Soviero Bros. Contracting Corp. v. City of New York

286 A.D. 435, 142 N.Y.S.2d 508
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJune 28, 1955
StatusPublished
Cited by36 cases

This text of 286 A.D. 435 (Soviero Bros. Contracting Corp. v. City of New York) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Soviero Bros. Contracting Corp. v. City of New York, 286 A.D. 435, 142 N.Y.S.2d 508 (N.Y. Ct. App. 1955).

Opinions

Breitel, J.

Plaintiff is a contractor who undertook in written agreements with the City of New York to construct two sewers at separate locations and to make the necessary excavations. It sues for damages based on misrepresentations in the city’s specifications as to the site of one of the sewer excavations and the physical condition of the subsurface area of the other. The city sets up as an affirmative defense the time limitation contained in the contracts for the bringing of suits. That provision requires that actions be commenced within one year after the filing in the office of the comptroller of the final certificate. Concededly, the one-year period has long expired. It is also conceded that the true physical facts were discovered by the contractor more than a year (indeed, more than three years) prior to the beginning of this action.

The issue is whether the city may interpose and rest upon the time limitation as a defense in an action charging it with 1 ‘ fraudulent ’ ’ misrepresentation as to material facts, in reliance upon which the contractor entered into its engagements, and which engagements the contractor has never elected to rescind.

The question arises on a motion for summary judgment made by the defendant under rule 113 of the Rules of Civil Practice. The City Court Special Term granted the motion, but the order was reversed by a divided court in the Appellate Term.

The complaint is framed in law and demands damages in almost the classical form for actual fraud. The affidavits submitted on the motion, on the other hand, reveal that reliance is not had upon the traditional five elements of fraud. On the contrary, the gravamen is misrepresentation, innocently or recklessly made by the city, with respect to material facts, at a time when, somewhere in the files of the city, there were documents and maps clearly revealing the true facts, which facts were never disclosed in advance to the contractor. Since, however, the action is based on damages at law for fraudulent inducement, it is in affirmance of the contracts. This being so, the city may avail itself of the short period of limitation contained in the written agreements with the contractor. Such a [438]*438contractual period of limitation is not contrary to public policy. Consequently, the order of the Appellate Term should be reversed and the order of Special Term granting judgment in favor of the city should be reinstated.

The complaint contains two causes of action: One is for damages of $3,529.44 based upon the additional expense incurred by the contractor in making one excavation at a site other than the one indicated in the specifications; and the other is for damages in the sum of $1,191.20 for additional expense incurred in removing trolley tracks and railroad ties found at the site of the other excavation, and of which the contractor was not advised at the time of the making of the agreement. The contracts, according to the final certificates, yielded a total payment to the contractor from the city of $29,699, exclusive of these claimed extras.

January 26, 1949, and October 11, 1949, were the dates for the opening of bids on the respective projects. For the first project, a final certificate was filed on November 25, 1949, and payment of the amount certified was made by the city to the contractor on December 28, 1949. On the latter date, the contractor filed a claim with the comptroller for the excess expenses, in the sum of $3,529.44, sustained at the relocated site. Various proceedings were had under this claim, including an examination of the contractor, and, on November 25, 1952, the city rejected the claim. In the second project, similar proceedings in part were had with respect to the contractor’s claim, in the sum of $1,191.20, for additional expenses incurred in removing trolley tracks and railroad ties.

This action was thereafter begun on January 23, 1953, more than three years after the issuance of the final certificate for the first contract and the payment made thereunder.

It is not disputed that the first contract and its specifications called for excavation in an existing dirt area to accommodate a twelve-inch sewer. To make such an excavation it was necessary for the work to extend for a width of fourteen feet. When the contractor was ready to proceed with the work under this contract, the site for the laying of the sewer had to be changed twice because, on each occasion, it was discovered that the proposed excavation would invade the properties of abutting owners. The site finally chosen for the excavation, free from the objections of abutting owners, lay under a concrete walk. This, of course, entailed additional expense for the contractor. At the location specified in the other contract, when the work penetrated to the subsurface, there were discovered abandoned [439]*439trolley tracks and railroad ties, which again increased the expense for the contractor. The contractor protested because of the changed requirements and the additional expense, but proceeded with the work. The additional expenses were the basis for the claims filed with the comptroller in December, 1949 and May, 1950, respectively. At no time, then or since, did the contractor elect, as it might have, to rescind the contracts, nor did it bring an action to recover damages within the time limitation contained in the written agreements.

The provision contained in each agreement which imposes the time limitation reads as follows: “ LIV. No action shall lie or be maintained by the Contractor, or anyone claiming under the Contractor, against The City upon any claim arising out of or based upon this contract or by reason of any act or omission or requirement of The City or its agents, unless such action shall be commenced within one year after date of filing in the office of the Comptroller of the City of New York the final certificate ’ \ It is a standard provision in city contracts, and is evidently designed to discourage stale and fraudulent claims for extras ” against the city.

The contractor knew of the falsity of the representations before the work on one of the excavations was commenced. It had to, because at the beginning it was faced with the change of site and the need to break through concrete. With respect to the trolley tracks and railroad ties at the second excavation, it learned of the failure to warn of that condition during the progress of the work in 1949. The contractor did not rescind, but proceeded with the contracts under protest. That was its right, namely, to proceed with performance of the contracts, in affirmance thereof, and claim later the damages which resulted from the misrepresentations. Even after the work was completed, the contractor might have tried to rescind, although it had fully executed its part. At this time, however, it would be doubtful whether its opportunity to rescind was still available, since the remedy of rescission must be invoked within a reasonable time after discovery of the misrepresentation. (Barnard v. Campbell, 58 N. Y. 73, 75; 5 Williston on Contracts [Rev. ed.], § 1526.)

In any event, the contractor did not attempt to rescind and disaffirm the contracts, but filed its claims for damages with the comptroller. For over two years while these claims were pending, the contractor still made no effort to rescind. Presumably, the contractor wished to retain the profits of these contracts, and to look only to damages for the misrepresentations, rather [440]*440than to rescind, risk his profits, and he limited to damages measured by benefits conferred.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Delidakis Construction Co. v. City of New York
9 Misc. 3d 517 (New York Supreme Court, 2005)
Morrissey v. General Motors Corp.
21 F. App'x 70 (Second Circuit, 2001)
TBG, INC. v. Bendis
845 F. Supp. 1459 (D. Kansas, 1994)
Diana Jewelers of Liverpool, Inc. v. A.D.T. Co.
167 A.D.2d 965 (Appellate Division of the Supreme Court of New York, 1990)
Goldstein v. City of New York
159 A.D.2d 313 (Appellate Division of the Supreme Court of New York, 1990)
Clark-Fitzpatrick, Inc. v. Long Island Rail Road
516 N.E.2d 190 (New York Court of Appeals, 1987)
Kardios Systems Corp. v. Perkin-Elmer Corp.
645 F. Supp. 506 (D. Maryland, 1986)
A.J. Tenwood Associates v. Orange Senior Citizens Housing Co.
491 A.2d 1280 (New Jersey Superior Court App Division, 1985)
Bernstein v. Cooke
103 A.D.2d 725 (Appellate Division of the Supreme Court of New York, 1984)
Novak & Co. v. New York City Housing Authority
125 Misc. 2d 647 (New York Supreme Court, 1984)
Beutel v. Beutel
434 N.E.2d 249 (New York Court of Appeals, 1982)
Brink's, Inc. v. City of New York
528 F. Supp. 1084 (S.D. New York, 1981)
Quick Erectors, Inc. v. Seattle Bronze Corp.
524 F. Supp. 351 (E.D. Missouri, 1981)
Raymond International, Inc. v. City of New York
511 F. Supp. 773 (S.D. New York, 1981)
John J. Kassner & Co. v. City of New York
389 N.E.2d 99 (New York Court of Appeals, 1979)
Hurlbut v. Christiano
63 A.D.2d 1116 (Appellate Division of the Supreme Court of New York, 1978)
Gannett Co., Inc. v. Register Pub. Co.
428 F. Supp. 818 (D. Connecticut, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
286 A.D. 435, 142 N.Y.S.2d 508, Counsel Stack Legal Research, https://law.counselstack.com/opinion/soviero-bros-contracting-corp-v-city-of-new-york-nyappdiv-1955.