Elizabethtown Water Co. v. Watchung Square Associates, LLC

871 A.2d 140, 376 N.J. Super. 571, 2005 N.J. Super. LEXIS 125
CourtNew Jersey Superior Court Appellate Division
DecidedApril 20, 2005
StatusPublished
Cited by4 cases

This text of 871 A.2d 140 (Elizabethtown Water Co. v. Watchung Square Associates, LLC) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Elizabethtown Water Co. v. Watchung Square Associates, LLC, 871 A.2d 140, 376 N.J. Super. 571, 2005 N.J. Super. LEXIS 125 (N.J. Ct. App. 2005).

Opinion

The opinion of the court was delivered by

COBURN, J.A.D.

In these back-to-back, interlocutory appeals, which we have consolidated for purposes of this opinion, we agreed to address three procedural questions for parties involved in related litigation pending concurrently and as a matter of right in arbitration and in court. The questions arose because the factual and legal issues in both tribunals concern performance of contracts for a large construction project for which some of the contracts require arbitration, while others do not. The questions are: whether the lawsuit should have been stayed pending the arbitration; whether a defendant in the lawsuit was obliged to litigate its third-party lawsuit claim in the pending arbitration, which involved, among others, the third-party lawsuit defendant; and whether discovery in the lawsuit of a partial settlement agreement between two of the arbitrating parties, only one of which was involved in the lawsuit, was appropriate.

[574]*574The principal parties in this complex, multi-party, multi-issue, multi-forum litigation are: the property owner, Watchung Square Associates, LLC, and its management company, Fidelity Land Development Corporation (“WSA”); the general contractor, Joseph A. Natoli Construction Corporation (“Natoli”); the excavator, Vollers Excavating and Construction, Inc. (“Vollers”); and the water supply company, Elizabethtown Water Company (“Elizabethtown”).

In early August 1999, Natoli agreed to construct a large shopping center for WSA on its Watchung property. In late November 1999, Natoli subcontracted with Vollers for excavation and site work. Both contracts required that all disputes were to be resolved by arbitration.

On August 21, 1999, Elizabethtown became involved in this project. It agreed with WSA to reroute about 1000 feet of water main through the construction site, and it hired Vollers to perform the excavation and other work required to accomplish the relocation. Neither of those contracts required arbitration.

In mid-February 2000, the slope Vollers was cutting failed in or near the area where the relocated water main was to be run up the mountain slope to connect with an existing Elizabethtown water main. This required a further relocation of the water main at additional expense. Subsequent slope failures occurred along the length of the mountain.

WSA’s largest claims were based on the problems it experienced as a result of the slope failures. The critical issue is whether Vollers or WSA was responsible. If Vollers was responsible, the remaining issue is: whether it caused the initial failure while working on the slope as a subcontractor for Natoli, with which it had an arbitration agreement; while working on the slope for Elizabethtown under the water main relocation contracts between WSA and Elizabethtown and between Elizabethtown and Vollers, which did not provide for arbitration; or whether it caused multiple slope failures while working on both projects. [575]*575Numerous disputes arose between WSA and Natoli, and in January 2002, WSA terminated their contract.

The procedural maneuvering has been extremely complex. For clarity, we omit reference to filings that appear to be peripheral to the issues at hand. Elizabethtown acted first by filing the captioned Law Division action against WSA for approximately $130,000 in unpaid invoices it claimed were due under the relocation contract. WSA counterclaimed, alleging that the work done for Elizabethtown by Vollers had caused the initial slope failure, resulting in over $11 million in damages. Elizabethtown filed an amended complaint, increasing its demand, and both Elizabeth-town and WSA impleaded Vollers as the party responsible for the slope failure. The fourth-party defendants were added later based, in part, on allegations that they were responsible for the slope failures.

In the meantime, WSA filed a demand for arbitration against Natoli, Vollers, and another company. The damages sought included the over $11 million claimed in the lawsuit. Shortly thereafter, Vollers filed a lien foreclosure action in Somerset County against WSA, Natoli, and others. That case was resolved by an order staying the claims of parties not subject to arbitration and directing WSA, Natoli, Vollers and others to resolve their disputes in the arbitration.

During the arbitration, Natoli and Vollers entered into a written contract, which the parties have called the “Liquidating Agreement.” WSA asserts that it “is apparently a document ... [which] may contain admissions by either party relevant to their acts or omissions____” Vollers describes it as a “joint defense agreement.” The arbitrators denied WSA’s demand for discovery of that agreement.

When we granted leave to appeal, the arbitrators had already conducted over 40 hearings.

The following events in the Morris County Law Division led to this appeal. Elizabethtown asked for a stay of the lawsuit it had [576]*576instituted pending the outcome of the arbitration among the other primary parties. But, to be clear, we note that what Elizabeth-town wanted to achieve was not a delay of its collection action. Rather, it was willing to have that matter delayed because it wanted to put off defending against WSA’s $11 million counterclaim, which asserted that Vollers, acting on Elizabethtown’s behalf pursuant to the contract between it and WSA, had caused the initial slope failure. The motion was denied, and we granted leave to appeal. We reverse that order in the interests of judicial economy and to avoid the confusion and possibly inconsistent results that could result from concurrent litigation before both tribunals.

Vollers asked for an order requiring WSA to bring the third-party claim it had asserted in the Law Division against Vollers in the pending arbitration. The motion was denied, and we granted leave to appeal. We affirm because that claim arises under contracts that do not require arbitration. In other words, Elizabethtown cannot be compelled to arbitrate the counterclaim by WSA or its third-party claim for indemnification against Vollers, both arising out of the initial slope failure, and therefore, WSA must pursue its counterclaim against Elizabethtown and its third-party complaint against Vollers, which arises out of that action, in the Law Division.

We also granted Vollers leave to appeal from an order requiring it to give WSA a copy of the Liquidating Agreement. We reverse because the order contradicts the arbitrators’ ruling and because it is premature in light of our decision staying the lawsuit.

“A trial court’s interpretation of the law and the legal consequences that flow from established facts are not entitled to any special deference.” Manalapan Realty, L.P. v. Tp. Comm, of Manalapan, 140 N.J. 366, 378, 658 A.2d 1230 (1995) (citations omitted). Our review of such decisions is plenary. Del Piano v. Merrill Lynch, 372 N.J.Super. 503, 507, 859 A.2d 742 (App.Div. 2004) (citations omitted).

[577]*577The purpose of Elizabethtown’s request for a stay, as we have noted, was to put off litigation of WSA’s counterclaim in the Law Division pending the outcome of the arbitration.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tiger Revitalization Fund, LLC v. 309 Pine Plaza, LLC
New Jersey Superior Court App Division, 2025
Valley National Bank v. Encore Led Lighting, LLC
New Jersey Superior Court App Division, 2024
Bruno v. Mark MaGrann Associates, Inc.
909 A.2d 768 (New Jersey Superior Court App Division, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
871 A.2d 140, 376 N.J. Super. 571, 2005 N.J. Super. LEXIS 125, Counsel Stack Legal Research, https://law.counselstack.com/opinion/elizabethtown-water-co-v-watchung-square-associates-llc-njsuperctappdiv-2005.