Buffalo Forge Co. v. Southern Railway Co.

159 S.E. 301, 43 Ga. App. 445, 1931 Ga. App. LEXIS 419
CourtCourt of Appeals of Georgia
DecidedJune 15, 1931
Docket21024
StatusPublished
Cited by5 cases

This text of 159 S.E. 301 (Buffalo Forge Co. v. Southern Railway Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Buffalo Forge Co. v. Southern Railway Co., 159 S.E. 301, 43 Ga. App. 445, 1931 Ga. App. LEXIS 419 (Ga. Ct. App. 1931).

Opinion

Bell, J.

(After stating the foregoing facts.) A materialman who furnishes material to a subcontractor for the improvement of real estate is not entitled to a lien upon the property so improved, where the subcontractor has no contractual relation with the owner of the realty. General Supply Co. v. Hunn, 126 Ga. 615 (55 S. E. 957). The question for decision in this case is whether the Seeley company was a subcontractor. If so, the judgment of the superior court was correct, but if this company was a contractor, and not a mere subcontractor, the plaintiff was entitled to its lien and the court erred in sustaining the certiorari. The solution of this question will depend upon the nature of the contract between the railway company, as owner, and the engineers company, by which the contract was made with the Seeley company for the installation of the heating system. If the engineers company was itself the contractor, then the Seeley company was a subcontractor, but if the engineers company was made the agent of the railway company for the erection of the building, the Seeley company became the contractor, and the plaintiff’s claim of lien should have been established.

The following is a statement of the material portions of the contract between the railway company and the engineers company:

[447]*447“New York, March 14, 1928.

“Southern Railway System, Washington, D. C.

“We hereby propose to design and construct for you at Atlanta, Georgia, a two-story addition to office building and a five-story addition to freight warehouse, together with such other changes to lower floors of these buildings as may be necessary.

“I. Service to be rendered. With respect to this work we propose to act as your own engineering, construction and purchasing departments, being guided in all respects by such instructions as you may from time to time give us. As engineers, we will make all necessary engineering studies and determinations, recommend to you the type and character of equipment and of construction required, and prepare plans and specifications for equipment, material and construction work. As constructors, we will execute with our own forces the construction and install the machinery and equipment, subletting parts of the work when it is to your advantage to do so, and .turn the completed work over to you ready for regular use. As purchasing agents, we will purchase the necessary machinery, equipment and materials.

“We will furnish at our own expense: (a) The service of the executive officers of the company who will direct and oversee the work performed under this agreement. (b) The service of the construction department in our home office. (c) The service of the purchasing department in our home office which will assist in tlie purchase of the machinery, apparatus and materials, (d) The service of the accounting and auditing departments in our home office, (e) All other expenses of our home office, excepting only the salaries of employees, and materials utilized, in the engineering and drafting departments for your work.

“II. Compensation. You are to pay us for the services specified the sum of $55,000, which covers the work included in our estimate of $739,000, dated March 14, 1928. In case the actual cost of the work included in the estimate is less than the estimated cost, our compensation is to be reduced to 7-1/2 per cent, of the actual cost of the completed work. Compensation is -payable in installments on the last of each month in the same proportionate amount that the actual expenditure made during that month bears to the total estimated cost of the work, until 90 per cent, of the total is paid, the balance of 10 per cent, being payable on completion of the [448]*448work. If material change in the scope of the work is ordered by yon there shall be added to or subtracted from this amount a sum equal to 7-1/2 per cent, of the estimated cost of the work added to or deducted from that now contemplated.

“III. Cost of the work. It is understood that ‘cost of the world shall include the following items whether commitments or expenditures are made by you direct or by us for your account: (a) The cost of all materials, machinery, equipment and labor, (b) The cost of tools and construction equipment purchased and the rental of any equipment hired, removing at mutually agreed depreciation such major construction equipment as you do not wish to retain—-or we will supply any part of such equipment on a rental basis, (c) The cost, at salary rates, of men in the engineering and drafting departments in our home office or in the field, in connection with the engineering or designing, the choice and purchase of materials and apparatus, and the inspection of the work. (d) The cost of a works office, including the salaries and expenses of a superintendent of construction, an accountant, a purchasing agent, and such assistants as they may require; the cost of all field engineering and inspection; the expense of maintaining the works office, (e) The cost of insurance and any expense incurred in connection with any accident or damage to person or property. (/) Any traveling expenses or expenses of a similar character and any other expenditures, we may make except for items specified in section 1, as furnished at our own expense.

“IV. Disbursements. [1] We will make all payments for material, labor, equipment, services, etc., for your account from funds to be advanced to us by you for the purpose, giving you each month a detailed .statement of expenditures during the previous month, supported by proper vouchers. [2] Or should we so elect, we will make such pa3unents from our own funds, giving you periodical statements of disbursements, the amounts of such statements to be paid to us within ten (10) da3's from date.

“V. Purchases and contracts, [a] You will have as full control as 3fou care to exercise of the purchase of materials and equipment and of the letting of such sub-contracts as may seem desirable, [b] All contracts and orders placed by us, pa3uolls and other obligations, shall be in our name, ‘United Engineers & Constructors, Inc/ and it is understood that we assume all pecuniary liabil[449]*449ity under or by reason of such obligations. If funds are advanced by you, in accordance with the first section of Art. IV, we will give you a surety bond, or an escrow agreement covering the deposit of marketable securities, to guarantee that such funds advanced will be used for the purpose expressed in our requests for these advances.

“VI. Insurance. Unless otherwise directed by you, we will place insurance covering liability to the public and to employees engaged on this work, with limits of $10,000 for any one person and $20,000 for any one accident, unless workmen’s compensation laws make it advisable to secure insurance in some other form or amount. The policies will be in the usual form. If you so request, we will place insurance covering damage to the work, or any part of it, by fire.

“VII. Progress reports. We will render reports to you monthly showing the progress of the work in its various parts and any changes that it may seem advisable to make in the estimates of cost or of time required for completion.

“VIII. Audit. Our correspondence, records, vouchers, and books of account, in so far as work clone or money expended under this agreement are concerned, will be open to your inspection.

“IX.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harris v. City of Chattanooga, Tenn.
507 F. Supp. 365 (N.D. Georgia, 1980)
Hodsdon v. Whitworth
266 S.E.2d 561 (Court of Appeals of Georgia, 1980)
Clements v. Georgia Power Co.
252 S.E.2d 635 (Court of Appeals of Georgia, 1979)
Swift & Co. v. Alston
173 S.E. 741 (Court of Appeals of Georgia, 1934)
Nichols v. Lindsey
165 S.E. 868 (Court of Appeals of Georgia, 1932)

Cite This Page — Counsel Stack

Bluebook (online)
159 S.E. 301, 43 Ga. App. 445, 1931 Ga. App. LEXIS 419, Counsel Stack Legal Research, https://law.counselstack.com/opinion/buffalo-forge-co-v-southern-railway-co-gactapp-1931.