Delaware Riverkeeper Network v. Sec Pa Dept Environmental Prot

CourtCourt of Appeals for the Third Circuit
DecidedAugust 30, 2017
Docket17-1533
StatusPublished

This text of Delaware Riverkeeper Network v. Sec Pa Dept Environmental Prot (Delaware Riverkeeper Network v. Sec Pa Dept Environmental Prot) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Delaware Riverkeeper Network v. Sec Pa Dept Environmental Prot, (3d Cir. 2017).

Opinion

PRECEDENTIAL UNITED STATES COURT OF APPEALS FOR THE THIRD CIRCUIT _____________

No. 17-1533 _____________

DELAWARE RIVERKEEPER NETWORK; MAYA VAN ROSSUM, the Delaware Riverkeeper, Petitioners

v.

SECRETARY OF THE PENNSYLVANIA DEPARTMENT OF ENVIRONMENTAL PROTECTION; PENNSYLVANIA DEPARTMENT OF ENVIRONMENTAL PROTECTION, Respondents

Tennessee Gas Pipeline Co., Intervenor

On Petition for Review from the Pennsylvania Department of Environmental Protection WQ02-002 E52-253 E63-305 FERC-1 : FERC CP16-4

Argued July 13, 2017 Before: SMITH, Chief Judge, NYGAARD, and FUENTES, Circuit Judges

(Filed: August 30, 2017)

Aaron J. Stemplewicz [ARGUED] Delaware Riverkeeper Network 925 Canal Street, Suite 3701 Bristol, PA 19007 Counsel for Petitioners

Alexandra C. Chiaruttini Joseph S. Cigan III [ARGUED] Commonwealth of Pennsylvania Department of Environmental Protection 2 Public Square Wilkes-Barre, PA 18701

Kimberly Hummel Childe Office of Attorney General of Pennsylvania Department of Environmental Resources 9th Floor P.O. Box 8464 Harrisburg, PA 17105 Counsel for Respondents

Pamela S. Goodwin Saul Ewing 650 College Road East, Suite 4000 Princeton, NJ 08540 2 Patrick F. Nugent John F. Stoviak [ARGUED] Saul Ewing 1500 Market Street Centre Square West, 38th Floor Philadelphia, PA 19102

Elizabeth U. Witmer Saul Ewing 1200 Liberty Ridge Drive, Suite 200 Wayne, PA 19087 Counsel for Intervenor Respondent

________________

OPINION OF THE COURT ________________

SMITH, Chief Judge.

Tennessee Gas Pipeline Co. (“Tennessee Gas”) submitted applications to several federal and state agencies seeking approval to build an interstate pipeline project. One such agency is the Pennsylvania Department of Environmental Protection (“PADEP”),1 which issued a permit approving the

1 A companion case, also before this panel, raises challenges to the United States Army Corps of Engineers. See Del. Riverkeeper Network v. U.S. Army Corps of Eng’rs, No. 17-1506 (3d Cir. 2017). 3 project. The petitioners, Maya van Rossum and Delaware Riverkeeper Network (collectively, “Riverkeeper”), argue that we lack jurisdiction to rule on its petition because PADEP’s order was not final. As to the merits, Riverkeeper challenges PADEP’s decision on the grounds that the agency made an erroneous “water dependency” finding and improperly rejected a “compression” alternative to the pipeline project.

We will exercise jurisdiction because PADEP’s decision was final. We will also uphold PADEP’s decision on the merits because the agency’s unique interpretation of water dependency is reasonable and worthy of deference. Furthermore, the agency considered and rejected the compression alternative for reasons that are supported by the record. We will therefore deny the petition for review.

I

At issue is the so-called Orion Project—12.9 miles of pipeline looping that would transport 135,000 dekatherms of natural gas per day via Pennsylvania. Approximately 99.5% of the new pipeline would run alongside existing pipelines.

Full background information on the Orion Project is provided in a companion case, Delaware Riverkeeper Network v. U.S. Army Corps of Engineers, No. 17-1506 (3d Cir. 2017). For purposes of this opinion, we will focus on the aspects of the state administrative procedures at issue here.

Under the Natural Gas Act of 1938, the Federal Energy Regulatory Commission (“FERC”) is the “lead agency” for evaluating interstate pipeline projects. 15 U.S.C. § 717n(b). As

4 a condition of FERC approval, the applicant is required to obtain any other state or federal licenses required by law. One such license is called a Water Quality Certification governed by Section 401 of the Clean Water Act. 33 U.S.C. § 1341. “A Water Quality Certification confirms that a given facility will comply with federal discharge limitations and state water quality standards.” Del. Riverkeeper Network v. Sec'y Pa. Dep’t of Envtl. Prot., 833 F.3d 360, 368 (3d Cir. 2016), as amended (March 24, 2017). “For activities affecting Pennsylvania waters, . . . Water Quality Certifications are issued by PADEP.” Id. at 369.

As a condition of obtaining a Water Quality Certification, PADEP requires applicants to obtain other state permits, including a Water Obstruction and Encroachment Permit issued under Pennsylvania’s Dam Safety and Encroachment Act and its implementing regulations, 25 Pa. Code Ch. 105. Those permits are commonly referred to as “Chapter 105 permits.”

Chapter 105 gives special protection to “exceptional value” wetlands. Wetlands are considered to have exceptional value if, inter alia, they are located along a drinking water supply or serve as habitat for endangered species. See 25 Pa. Code § 105.17(1). It is undisputed that the Orion Project would affect ten exceptional-value wetlands in Pike County and three in Wayne County.

PADEP cannot issue a Chapter 105 permit for a project affecting exceptional-value wetlands unless it certifies in writing that seven requirements are met. 25 Pa. Code § 105.18a. Two are relevant here: 5 (2) The project is water-dependent. A project is water-dependent when the project requires access or proximity to or siting within the wetland to fulfill the basic purposes of the project.

(3) There is no practicable alternative to the proposed project that would not involve a wetland or that would have less effect on the wetland, and not have other significant adverse effects on the environment.

Id. § 105.18a(a)(2)–(3).

On September 20, 2016, PADEP issued a conditional Water Quality Certification for the Orion Project. Then, on February 23, 2017, PADEP issued two Chapter 105 permits approving the Orion Project’s stream and wetland crossings—Permit Nos. E52-253 (Pike County) and E64-305 (Wayne County). In doing so, PADEP certified that the Orion Project “[i]s water dependent” and would be “the least environmentally damaging alternative.” JA 49, 180.

On March 10, 2017, Riverkeeper filed this petition for review. We granted Tennessee Gas’s motion to intervene on March 17, 2017. Riverkeeper filed a motion for an emergency stay, which this Court denied on April 7, 2017. Riverkeeper then filed a motion to expedite the case. We granted that motion on May 8, 2017.

6 II

The parties ask us to resolve two jurisdictional issues: (1) whether we may review nonfinal administrative orders under the Natural Gas Act; and (2) whether the petition was timely filed. We need not reach the first question. The agency decision at issue is final, and therefore jurisdiction would be proper under either interpretation of the Natural Gas Act. As for the second question, we conclude that the petition was timely filed.

A

First, Riverkeeper argues that we lack jurisdiction because we may only review final orders, and PADEP’s order is not final until it has been reviewed by a separate administrative entity, Pennsylvania’s Environmental Hearing Board. Riverkeeper asks us to transfer the case to the Board.2 We conclude that jurisdiction is proper because PADEP’s order is final.

Our jurisdiction is controlled by Section 19(d) of the Natural Gas Act, as amended in 2005. Where an interstate pipeline project is proposed to be constructed, see 15 U.S.C.

2 Because we conclude that jurisdiction is proper, we need not address Riverkeeper’s request for a transfer. See McLaughlin v. Arco Polymers, Inc., 721 F.2d 426, 430 (3d Cir. 1983); see also Moravian Sch. Advisory Bd. of St. Thomas, V.I. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sierra Club v. Robert B. Flowers
362 F. App'x 100 (Eleventh Circuit, 2010)
North Haven Board of Education v. Bell
456 U.S. 512 (Supreme Court, 1982)
Bell v. New Jersey
461 U.S. 773 (Supreme Court, 1983)
North Star Steel Co. v. Thomas
515 U.S. 29 (Supreme Court, 1995)
Auer v. Robbins
519 U.S. 452 (Supreme Court, 1997)
Bennett v. Spear
520 U.S. 154 (Supreme Court, 1997)
Barnhart v. Walton
535 U.S. 212 (Supreme Court, 2002)
Jones v. R. R. Donnelley & Sons Co.
541 U.S. 369 (Supreme Court, 2004)
City of Bangor v. Citizens Communications Co.
532 F.3d 70 (First Circuit, 2008)
Atlantic Seaboard Corp. v. Federal Power Commission
201 F.2d 568 (Fourth Circuit, 1953)

Cite This Page — Counsel Stack

Bluebook (online)
Delaware Riverkeeper Network v. Sec Pa Dept Environmental Prot, Counsel Stack Legal Research, https://law.counselstack.com/opinion/delaware-riverkeeper-network-v-sec-pa-dept-environmental-prot-ca3-2017.