DELAWARE RIVER PARTNERS, LLC v. RAILROAD CONSTRUCTION COMPANY, INC. (L-0026-21, GLOUCESTER COUNTY AND STATEWIDE)

CourtNew Jersey Superior Court Appellate Division
DecidedJune 24, 2022
DocketA-2613-20
StatusUnpublished

This text of DELAWARE RIVER PARTNERS, LLC v. RAILROAD CONSTRUCTION COMPANY, INC. (L-0026-21, GLOUCESTER COUNTY AND STATEWIDE) (DELAWARE RIVER PARTNERS, LLC v. RAILROAD CONSTRUCTION COMPANY, INC. (L-0026-21, GLOUCESTER COUNTY AND STATEWIDE)) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
DELAWARE RIVER PARTNERS, LLC v. RAILROAD CONSTRUCTION COMPANY, INC. (L-0026-21, GLOUCESTER COUNTY AND STATEWIDE), (N.J. Ct. App. 2022).

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court ." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION DOCKET NO. A-2613-20

DELAWARE RIVER PARTNERS, LLC,

Plaintiff-Respondent,

v.

RAILROAD CONSTRUCTION COMPANY, INC.,

Defendant-Appellant,

and

RIGGS DISTLER AND COMPANY, INC. and HUNTER SITE SERVICES, LLC,

Defendants-Respondents. _____________________________

Argued May 2, 2022 – Decided June 24, 2022

Before Judges Messano, Enright and Marczyk.

On appeal from the Superior Court of New Jersey, Law Division, Gloucester County, Docket No. L-0026-21.

Michael F. McKenna argued the cause for appellant Railroad Construction Company, Inc. (Cohen Seglias Pallas Greenhall & Furman, PC, attorneys; Michael F. McKenna and Timothy Ryan, on the briefs).

James H. Landgraf argued the cause for respondent Railroad Construction Company, Inc. (Dilworth Paxson, LLP, attorneys; James H. Landgraf and Benjamin W. Spang, on the brief).

PER CURIAM

In 2019, plaintiff Delaware River Partners, LLC, accepted a proposal from

defendant Railroad Construction Company, Inc., to design, procure and

construct a liquified petroleum gas unloading and loading facility in Gibbstown

known as the Repauno Port & Rail Terminal Project (the Project). Plaintiff and

defendant entered into a $75 million contract (the Contract).

Disputes arose over defendant's timely performance, and informal dispute

resolution procedures outlined in the Contract failed to resolve the issues. In

January 2021, plaintiff filed a complaint against defendant in the Law Division;

plaintiff also named Riggs Distler and Company, Inc. (Riggs), a subcontractor

defendant hired to work on the Project, as a defendant. Riggs had filed a

construction lien claim against the property as the result of a dispute with

defendant over payment. Plaintiff's complaint alleged defendant breached the

Contract, and it also sought to discharge Riggs' construction lien.

A-2613-20 2 On February 19, 2021, defendant sent formal written notice to plaintiff

invoking Section 12.1.3 of the Contract and demanding the complaint be

dismissed and the dispute submitted to binding arbitration. Later that same day,

defendant filed a formal motion to dismiss the complaint in the Law Division

"pursuant to the arbitration clause within" the Contract.

Plaintiff opposed the motion and cross-moved to amend its complaint to

add Hunter Site Services, LLC (Hunter), another subcontractor of defendant that

also filed a construction lien claim, as a defendant. Riggs joined in defendant's

motion arguing the arbitration provision applied to plaintiff's claim against

Riggs; alternatively, Riggs asserted that plaintiff's claim seeking to discharge

Riggs' construction lien should be stayed pending arbitration between plaintiff

and defendant.

After considering oral argument, the judge denied defendant's motion to

dismiss and granted plaintiff's motion to amend the complaint. The judge

reasoned Section 12.1.3's language was ambiguous, was permissive regarding

arbitration and did not compel plaintiff to arbitrate its claims against defendant.

He entered an order on March 22, 2021, denying the motion to dismiss.

Plaintiff soon filed its amended complaint, and defendant moved for

reconsideration, with Riggs joining. Plaintiff filed opposition, and, in his oral

A-2613-20 3 opinion of April 30, 2021, the judge denied the motion. He entered a conforming

order, and this appeal followed.

Before us, defendant reprises the essential argument it made in the Law

Division. It contends the only reasonable construction of the Contract's

unambiguous dispute resolution provisions allowed either party to submit

disputes to binding arbitration and compel the other party's participation.

Plaintiff reiterates its argument that Section 12.1.3 is permissive, and neither

party can compel arbitration without the other's consent. Riggs has not

participated in the appeal.

We agree with defendant. When viewed in their entirety, the only

reasonable interpretation of the Contract's dispute resolution provisions

permitted either party to compel arbitration of disputes that arose under the

Contract. We reverse and remand the matter to the Law Division for entry of an

appropriate order consistent with this opinion.

I.

Because we construe "arbitration agreements under general contract

principles," Martindale v. Sandvik, Inc., 173 N.J. 76, 85 (2002), we start with

the language of the Contract in this case. Article 12, entitled "Dispute

Resolution," provides the following:

A-2613-20 4 12.1 In General. The [p]arties shall attempt to settle every dispute arising out of or in connection with this [a]greement ("Dispute"), by following the dispute resolution process set forth below in this Article 12, to the extent permitted by [l]aw.

12.1.1 Mutual Discussions. If any dispute or difference of any kind whatsoever (a "Dispute") arises between the [p]arties in connection with, or arising out of, this [a]greement, the [p]arties within ten (10) days shall attempt to settle such Dispute in the first instance by mutual discussions between [o]wner and [c]ontractor.

12.1.2 Further Procedures. If the Dispute cannot be settled within ten (10) days by mutual discussions, then the Dispute shall be finally settled under the provisions of this Section 12.1.2 or Section 12.1.3. If the [p]arties fail to resolve any dispute through discussions pursuant to Section 12.1.1, either [p]arty shall have the right to provide written notice of the Dispute to the president or chief executive officer ("Senior Management") of the other [p]arty. Upon a timely referral, the Senior Management of the [p]arties shall consider the Dispute, review such relevant information as they may determine and issue their decision (which decision shall be confirmed in writing) within five (5) [b]usiness [d]ays after receiving the referral. If the Senior Management of the [p]arties cannot resolve the issue within the [five b]usiness[-d]ay period, then the [p]arties shall have the rights set forth below in Section 12.1.3.

12.1.3 Arbitration. Subject as hereinafter provided, any Dispute arising out of[,] or in connection with, this [a]greement and not settled by Section 12.1.1 or Section 12.1.2 of this [a]greement may (regardless of the nature of the Dispute) be submitted by either

A-2613-20 5 [p]arty to arbitration and finally settled in accordance with Commercial Arbitration Rules of the American Arbitration Association. The arbitration will be held in Gloucester County, New Jersey. There shall be a single arbitrator experienced in construction law. The arbitrator shall apply New Jersey law to resolve legal matters in dispute. The decision of the arbitrator shall be final and conclusive upon the parties hereto and shall be enforceable in a court of competent jurisdiction. Each party to the arbitration shall pay the compensation, costs, fees and expenses of its own witnesses, exhibits and counsel. The compensation, costs and expenses of the arbitrator, if any, shall be borne equally by the parties hereto. . . .

12.2 Continued Performance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Crawford v. West Jersey Health Systems
847 F. Supp. 1232 (D. New Jersey, 1994)
Martindale v. Sandvik, Inc.
800 A.2d 872 (Supreme Court of New Jersey, 2002)
Riverside Chiropractic Group v. Mercury Ins. Co.
961 A.2d 21 (New Jersey Superior Court App Division, 2008)
Schenck v. HJI ASSOCIATES
685 A.2d 481 (New Jersey Superior Court App Division, 1996)
Hardy Ex Rel. Dowdell v. Abdul-Matin
965 A.2d 1165 (Supreme Court of New Jersey, 2009)
Kieffer v. Best Buy
14 A.3d 737 (Supreme Court of New Jersey, 2011)
Manahawkin Convalescent v. Frances O'neill (071033)
85 A.3d 947 (Supreme Court of New Jersey, 2014)
Annemarie Morgan v. Sanford Brown Institute(075074)
137 A.3d 1168 (Supreme Court of New Jersey, 2016)
Tahisha Roach v. Bm Motoring, Llc(077125)
155 A.3d 985 (Supreme Court of New Jersey, 2017)
Borough of Princeton v. Board of Chosen Freeholders
755 A.2d 637 (New Jersey Superior Court App Division, 2000)
Elizabethtown Water Co. v. Watchung Square Associates, LLC
871 A.2d 140 (New Jersey Superior Court App Division, 2005)
Angrisani v. Financial Technology Ventures
952 A.2d 1140 (New Jersey Superior Court App Division, 2008)
Kernahan v. Home Warranty Adm'r of Fla., Inc.
199 A.3d 766 (Supreme Court of New Jersey, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
DELAWARE RIVER PARTNERS, LLC v. RAILROAD CONSTRUCTION COMPANY, INC. (L-0026-21, GLOUCESTER COUNTY AND STATEWIDE), Counsel Stack Legal Research, https://law.counselstack.com/opinion/delaware-river-partners-llc-v-railroad-construction-company-inc-njsuperctappdiv-2022.