Joe H. Mosley v. George A. Fuller Co.

250 F.2d 686, 1957 U.S. App. LEXIS 4457
CourtCourt of Appeals for the Fifth Circuit
DecidedDecember 19, 1957
Docket16751_1
StatusPublished
Cited by5 cases

This text of 250 F.2d 686 (Joe H. Mosley v. George A. Fuller Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Joe H. Mosley v. George A. Fuller Co., 250 F.2d 686, 1957 U.S. App. LEXIS 4457 (5th Cir. 1957).

Opinion

CAMERON, Circuit Judge.

Appellant Mosley filed this action in tort against appellee George A. Fuller Co. to recover damages for personal injuries he alleged he had received when he was struck by certain heavy materials negligently thrown from the roof of a building by appellee’s servants. Appellee was general contractor in the construction, for the State Hospital Authority of Georgia, of the Eugene Tal-madge Memorial Hospital. Appellee had, by written subcontract which incorporated into its terms the provisions of the general contract, agreed that Mechanical Contractors and Engineers, Inc. would perform certain designated work in connection with the plumbing,heating and other installations in the hospital. Appellant was employed by Mechanical. Instead of making claim against his employer under the Georgia Workmen’s Compensation Law, Code, § 114-101 et seq., appellant brought this tort action direct against appellee, the general contractor.

Appellee exhibited with its pleadings a copy of the general contract between it and the State of Georgia and a copy of the subcontract between it and Mechanical, alleging that under their terms Mechanical “was in fact this defendant’s [appellee’s] agent and subcontractor at the time of plaintiff’s [appellant’s] alleged injury and he was an employee of defendant’s and defendant’s agent and subcontractor and is therefore barred by the Workmen’s Compensation Act of Georgia from bringing suit at common law.”

Appellant moved for judgment on the pleadings, and appellee moved for summary judgment 1 “upon the ground that there is no genuine issue as to any material fact, and that the defendant is entitled to judgment on the pleadings as a matter of law.” The parties entered into a stipulation as to certain facts 2 and, based upon the pleadings, the exhibits and the stipulations, the court below denied appellant’s motion and entered summary judgment for appellee. 3

*688 From that judgment appellant has appealed, claiming that he was entitled to maintain this action against appellee under Georgia statutes 4 and decisions, 5 and asserting that, under the decision of the Supreme Court of Georgia in Blair v. Smith, 6 1947, 201 Ga. 747, 41 S.E.2d 133, he was not a servant of appellee, but was an employee of Mechanical, an independent contractor. Appellee contends, on the other hand, that appellant’s exclusive remedy was under the Georgia Workmen’s Compensation Law 7 on the ground that the relationship existing between appellee and Mechanical, appellant’s employer, “at the time of the alleged injury, as evidenced by said contract, was in fact that of master and servant as distinguished from independent contractor * * * ” It stakes its case chiefly on the decision of the Court of Appeals of Georgia in Davis v. Starrett Bros., Inc., 8 1929, 39 Ga.App. 422, 147 S.E. 530, which it claims is “on all fours with the facts in the case at bar.”

We do not think that the contract before us is exactly the same as that involved in the Blair case, or that dealt with in the Davis case, but on principle, supported by the Georgia decisions, we are of the opinion that the relationship between appellee and Mechanical was that of independent contractor, rather than principal and agent, or master and servant.

No good purpose will be served by attempting a detailed analysis of the provisions of the contract between appellee and Mechanical, as the parties do in their briefs in an effort to identify it with the cases upon which they respectively rely. In it, Mechanical is referred to throughout as “Sub-Contractor” and appellee as Contractor; Mechanical agrees to provide all the materials, labor, equipment and other necessary items and perform the work therein described on the hospital according to the plans and specifications forming a part of the contract between appellee and the State of Georgia, the work to be subject to the approval of appellee and the architect in charge for an agreed contract price, the language being similar to that found generally in such subcontracts. 9

*689 A careful examination of the provisions of the contract before us fails to reveal any provisions not normally found in such instruments; and, moreover, the criticisms of the contract are met, in most instances, by the specific holdings of the Blair case, a part of which decision we quote: 10

“Smith had a valid cause of action against Blair, should it be determined that Wilson, his immediate employer, was an independent contractor, rather than a servant, of the general contractor, Blair * * *
“ ‘ * * * the test to be applied in determining whether the relationship of the parties under a contract for the performance of labor is that of employer and servant, or that of employer and independent contractor, lies in whether the contract gives, * * * the right to control the time, manner, and method of executing the work, as distinguished from the right merely to require certain definite results in conformity to the contract.’
****** “Under provisions of paragraphs * * * [0f the Blair contract], the subcontractor will begin work promptly, will carry the work forward rapidly, with due diligence and without delay, and will not delay or interfere with the work of the contractor. Should it be determined that the subcontractor is delaying the work, the contractor shall have the right to employ additional men and charge the expense to the subcontractor. The subcontractor is to indemnify the contractor against any loss by reason of delay. * * * The provision that, should the subcontractor Wilson delay the progress of the work, the general contractor Blair might employ additional men, sufficient to complete the contract within the time specified by the general contract between him and the Government, would not make the subcontractor Wilson a servant of the general contractor Blair.
“The provisions of * * * the contract between Wilson and Blair, giving Blair the right to inspect the premises and the progress of the work, is a usual provision and, * * * is not inserted for the purpose of controlling the contractor in his methods, but for the purpose of permitting the general contractor to assure himself that the specifications of the contract are being reached step by step as the work progresses.
“The contract provides for definite and positive results, but does not authorize the general contractor to control the method and manner of executing the work. In Davis v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Doreen M. White v. Excalibur Insurance Company
599 F.2d 50 (Fifth Circuit, 1979)
Norton v. McShane
33 F.R.D. 131 (N.D. Mississippi, 1963)
Murchison v. Kirby
27 F.R.D. 14 (S.D. New York, 1961)
Bowyer & Johnson Construction Co. v. White
255 F.2d 482 (Fifth Circuit, 1958)
Bowyer & Johnson Construction Company v. Joe White
255 F.2d 482 (Fifth Circuit, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
250 F.2d 686, 1957 U.S. App. LEXIS 4457, Counsel Stack Legal Research, https://law.counselstack.com/opinion/joe-h-mosley-v-george-a-fuller-co-ca5-1957.