Davis v. Starrett Bros.

147 S.E. 530, 39 Ga. App. 422, 1929 Ga. App. LEXIS 351
CourtCourt of Appeals of Georgia
DecidedMarch 6, 1929
Docket19118
StatusPublished
Cited by22 cases

This text of 147 S.E. 530 (Davis v. Starrett Bros.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Davis v. Starrett Bros., 147 S.E. 530, 39 Ga. App. 422, 1929 Ga. App. LEXIS 351 (Ga. Ct. App. 1929).

Opinion

Luke, J.

Lyle C. Davis brought his action for damages against Starrett Brothers Incorporated, alleging that while working in an elevator shaft on the first floor of a certain building in Atlanta as the employee of the Tyler Company, a carpenter who was in the employ of Starrett Brothers Incorporated and was working in the shaft five floors above him negligently dropped a hammer down the shaft and it fell upon him .and seriously injured him. The defendant was alleged to be negligent because it did not place something underneath its carpenters to prevent anything from falling down the shaft and injuring him, and for various other reasons which need not be stated here. After the plaintiff had rested his case and the defendant had submitted a part of its evidence, the defendant offered to amend its answer by pleading that the plaintiff was barred by reason of the fact he was working under the workmen’s compensation act, and was, under an agreement with the Tyler Company and a named insurance carrier, which had been approved by the industrial commission, receiving $15 a week for the injuries alleged in the petition. The plaintiff objected to the allowance of the amendment, moved to strike it, and demurred to it.'- The said objection, motion to strike, and demurrer were all overruled, and the plaintiff excepted pendente lite. The court then directed a verdict for the defendant, and a verdict was rendered accordingly. The plaintiff’s motion for a new trial as amended was overruled, and he excepted.

The motion for a new trial contains several special grounds which disclose no reversible error and warrant no special consideration. The remainder of the special grounds are governed by the [423]*423controlling question raised by the record, which is this: Was, or was not, the Tyler Company an independent contractor ? If it was, the plaintiff was entitled to go to the jury, and the direction of the verdict was error. If it was not, the direction of the verdict was proper. Before discussing the main question in the case, we deem it proper to say that the amendment to the answer was properly allowed. “All parties, whether plaintiffs or defendants, in the superior or other courts, whether at law or in equity, may at any stage of the cause, as matter of right, amend their pleadings in all respects, whether in matter of form or of substance, provided there is enough in the pleadings to amend by. The defendant after the first term can not set up new matter by way of amendment, except as provided in section 5640.” Civil Code (1910), § 5681. The affidavit to the plea that “the new facts or defense were not omitted from the original answer for the purpose of delay, and the same is now filed in good faith and not for the purpose of delay,” meets the requirements of the Civil Code (1910), § 5640. We hold also that the court properly overruled the demurrer to the amendment, and the motion to strike it. Attached to the amendment as “Exhibit A” was- a copy of the contract between Asa G-. Candler Incorporated and Starrett Brothers Incorporated, providing for the erection of a building by the latter for the former on a plot of ground on Peachtree and Ellis streets- in the City of Atlanta. Starrett Brothers Incorporated was to provide labor, equipment, and materials, and erect the building according to plans and specifications, and negotiate all employment and purchases and let all subcontract work. It agreed also to provide workmen’s compensation, public liability, and contingent insurance. “Exhibit B,” attached to the plea, is the contract between Starrett Brothers Incorporated and the Tyler Company. This contract covers twelve pages and is too long to -be set out fully here. However, since by it the relationship of the parties thereto is to be determined, and that relationship controls this case, this contract demands very careful consideration.

The salient features of the latter contract appear from the following: Starrett Brothers Incorporated is designated “Builder,” and the Tyler Company “subcontractor.” The contract provides: 1st. That “to the satisfaction of the Builder and the Architect,” the Subcontractor shall provide all materials and perform all work [424]*424mentioned in the specifications (and addenda thereto, if any), and shown on the drawings prepared by the Architect. 2d. The Subcontractor shall abide by the general conditions in the specifications of the Architect in so far as they apply to the work. And where the contract is at variance with the plans and specifications it controls. 3d.. “The Builder shall furnish the Subcontractor such further drawings or explanations as may be necessary to detail and illustrate the work to be done, and the Subcontractor shall conform to the same as part of this contract, as far as may be consistent with the original drawings and specifications. . . ” “The Subcontractor shall exercise the utmost diligence to obtain the drawings and information necessary to fulfill the work herein contemplated,” and “shall, from time to time, and at frequent intervals, inform the builder in writing as to what drawings or information may still be required. . . ” 4th. “All workmanship and material . . shall be subject at all times to the inspection and approval of the Architect, to whom the same shall be made satisfactory within the meaning of the plans and specifica7 tions and this contract;” and the subcontractor shall provide facilities at all times for the inspection of the work by the Architect, the Builder, or the authorized representative of either or both. Within twenty-four hours after receiving written notice to that effect, the subcontractor shall proceed to remove all material condemned by the Builder as unsound or improper, and to take down all portions of the work so condemned as unsound or improper, or in any way failing to conform to the drawings and specifications, replacing same, without extra expense, with material and workmanship satisfactory to the Architect or Builder, or both. 5th. “Should the Subcontractor at any time refuse or neglect to supply a sufficient number of properly skilled workmen, or sufficient materials of the proper quality, or fail-in any respect to prosecute the work with promptness and diligence, or fail in the performance of any of the agreements herein contained, the Builder shall be at liberty to provide any such labor and materials, and deduct the cost thereof from any money then due or thereafter to become due the Subcontractor;” and the builder shall have the right to cancel the contract and complete the work under it, paying the subcontractor the excess, if any, of the unpaid balance due it over the expense incurred by the builder in completing the contract: if the balance [425]*425be against the subcontractor, it shall pay the builder the difference. 6th. “Should the Owner or Architect make changes in the plans and specifications which would decrease the amount oí work to be performed or materials furnished under this contract, the Builder shall have the right to order curtailment in conformity therewith, and the Subcontractor shall make proper allowance to the. Builder to the value of the work and materials so omitted.” 7th. An officer of the builder must sign confirming orders for any overtime, extra work, or materials furnished under any order from the Builder’s job representative, to enable the subcontractor to collect for any amount in excess of that stated in the contract. 8th.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harris v. City of Chattanooga, Tenn.
507 F. Supp. 365 (N.D. Georgia, 1980)
Clements v. Georgia Power Co.
252 S.E.2d 635 (Court of Appeals of Georgia, 1979)
Savannah Electric & Power Co. v. Edenfield
164 S.E.2d 366 (Court of Appeals of Georgia, 1968)
Boehm v. Witte
231 A.2d 240 (New Jersey Superior Court App Division, 1967)
Barbree v. Shelby Mutual Insurance Co.
123 S.E.2d 905 (Court of Appeals of Georgia, 1962)
Cash v. American Surety Company
114 S.E.2d 57 (Court of Appeals of Georgia, 1960)
American Automobile Insurance v. Tanner
101 S.E.2d 875 (Court of Appeals of Georgia, 1958)
Joe H. Mosley v. George A. Fuller Co.
250 F.2d 686 (Fifth Circuit, 1957)
American Casualty Co. v. Harris
101 S.E.2d 618 (Court of Appeals of Georgia, 1957)
Old Republic Insurance Co. v. Pruitt
97 S.E.2d 521 (Court of Appeals of Georgia, 1957)
Smith v. Maryland Casualty Company
91 S.E.2d 188 (Court of Appeals of Georgia, 1956)
St. Paul-Mercury Indemnity Co. v. Alexander
65 S.E.2d 694 (Court of Appeals of Georgia, 1951)
Blair v. Smith
41 S.E.2d 133 (Supreme Court of Georgia, 1947)
Scott v. Minor
191 S.E. 263 (Court of Appeals of Georgia, 1937)
Liberty Lumber Co. v. Silas
175 S.E. 265 (Court of Appeals of Georgia, 1934)
Swift & Co. v. Alston
173 S.E. 741 (Court of Appeals of Georgia, 1934)
Robinson v. Reese
165 S.E. 744 (Supreme Court of Georgia, 1932)
Cooper v. Dixie Construction Co.
165 S.E. 152 (Court of Appeals of Georgia, 1932)
Public Indemnity Co. v. Browning
164 S.E. 166 (Court of Appeals of Georgia, 1932)
Buffalo Forge Co. v. Southern Railway Co.
159 S.E. 301 (Court of Appeals of Georgia, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
147 S.E. 530, 39 Ga. App. 422, 1929 Ga. App. LEXIS 351, Counsel Stack Legal Research, https://law.counselstack.com/opinion/davis-v-starrett-bros-gactapp-1929.