Meyer Scale & Hardware Co. v. United States

57 Ct. Cl. 26, 1922 U.S. Ct. Cl. LEXIS 536, 1922 WL 1839
CourtUnited States Court of Claims
DecidedJanuary 9, 1922
DocketNo. 34678
StatusPublished
Cited by8 cases

This text of 57 Ct. Cl. 26 (Meyer Scale & Hardware Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Meyer Scale & Hardware Co. v. United States, 57 Ct. Cl. 26, 1922 U.S. Ct. Cl. LEXIS 536, 1922 WL 1839 (cc 1922).

Opinions

DowNey, Judge,

delivered the opinion of the court.

The plaintiff seeks to recover for certain alleged losses occasioned by the suspension, modification, and partial cancellation of a contract which it had on January 31, 1919, entered into with the "United States for the furnishing of 1,185 suspension crane scales at $155 per scale and includes in its claim anticipated profits of $78,408.46 on 688 of the scales as to which the contract was canceled. As presented to us this last-mentioned part of the claim constitutes the chief, practically the only, subject of material controversy.

These scales were intended for use on vessels of the Navy, particularly on destroyers, and on February 14, 1919, plaintiff was notified that due to a change recently made in the equipment of ships the 300 scales scheduled for delivery at the Boston Navy Yard would not be needed and that investigation was being made to ascertain whether those scheduled for delivery at other points were still desired, but at a conference had it was ascertained that this action was taken because the scales were unsuitable by reason of size of platform for use on destroyers and the difficulty was overcome by agreement as to reduction of size.

On February 25, 1919, plaintiff was notified that most of the scales called for by the contract would not bej needed, that investigation was being made to ascertain the exact quantity that would be needed, and was requested not to proceed with the manufacture of scales, and to notify its subcontractors accordingly, and also to advise whether it could make a reduction in the quantity without incurring damage, but plaintiff, assuming that this action; like that of February 14, was because of the size of the scales, a matter which had been adjusted, made no reply to this letter and on March 21, 1919, the plaintiff was further advised by the Bureau of Supplies and Accounts, Navy Department, that due to changes in the equipment of ships of the Navy many of the scales called for by the contract would not be needed and was informed of the respective numbers which would be needed at stated yards and stations, a total of 497.

Deliveries having been in the meantime suspended, the plaintiff on June 7, 1919, requested, for reasons stated,, authority to make shipment of the 497 scales mentioned in [38]*38the Bureau’s letter of March 21, 1919, stipulating that “by so doing we do not in any way prejudice ourselves on the balance of the original order which will come up on final adjustment,” and, under the same date, whether before or after the receipt of plaintiff’s letter does 'not appear, the Bureau of Supplies and Accounts issued to the plaintiff instructions for the shipment of the scales required under the contract in question stated in the letter of March 21, under items 1 to 6, but excluding any shipment to Mare Island, and the plaintiff at subsequent times delivered the 497 scales as directed and was paid therefor the contract price.

On August 18, 1919, the plaintiff was informed by letter that the requirements for scales had been taken up with all yards and stations and that “no further additions will be made to the reduced quantities as now called for under contract 45987.”

It is conceded by the defendant that there is a right of recovery on the part of the plaintiff, and the conceded amount is but comparatively little less than that claimed, $15,582.70 conceded as against $16,853.59 claimed, aside, of course, from the wholly disputed claim for anticipated profits. Upon plaintiff’s showing as to a damage in the sum of $4,966.65 by reason of directed suspension of the work and a loss of $11,886.94 on materials, etc., provided for the filling of the contract as originally made, coupled with the fact that the defendant lias not made any real attempt to controvert these figures, we have considered the claim of the plaintiff in these respects as established, and there remains for solution only the question as to the right of the plaintiff to recover its prospective profits on 688 scales which it was not permitted to deliver, alleged by it to be $78,408.46, or $113.96-f- per scale, contract price of which was $155.00.

The plaintiff’s contention is that there was a partial cancellation of the contract without right, a refusal to perform in full, and therefore a breach, and that the profits that it would have earned are recoverable as a part of its damage. The defendant predicates its defense on the proposition that [39]*39even though there was in terms no cancellation clause in the contract, the defendant, under the law, had a right to cancel, and, having such a right, anticipated profits are no part of the just compensation provided for in the law. The acts of March 4, 1917, 39 Stat. 1168-1192, June 15, 1917, 40 Stat. 182, and July 1, 1918, 40 Stat. 704-719 and 720, are relied upon.

The plaintiff suggests the inapplicability of the acts of March 4, 1917, and July 1, 1918, because both refer to “ existing contracts ” and because further the act of March 4, 1917, was limited in its authority to March 1, 1918, and discusses in detail the construction of the act of June 15, 1917, while the defendant, relying on the act of June 15, 1917, maintains that the other acts are properly for consideration because in pari materia and enlightening as to the legislative intent.

The act of June 15, 1917, was an act making appropriations to supply deficiencies in appropriations for the Military and Naval Establishments on account of war expenses. The provisions invoked by the defendant are found under the subhead “ Emergency shipping fund ” wherein, within the limits of the amounts authorized, the President is given certain powers with reference to placing orders for ships or material, requiring owners of plants to place their output at the disposal of the United States, requisitioning plants and ships, etc., among which is the power “(J) To modify, suspend, cancel, or requisition any existing or future contract for the building, production, or purchase of ships or material.”

Provision follows, in case of the exercise of any of these powers by the President, for the making of just compensation to be determined by the President with a right, if the compensation fixed is unsatisfactory, to receive 75 per centum thereof and to sue under section 24, paragraph 20, and section 145 of the Judicial Code for such sum as added to said 75 per centum will make up such amount as will be just compensation, followed by a further provision that—

“ The President may exercise the power and authority hereby vested in him, and expend the money herein and here[40]*40after appropriated through such agency or agencies as he shall determine from time to time,”

with a proviso not here material.

Following are provisions as to what shall be deemed to be included in certain words used in the act, among which it is provided that—

“ The word 1 material ’ shall include stores, supplies, and equipment for ships, and everything required for or in connection with the production thereof,”

and it is then, provided that the authority granted to the President in the act or by him delegated shall cease six months after the final treaty of peace is proclaimed between this Government and the German Empire.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

International Arms & Fuze Co. v. United States
101 Ct. Cl. 297 (Court of Claims, 1944)
Nitro Powder Co. v. United States
71 Ct. Cl. 369 (Court of Claims, 1930)
De Laval Steam Turbine Co. v. United States
70 Ct. Cl. 51 (Court of Claims, 1930)
Gilbert v. United States
60 Ct. Cl. 1005 (Court of Claims, 1925)
Twin City Forge & Foundry Co. v. United States
60 Ct. Cl. 673 (Court of Claims, 1925)
Davis Sewing Machine Co. v. United States
60 Ct. Cl. 201 (Court of Claims, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
57 Ct. Cl. 26, 1922 U.S. Ct. Cl. LEXIS 536, 1922 WL 1839, Counsel Stack Legal Research, https://law.counselstack.com/opinion/meyer-scale-hardware-co-v-united-states-cc-1922.