Perini Corporation v. The City of New York (Pulaski Bridge)

178 F.3d 90, 1999 U.S. App. LEXIS 9207, 1999 WL 304376
CourtCourt of Appeals for the Second Circuit
DecidedMay 14, 1999
DocketDocket 98-7946
StatusPublished
Cited by4 cases

This text of 178 F.3d 90 (Perini Corporation v. The City of New York (Pulaski Bridge)) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Perini Corporation v. The City of New York (Pulaski Bridge), 178 F.3d 90, 1999 U.S. App. LEXIS 9207, 1999 WL 304376 (2d Cir. 1999).

Opinion

OAKES, Senior Circuit Judge:

I. INTRODUCTION

The City of New York (City) contracted with the Perini Corporation (Perini) to reconstruct the Pulaski Bridge. Soon after Perini commenced work in September 1991, the City ordered Perini to stop work because the necessary engineering and construction support services were not yet in place. Perini was directed to resume work in February 1992. In August 1995, Perini sued the City for delay damages caused by the City’s suspension of the work. The United States District Court for the Southern District of New York, Judge Louis L. Stanton, dismissed Perini’s claims as barred by the contractual period of limitations. We hold that summary judgment was improperly granted because Perini’s claim for delay damages was not subject to the contractual period of limitations. We therefore vacate the grant of summary judgment and remand for further proceedings.

II. BACKGROUND

This action arises out of the reconstruction of the Pulaski Bridge, a 3,800-foot drawbridge over the Newtown Creek, connecting Brooklyn with Queens. In June 1991, the City, acting through its Department of Transportation (DOT), contracted with Perini to perform the reconstruction and related incidental work on the bridge. The work was to be completed in 1,246 consecutive calendar days (three years and five months). The City ordered Perini to commence work on September 23, 1991.

As ordered, Perini began work on or about September 23, 1991. But on October 8,1991, the City ordered Perini to stop work because the necessary resident engineering and construction support services were not yet in place. Perini removed its workers, equipment and materials from the site. Perini was directed to resume work in February 1992.

While it is uncontroverted that Perini worked on the project for several years, the parties vigorously dispute the date the project was “substantially completed.” Article 43 of the contract essentially identifies the date of substantial completion by providing that “[w]hen the work, in the opinion of the Commissioner, has been substantially but not entirely completed, he shall issue a certificate of substantial completion and a voucher calling for payment of any part or all of the balance due under the contract....” Unfortunately, one element of this event — which would have unequivocally indicated when the project was substantially completed — never occurred; that is, no such certificate was issued.

On December 14,1994, the City conducted what was intended to be a “final inspection” of the project. The record contains conflicting representations as to what happened on that date. According to Perini, the City’s mechanical inspectors walked out of the inspection and refused to accept Perini’s work as complete. But Perini itself stated in a letter that a final inspection had been performed on December 14, 1994, and that Perini had been “advised” that a substantial completion payment would be prepared and submitted by December 31, 1994. The City did prepare a punch list — a list of tasks that Perini still had to complete — on December 14, 1994. A final inspection of the mechanical components of the job took place on February 2, 1995. On or about February 8, 1995, a final punch list was furnished to Perini.

On March 30,1995, the City prepared an internal voucher authorizing the Comptroller to prepare a check for payment to Perini for its “substantial completion” moneys. This voucher, which Perini did not see, authorized a reduction of retain- *92 age from five percent to one percent and approved the release of the substantial completion payment to Perini. As Perini points out, this event is also relevant to the determination of the substantial completion date, because the contract provides that “[r]etainage will be reduced from 5% ... at the point of substantial completion.” Perini received the City’s substantial completion payment, dated April 20, 1995, on April 27, 1995. Perini contends that it had no notice that the City deemed Perini’s contract work to be substantially complete until it received this check.

Perini filed a notice of claim with the Comptroller of the City of New York in February 1995 1 and filed the complaint in this action on August 22, 1995. Perini sued to recover, among other things, damages sustained by reason of the suspension of work. 2 Perini’s third cause of action sought an equitable adjustment under the specific “suspension of work” clause (“Suspensions Clause”) contained in an addendum to the contract as required by federal regulations. The fourth cause of action sought damages based on the City’s failure to provide the resident engineering and construction support services which “was not contemplated by the plaintiff and/or [was] caused by the defendant’s bad faith, fraud, misrepresentations of material fact and its willful, malicious, recklessly indifferent or grossly negligent conduct and/or resulted from the defendant’s breach of its fundamental obligations under the Contract. ...”

' The City sought summary judgment on Perini’s third and fourth causes of action, arguing that the claims were time-barred under the period of limitations contained in Article 53 of the Agreement between the parties. Article 53 provided that,

No action shall lie or be maintained against the City by the Contractor upon any claims based upon this Agreement unless such action be commenced within four (4) months after the date of filing in the Office of the Comptroller of the City of the certificate for the final payment hereunder, or within four (4) months of the termination or conclusion of this Agreement, or within four (4) months after the accrual of the Cause of Action, whichever first occurs.

The City argued that Perini’s cause of action seeking delay damages accrued in October 1991, when the City issued the stop work order, and that Perini had to sue within four months of the stop work order. The United States District Court for the Southern District of New York, Judge Louis L. Stanton, agreed and granted summary judgment for the City on Perini’s third and fourth causes of action.

Perini appeals.

III. DISCUSSION

Perini argues that the district court erred by granting summary judgment based on the contractual period of limitations contained in Article 53. It first contends that Article 53 applies only to claims brought under the “Agreement” and therefore did not apply to Perini’s third and fourth causes of action, which sought damages for the delay under the Suspensions Clause and for the City’s breach of its fundamental contract obligations. In the *93 alternative, Perini asserts that even if Article 53 did apply to its claims for delay damages, that provision did not require Perini to sue the City within four months after the City issued the stop work order in October 1991. Rather, Perini argues, the contract was indivisible and all possible claims accrued only upon “substantial completion” of the construction project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Delidakis Construction Co. v. City of New York
29 A.D.3d 403 (Appellate Division of the Supreme Court of New York, 2006)
Delidakis Construction Co. v. City of New York
9 Misc. 3d 517 (New York Supreme Court, 2005)
Herring v. Teradyne, Inc.
256 F. Supp. 2d 1118 (S.D. California, 2002)
McKinley Associates, LLC v. McKesson HBOC, Inc.
110 F. Supp. 2d 169 (W.D. New York, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
178 F.3d 90, 1999 U.S. App. LEXIS 9207, 1999 WL 304376, Counsel Stack Legal Research, https://law.counselstack.com/opinion/perini-corporation-v-the-city-of-new-york-pulaski-bridge-ca2-1999.