chapter I of the agreement does not carefully distinguish between the contract and the agreement; it merely lists all of the documents comprising the parties’ written contract, including the agreement. This document is a compilation of general, nontechnical and non-project-specific contractual [521]*521provisions that apply to all DOT construction sites involving bridges. For example, the agreement covers such important items as inspections (art 6), protection of the work site (art 7), giving notice of conditions causing delay (art 11), extensions of time for performance (art 13), no damages for delay (art 13 [H]), subcontracts (art 18), insurance (art 22), changes and extra work (arts 25A, 26), resolution of disputes (art 27), and claims and actions against the City (ch XI, art 53). The only interpretation of article 53 that makes sense is that the terms “Agreement” and “Contract” are synonymous. The terms are used interchangeably throughout the entire contract and within the agreement section itself. For example, in articles 59 and 59A of the agreement, the City is given the right to terminate “this agreement,” “this contract” and “this Contract” for various reasons. (Frade affirmation, exhibit A-3, at 00255.) Any other interpretation would lead to the absurd result of permitting termination of the agreement and a continuation of the remainder of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Delidakis Construction Co. v. City of New York
29 A.D.3d 403 (Appellate Division of the Supreme Court of New York, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
9 Misc. 3d 517, Counsel Stack Legal Research, https://law.counselstack.com/opinion/delidakis-construction-co-v-city-of-new-york-nysupct-2005.