Davis v. Holsten

621 S.E.2d 101, 270 Va. 389, 2005 Va. LEXIS 99
CourtSupreme Court of Virginia
DecidedNovember 4, 2005
DocketRecord 050215.
StatusPublished
Cited by11 cases

This text of 621 S.E.2d 101 (Davis v. Holsten) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Davis v. Holsten, 621 S.E.2d 101, 270 Va. 389, 2005 Va. LEXIS 99 (Va. 2005).

Opinion

ELIZABRTH B. LACY, Justice.

In this appeal, Kenneth A. Davis asserts that the trial court erred in ruling that substantial compliance does not apply to an escrow agreement obligating him to remove and replace synthetic stucco siding and rotten wood from a house and seeks a reversal of the trial court's finding that he did not comply with the terms of the agreement. Because we conclude that the trial court was correct in its application of the law and that its findings of fact are supported by the record, we will affirm the judgment of the trial court.

FACTS AND PROCEEDINGS

On July 11, 2002, Davis contracted to sell his Fairfax, Virginia, home to Stephen E. and Tami S. Holsten. At the time of contracting, the house was coated with Exterior Insulation Finishing System (EIFS), a type of synthetic stucco, which had caused water damage to the home. Paragraph 33 of the sales contract stated that prior to the date of settlement, Davis would "have or cause to have the Stucco replaced with hard coat Stucco." If the repairs were not made prior to settlement, Davis would escrow $50,000 until "repairs are made and Stucco is replaced along with any rotted or damaged wood." Davis had not made the repairs by the date of settlement; thus, he, the Holstens, and Virginia Settlement Group, L.L.C. (VSG), an escrow agent, executed a contract entitled "Escrow Agreement" (the Agreement). Paragraph 2 of the Agreement incorporated the provisions of Paragraph 33 of the sales contract and required Davis to deliver $50,000 to VSG at settlement and to engage a contractor to do the work within ten days of the execution of the Agreement. Under the Agreement, when the obligations set out in Paragraph 2 were completed, VSG would release the escrowed funds to Davis. If the obligations were not completed within one year, VSG would pay the escrowed funds to the Holstens upon their written notification that the repairs and replacement were not completed. * Paragraph 4 of the Agreement also provided that Davis would indemnify the Holstens for losses, damages, costs, and attorney's fees associated with completing the reinstallation.

On August 19, 2002, Davis hired a contractor to perform the work required under the Agreement. The work did not progress smoothly. In an exchange of correspondence in early 2003, the Holstens notified Davis of their dissatisfaction with the contractor's progress, stating the work was "`complete' but not done." In a February 6, 2003 letter, Davis informed the Holstens that he had inspected the reinstallation and believed he was entitled to the escrowed money. He stated that he had contracted for the repair work within ten days of closing and that "[t]he stucco is replaced along with any wood." Davis told the Holstens he expected "no delays" from them.

By a letter of the same date, Davis reported to VSG that "the repairs are now completed" and that it should consider the letter as *103 Davis' demand for release of the escrowed funds. In the letter, Davis acknowledged matters of disagreement between himself and the Holstens but asserted that the Agreement does not allow withholding release of the funds "over a few very small details."

VSG refused to release the funds, stating that Davis' demand "did not create an absolute right to receive" the funds and that it could not release the funds "unless and until it is clear that the terms of the escrow have been met." Davis then filed a Bill of Complaint against the Holstens and VSG for specific performance of the Agreement and for breach of contract. He contended that since he had performed, or at least substantially performed, all of his obligations under the Agreement, the Holstens and VSG had breached their duty to him by failing to release the $50,000 in escrow. Prior to trial, VSG paid into court the escrowed funds and was dismissed as a party.

At trial, various experts testified regarding the stucco reinstallation. Ronald E. Wright, an expert in engineering and in providing estimates for costs related to residential construction, testified on behalf of Davis. The trial court refused to allow Wright to testify whether, in Wright's opinion, the work the Agreement required was "substantially complete." The trial court concluded such testimony was not relevant; the contracting parties "could have said substantial performance. . . . But the parties didn't do that. . . . Every contract has a term of reasonableness that is part of it. . . . But that is a far cry from substantial completion." Davis objected to this ruling. Wright was allowed to testify that he estimated the total cost to repair the installation was $4,692 and that apart from the specific repairs about which he had testified, the installation was "complete."

Stanley Yeskolski, a certified EIFS inspector, testified for the Holstens. Prior to the litigation, the Holstens had engaged Yeskolski to inspect the property and prepare a stucco inspection report. At trial, Yeskolski testified on proper stucco reinstallation procedures and on the shortcomings of the repair work. He testified that, among other things, crucial expansion joints were not installed at the front of the house and all the EIFS had not been removed from the exterior of the home. Yeskolski did not "think the installation was complete" because of the elements left out or performed incorrectly.

The Holstens also called Ralph D.(Donnie) Davis, a specialist in EIFS repair and restoration. Based on his inspection of the home prior to the reinstallation and his visual observations of the home after reinstallation, he opined that all of the rotten wood under the synthetic stucco had not been removed. Donnie Davis, like Yeskolski, identified a number of problems with the stucco reinstallation and recommended "completely removing it, put[ting] it in the dumpster, and start[ing] over" at a cost he estimated to be in excess of $50,000.

At the close of Davis' case in chief, the trial judge granted the Holstens' Motion to Strike Count I for specific performance because VSG had paid the funds into court and was no longer a party to the case. After the parties rested, the trial court, again relying on the language of the Agreement, concluded that the greater weight of the evidence did not show that the conditions for release of the escrowed funds were met because EIFS stucco remained under a bay window and control and expansion joints reasonably necessary for appropriate repairs had not been installed. Accordingly, the trial court held that Davis had not carried his burden of proof to show that the Holstens had breached the Agreement and entered judgment in favor of the Holstens. From that decision, Davis appeals to this Court.

DISCUSSION

Although Davis raises three assignments of error on appeal, his basic contention is that under the facts of this case, "a reasonable person could find that Davis completed, or at least substantially completed, his obligations under the escrow agreement." We begin by considering Davis' claim that the trial court erred in concluding that substantial compliance does not apply to the Agreement in this case.

*104 The Agreement

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tim Duy Pham v. Xuan Nguyen
Court of Appeals of Virginia, 2025
Total Quality Logistics v. Riverside Turf, LLC
Court of Appeals of Virginia, 2022
Scott v. Clarke
355 F. Supp. 3d 472 (W.D. Virginia, 2019)
Psychiatric Solutions of Virginia, Inc. v. Finnerty
676 S.E.2d 358 (Court of Appeals of Virginia, 2009)
Nichols Const. v. Virginia MacHine Tool
661 S.E.2d 467 (Supreme Court of Virginia, 2008)
F & W Management Corp. v. American Shelter Corp.
70 Va. Cir. 243 (Roanoke County Circuit Court, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
621 S.E.2d 101, 270 Va. 389, 2005 Va. LEXIS 99, Counsel Stack Legal Research, https://law.counselstack.com/opinion/davis-v-holsten-va-2005.