Dean v. Frank W. Neal & Associates, Inc.

166 S.W.3d 352, 2005 Tex. App. LEXIS 3870, 2005 WL 1189173
CourtCourt of Appeals of Texas
DecidedMay 19, 2005
Docket2-04-034-CV
StatusPublished
Cited by22 cases

This text of 166 S.W.3d 352 (Dean v. Frank W. Neal & Associates, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dean v. Frank W. Neal & Associates, Inc., 166 S.W.3d 352, 2005 Tex. App. LEXIS 3870, 2005 WL 1189173 (Tex. Ct. App. 2005).

Opinion

OPINION

TERRIE LIVINGSTON, Justice.

This construction defect case involves multiple summary judgments granted on limitations grounds. In three issues, William H. and Madelyn S. Dean contend that the trial court erred in granting summary judgments on their claims against appel-lees Frank W. Neal & Associates, Inc., HBC Engineering, Inc., David Lewis Builders, Inc., and David T. Lewis, individually, because the limitations period was tolled by application of the discovery rule and because the appellees are equitably estopped from asserting limitations as a result of their conduct. • Because the Deans failed to raise a fact issue on the discovery rule and equitable estoppel, we affirm the summary judgments for all of the appellees on limitations grounds.

Background

On November 10, 1995, the Deans entered into a contract with Nader Design Group (NDG) and David Lewis Builders, Inc. (DLBI) for the construction of a home, James Nader of NDG was the architect for the project, and DLBI was the builder. As part of the design process, the Deans’ architect hired Frank W. Neal & Associates, Inc., a structural engineering firm, to design the home’s foundation. When preparing the design, Neal used some information in a soils report'that HBC Engineering, Inc., another engineering firm, prepared in 1994 for a different architect. The soils report indicated a potential for movement in the soil below the house of approximately 2.1 inches. Consequently, Neal recommended that the house be designed with a suspended slab, or pier and beam, foundation. The Deans reject *355 ed this recommendation because it was too costly, and Neal designed a foundation that was slab-on-grade with some piers. According to Neal’s deposition testimony, he told Nader the new design would be less costly but not as good as a suspended slab. Construction of the home took place in 1996.

During construction, Neal and the Deans noticed some cracks in the foundation. Neal did not think the foundation was structurally compromised at that point, so he recommended that the cracks in the garage be repaired with an epoxy patch and that a flexible bed be laid under the tile in the other parts of the house where cracking had occurred. 1 There is no evidence that Neal’s recommendations were implemented, but construction was completed, and the Deans closed on the house in December 1996.

After they moved in, the Deans noticed cracks in the garage and “various places” in the house. By October 1997, more cracks had appeared, and later that month Nader met with Neal, Lewis, and Ralph Barnes of HBC to discuss how to mitigate the problem. At this meeting, the participants discussed chemically injecting the soil underneath the house to stop potential movement related to moisture in the soil caused by groundwater. Mrs. Dean was aware of this meeting and its purpose. In her deposition, Mrs. Dean admitted that she knew there had been some movement as of October 1997, which is why chemically injecting the soil was considered.

Between 1998 and 2002, Nader met with various parties, including Neal and Barnes, regarding the home’s foundation. The Deans believed that some or all of the appel-lees would pay for any necessary repairs to the home’s foundation. But at a meeting on January 23, 2002, the Deans discovered that there was no general agreement among the appellees to pay for such repairs.

The Deans filed suit against NDG, Neal, DLBI, Lewis, and HBC on January 28, 2002. They asserted negligence, breach of warranty, fraud, fraud-failure to disclose, fraud in a real estate action and fraud-false promise, DTPA, and breach of contract claims against the various parties. They later nonsuited NDG, Nader’s architectural firm. 2 Neal, DLBI and Lewis, and HBC subsequently filed separate motions for summary judgment contending that all of the Deans’ claims were barred by the applicable statutes of limitations. 3 The Deans filed a third amended petition alleging that the discovery rule applied to their claims and that the appellees were equitably estopped from asserting limitations because their conduct induced the Deans not to file suit. The trial court granted separate summary judgments in favor of each of the appellees.

Standard of Review

A defendant who moves for summary judgment on the affirmative defense of limitations has the burden to conclusively establish the defense. KPMG Peat Marwick v. Harrison County Hous. Fin. Corp., 988 S.W.2d 746, 748 (Tex.1999). The defendant must, therefore, conclusively prove when the cause of action accrued. Id. Additionally, the defendant must negate the discovery rale, if it applies and has been pleaded or otherwise raised, by proving as a matter of law that there is no *356 genuine issue of material fact about when the plaintiff discovered, or in the exercise of reasonable diligence should have discovered, the nature of its injury. Id. If the movant establishes that the statute of limitations bars the action, the nonmovant must then adduce summary judgment proof raising a fact issue in avoidance of the statute of limitations. Id.

Discovery Rule

The discovery rule is a limited exception to the statute of limitations. Computer Assocs. Int’l, Inc. v. Altai, Inc., 918 S.W.2d 458, 455 (Tex.1996). The discovery rule is applied when the nature of the injury is inherently undiscoverable. Id. at 456. Thus, the discovery rule should be applied only when “it is difficult for the injured party to learn of the negligent act or omission.” Id. A cause of action accrues when the plaintiff knew or should have known of the wrongful injury. KPMG Peat Marwick, 988 S.W.2d at 749-50. A plaintiff need not know the full extent of the injury before limitations begins to run. Murphy v. Campbell, 964 S.W.2d 265, 273 (Tex.1997).

Here, Mrs. Dean’s deposition testimony shows that the Deans first observed cracking in the garage in July 1996 while the house was under construction. In an affidavit attached to the Deans’ summary judgment responses, Mrs. Dean testified that after they moved into the house, they noticed “more minor problems” with cracking in the garage and “various places” in the house, but they were assured that “these were normal cosmetic cracks that would occur with settlement of the [residence.” But there is no indication as to who assured them so. Lewis’s affidavit states that after construction of the home was completed, he received a letter from Mr. Dean indicating that there had been movement in the foundation. But he could not locate the original letter, and the Deans did not produce it. The evidence also shows that by October 1997, when Nader began to call meetings regarding the problem, the parties had begun investigating chemically injecting the soil to dry up the moisture level.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
166 S.W.3d 352, 2005 Tex. App. LEXIS 3870, 2005 WL 1189173, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dean-v-frank-w-neal-associates-inc-texapp-2005.