MEDFORD TOWNSHIP SCHOOL DISTRICT VS. SCHNEIDER ELECTRIC BUILDINGS AMERICAS, INC. (L-0787-18, BURLINGTON COUNTY AND STATEWIDE)

207 A.3d 265, 459 N.J. Super. 1
New Jersey Superior Court Appellate Division·Decided April 26, 2019·No. A-5798-17T4·Published·Cited by 8 cases

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION

DOCKET NO. A-5798-17T4

MEDFORD TOWNSHIP SCHOOL DISTRICT, APPROVED FOR PUBLICATION

Plaintiff-Respondent, April 26, 2019

APPELLATE DIVISION

v.

SCHNEIDER ELECTRIC BUILDINGS AMERICAS, INC.,

Defendant-Appellant.

Argued April 1, 2019 – Decided April 26, 2019 Before Judges Messano, Fasciale and Rose.

On appeal from Superior Court of New Jersey, Law Division, Burlington County, Docket No. L-0787-18.

Mark A. Rosen argued the cause for appellant (McElroy, Deutsch, Mulvaney & Carpenter, LLP, attorneys; Mark A. Rosen, of counsel and on the briefs).

Richard W. Hunt argued the cause for respondent (Parker McCay PA, attorneys; Richard W. Hunt and John Neckonchuk, on the brief).

The opinion of the court was delivered by ROSE, J.A.D.

Defendant Schneider Electric Buildings Americas, Inc. (Schneider)

appeals from a July 3, 2018 Law Division order enjoining and dismissing arbitration proceedings filed against plaintiff Medford Township School District (District). 1 We affirm.

I.

The dispute arises from the implementation of an energy savings improvement program (ESIP), N.J.S.A. 18A:18A-4.6, under which the District contracted with Schneider to design and implement upgrades to several of the District's schools and its transportation and operations center. Initially, the parties executed the Performance Assurance Support Services Agreement (PASS Agreement), requiring the District to monitor the ESIP's actual energy savings and guaranteeing the District a certain level of monetary savings. The PASS Agreement did not contain an arbitration provision. Instead, its governing law clause provided, in pertinent part (emphasis added):

This PASS Agreement will be governed, interpreted and construed by, under and in accordance with the laws, statutes and decisions of the state in which the [s]ervices are to be performed, without regard to its choice of law provisions. Venue shall be in the federal, state or municipal courts serving the county in which the [s]ervices are performed.

1 See R. 2:2-3(a)(3) (deeming an order compelling or denying arbitration "a final judgment of the court for appeal purposes").

A-5798-17T4

Thereafter, the District issued a request for proposals (RFP), seeking a qualified energy services company (ESC) to perform the services of a general contractor for its ESIP. Among other things, the RFP outlined the terms of the ESIP Agreement, including development and implementation of an energy savings plan. Paragraph 30 of the RFP contained a governing law clause, which stated verbatim (emphasis added):

The ESIP Agreement shall be governed by the laws of the State of New Jersey. The successful [ESC] shall agree that any action or proceeding that arises in any manner out of performance of the RFP or ESIP Agreement, shall be litigated in the Superior Court of New Jersey, Burlington County, State of New Jersey, and the [ESC] shall consent and submit to the jurisdiction of the Superior Court.

After Schneider was awarded the project, the parties executed the Energy Services Construction Contract (ESCC). 2 Under the terms of the ESCC, the parties agreed that Schneider would be paid $2,494,575 for performing energy conservation measures, including lighting upgrades and building automation systems throughout the District.

Article 5 of the ESCC contained a dispute resolution provision, which

2 The parties do not dispute that although the PASS Agreement predated the ESCC, which was executed in June 2015, and the RFP, which was issued in June 2014, the PASS Agreement applied to the project and Schneider's obligations. Inexplicably, however, the PASS Agreement was signed by the District's business administrator in January 2010 and Schneider's regional director in February 2012.

A-5798-17T4

stated (emphasis added):

5.1 To the extent allowed by applicable law, any controversy or claim arising out of or relating to this [c]ontract, or [c]ontract [d]ocuments, or any breach thereof, may be settled by binding arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association [(AAA)], and judgment upon the award rendered by the arbitrator(s) may be entered in any court having jurisdiction thereof.

5.2 The arbitration proceeding location shall be in the county in which the [p]roject is located.

Schneider alleged it completed its scope of work under the ESCC in January 2017 but the District withheld $462,269, claiming the work was unsatisfactory. On March 14, 2018, Schneider filed a demand for arbitration with the AAA pursuant to the arbitration provision set forth in Article 5.1 of the ESCC.

One month later, the District filed a verified complaint and an order to show cause (OTSC) in the Law Division, seeking to enjoin and dismiss Schneider's arbitration action. The complaint also alleged breaches of the ESCC and PASS Agreement and other causes of action related to Schneider's performance of work on the project. The District claimed all of the contract disputes should be litigated in the Law Division.

Schneider filed its answer to the complaint and opposition to the OTSC, countering the ESCC's arbitration provision was valid and enforceable.

A-5798-17T4

Schneider further argued the District's "allegations of defective work under the [ESCC] are inextricably intertwined with Schneider's claim for payment and should be resolved in the [a]rbitration proceeding . . . ."

On the return date of the OTSC, the trial judge rendered a tentative written decision granting the District's requested relief, but afforded the parties an opportunity to be heard. Thereafter, the judge issued a well-reasoned amplified statement of reasons, 3 thoroughly addressing the parties' arguments and applying the relevant law.

The trial judge acknowledged the validity of the arbitration provision, finding "no indication that [it] was included without negotiation or that it was an inconspicuous part of the [ESCC]." However, the judge further found by using the term, "may," the provision was permissive and not mandatory. Comparing the plain terms of the arbitration provision to other terms in the ESCC, the judge observed "the parties specifically used the word 'shall' when the terms were intended as mandatory." For example, "mandatory 'shall' language r[an] throughout the entirety of Article 2 [pertaining to payments], except for where '[p]ayments may [have been] withheld.'"

The trial judge found additional support for his conclusion in the governing law provision of the RFP, which "distinctly g[ave] the Burlington

3 See R. 2:5-1(b).

A-5798-17T4

Vicinage of the Superior Court . . . jurisdiction over disputes arising from the implementation of the District's ESIP." As such, the judge reasoned the RFP, which preceded the ESCC, "serve[d] as extrinsic evidence for the ESCC – an agreement made to satisfy ESIP requirements – and help[ed] to uncover the actual meaning of the arbitration clause in the ESCC."

In sum, the trial judge concluded:

the permissive, "may" in the ESCC arbitration clause ma[d]e[] arbitration optional. In order for the ESCC arbitration clause to require arbitration, the clause needed to include mandatory language that waived the right to adjudicate in the courts or there needed to be mutual consent by the parties. As neither of [those]

scenarios exist[ed] here, . . . the District's injunction request to restrain arbitration [is granted].

This appeal followed.

Schneider maintains the plain terms of the ESCC permit either party to select binding arbitration as a means for dispute resolution, which then compels the other party to arbitrate. In essence, Schneider claims the judge's interpretation of the arbitration provision renders the clause "superfluous" because a dispute resolution provision is unnecessary when both parties agree to arbitrate. Schneider further argues the judge erred in considering parol evidence because the ESCC contains a merger clause. We disagree.

A-5798-17T4

II.

Free access — add to your briefcase to read the full text and ask questions with AI

MEDFORD TOWNSHIP SCHOOL DISTRICT VS. SCHNEIDER ELECTRIC BUILDINGS AMERICAS, INC. (L-0787-18, BURLINGTON COUNTY AND STATEWIDE), 207 A.3d 265, 459 N.J. Super. 1 (N.J. Ct. App. 2019).

207 A.3d 265 (MEDFORD TOWNSHIP SCHOOL DISTRICT VS. SCHNEIDER ELECTRIC BUILDINGS AMERICAS, INC. (L-0787-18, BURLINGTON COUNTY AND STATEWIDE)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related