Davis Sewing Machine Co. v. United States

60 Ct. Cl. 201, 1925 U.S. Ct. Cl. LEXIS 557, 1925 WL 2797
CourtUnited States Court of Claims
DecidedJanuary 26, 1925
DocketNo. B-17
StatusPublished
Cited by11 cases

This text of 60 Ct. Cl. 201 (Davis Sewing Machine Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Davis Sewing Machine Co. v. United States, 60 Ct. Cl. 201, 1925 U.S. Ct. Cl. LEXIS 557, 1925 WL 2797 (cc 1925).

Opinion

GRAi-iam, Judge,

delivered tbe opinion of the court:

The contract in this case was dated the 5th day of August, 1918, and was for the manufacture of Very pistols. These pistols were to be used for giving signals by firing a charge which exploded with certain lighting effects. Delivery was to be commenced on the 1st of September, 1918, and completed on the 1st of March, 1919. The number of pistols to be delivered was 75,000, for which the plaintiff was to receive payment in the sum of $375,000. The contract contained a clause giving the defendant the right to terminate the contract at any time under certain conditions. The armistice having been declared in November, on the 11th of December the defendant, through the Ordnance Department, addressed a communication to the plaintiff stating that “you are requested immediately to suspend further operations under your contract * * * and to order no further materials or facilities,” and further, “to enter into no further subcontracts ” or make any “ further commitments and incur no further expenses,” and stated that the request was made with the view to the negotiation of a supplemental contract providing for cancellation, settlement, and adjustment of the existing contract in a manner that would permit a more prompt settlement and payment than would be practicable under the terms of the existing contract. It concluded by asking for immediate acknowledgment of receipt of the notice and an indication of plaintiff’s decision to comply with or reject the request. On December 14 this letter was forwarded to the plaintiff with a letter from the representative of the Ordnance Department, stating that upon acceptance of the request the negotiation of a settlement in the form of a supplemental contract would be initiated by the St. Louis district claims board, and in this ivay plaintiff would get a more prompt settlement and payment than under the terms of the existing contract.

Replying to these several letters, on the 18th of December the plaintiff acknowledged the notice of “ suspension of the above contract,” stating “ we accept this suspension, effective December 18, 1918, without prejudicing our rights under said contract,” and further, “ we take it from your request that immediate steps will be taken toward the negotiation [215]*215of a settlement in the formation of a supplemental contract* thereby affording a prompt adjustment, settlement, and payment arising from the suspension and eventual cancellation of the contract, and accept this condition as a consideration of our acceptance of the request of suspension.” On December 27 following, the secretary of the Ordnance Department claims board at St. Louis acknowledged this communication of the plaintiff, saying that it was the wish of the Ordnance Department to do all in its power consistent with the interests of the Government to arrive at a settlement which would enable the plaintiff to take up its regular line of business with the least delay, and to this end inclosed an outline of the method for presenting the claim. The plaintiff was requested to give this careful study and be prepared to act. Further instructions were also given as to preparation of the claim upon printed blanks that would be later furnished.

Pursuant to this correspondence the plaintiff on January 16, 1919, filed an itemized claim in the sum of $189,507.38, in which was a claim for profit of $1.66 each on 30,000 pistols which could have been completed before the termination of the contract but for the delay caused by the Government’s changes in the specifications and drawings. Against this claim the plaintiff entered a credit of $18,211.08 for certain materials, the property of the Government, which had been turned back to the Government, and then sold to and retained by the contractor, leaving a net claim of $171,296.30. Thereafter a partial payment and supplemental contract was entered into. Under this supplemental contract the plaintiff was paid the sum of $103,650.66 as an advance payment, and it was stipulated that the United States agree to pay such additional sum which, together with this last-named sum, would cover such portion of his expenditures, obligations, and liabilities necessarily incurred and for work, labor, and services rendered in connection with the performance of the original contract as would be properly and fairly apportionable to the uncompleted part thereof, enumerating the particular classes of items for which payment was to be made. In this supplemental contract the plaintiff waived all claim to prospective profits which he might have made by the performance of that portion of [216]*216said original contract which, “under the terms of this supplemental agreement, will not be performed.” It was also provided that in addition to the sums to be paid, as just mentioned, there should be paid such sums as the Secretary of War may deem fair and just to compensate the contractor for expenditures, obligations, and liabilities necessarily incurred, and for work, labor, and services rendered under the original contract or in preparation for the performance thereof or under this supplemental contract. Thereafter, on further hearing, the War Claims Board awarded the plaintiff the additional sum of $14,192.25, which was tendered in full settlement of its claim under the original and supplemental contracts, making a total of $111,842.91 found due under the contract. In arriving at this sum a part of an item of $9,461.72, claimed by the plaintiff as 10 per cent profit on the greater part of the contractor’s claim, as shown by Finding VI, amounting to $3,467.74, was disallowed.

The item of $49,800 claimed as profits by the plaintiff on the pistols which he claimed could have been completed and delivered before the suspension of the contract but for the delay in the work caused by the Government, was disallowed on the ground that it was prospective profits. The contractor refused to accept this proposed final settlement and took an appeal to the War Department Board of Contract Adjustment, which board affirmed the decision of the claims board. It does not appear that any final appeal was taken to the Secretary of War, as provided by the contract.

The plaintiff is here suing apparently, although his claim has assumed different forms and is in different amounts in his petition and proof, for profits which it claims it would have made on pistols that could have been completed and delivered before the suspension of the contract had not the Government delayed the performance of it.

The original contract contained a provision for its termination at the will of the Government, and, except as provided in the clause for termination, is in the same position as a contract made subject to the provisions of the act of June 15, 1917, which the courts have held must be taken to have been read into the contract. See Meyer Scale Co. v. [217]*217United States, 57 C. Cls. 26, and Bussell Motor Car Co. v. United States, 261 U. S. 514-524. In the last quoted cases it was held that where there was a termination clause there could be no recovery for loss of profits. The right to terminate necessarily contemplates the possibility of not being allowed to complete the contract, with the attendant loss of profits, and the party’s bid includes this risk. It also includes the possibility of a termination before any of the articles contracted for are completed. Thus, the right to recover prospective profits is negatived by the very insertion of á termination clause.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Questar Builders, Inc. v. CB Flooring, LLC
978 A.2d 651 (Court of Appeals of Maryland, 2009)
NGC Investment & Development, Inc. v. United States
40 Cont. Cas. Fed. 76,787 (Federal Claims, 1995)
Salsbury Industries v. United States
35 Cont. Cas. Fed. 75,661 (Court of Claims, 1989)
Torncello v. United States
681 F.2d 756 (Court of Claims, 1982)
G. L. Christian and Associates v. The United States
312 F.2d 418 (Court of Claims, 1963)
G. L. Christian & Associates v. United States
160 Ct. Cl. 1 (Court of Claims, 1963)
Librach v. United States
147 Ct. Cl. 605 (Court of Claims, 1959)
New Rawson Corporation v. United States
55 F. Supp. 291 (D. Massachusetts, 1943)
Middlebrook v. United States
67 Ct. Cl. 294 (Court of Claims, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
60 Ct. Cl. 201, 1925 U.S. Ct. Cl. LEXIS 557, 1925 WL 2797, Counsel Stack Legal Research, https://law.counselstack.com/opinion/davis-sewing-machine-co-v-united-states-cc-1925.