David v. Town of Webster

24 Mass. L. Rptr. 262
CourtMassachusetts Superior Court
DecidedJune 23, 2008
DocketNo. 060351D
StatusPublished

This text of 24 Mass. L. Rptr. 262 (David v. Town of Webster) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
David v. Town of Webster, 24 Mass. L. Rptr. 262 (Mass. Ct. App. 2008).

Opinion

Lemire, James R., J.

The plaintiff, Patrice David (“David”), brings this action against the defendants, the Town of Webster (“Town”), Thomas W. Brousseau (“Brousseau”), and Melissa Hubert (“Hubert”), alleging that the Town is liable to David for unjust enrichment and quantum meruit, that Brousseau is liable for breach of contract, breach of fiduciary duty, and conflict of interest, and that Hubert is liable for breach of contract, unjust enrichment, and quantum meruit. The defendants each move for summary judgment. For the reasons stated below, the defendants’ motions for summary judgment are ALLOWED.

BACKGROUND

The relevant undisputed material facts as established by the summary judgment record are as follows.2 On December 11, 2003, seller David entered into a Purchase and Sale Agreement with buyer Hubert for real estate located at 9 Juniper Lane, Webster, Massachusetts. January 15, 2004 was set as the closing date. At the time of the sale, the property was not connected to the Town sewer and utilized a private septic system. Between the execution date and the closing date, David was unable to comply with Title V of the State Environmental Code,3 as referenced in paragraph twenty-five of the agreement. David .informed Hubert about the septic system’s failure to pass Title V requirements. Despite this problem, Hubert wished to proceed with the sale. Rather than reducing the price of the property, David and Hubert planned to set aside money from the sale to use toward connecting the property to the Town sewer.

David and Hubert entered into a one-page Escrow Agreement dated January 15, 2004. Hubert’s attorney, Brousseau, had drafted the agreement, but had not forwarded a copy to David prior to David’s visit to his office on the closing date. The recital of the Escrow Agreement stated that David was “unable to provide a Title V Certificate to [Hubert], as required under the Massachusetts Laws, due to non-completion of the septic system, prior to the transfer and the system cannot be corrected prior to the transfer, due to the winter conditions.” The Escrow Agreement provided that

1.The Seller shall, at her expense, tie in to the Town sewer lines in complying with all state and municipal laws and codes. The Seller shall be responsible for all expenses and costs, including all municipal permits, inspections, police road details, all equipment and work, as set forth in the proposal of M&M Excavators Co. Inc., dated December 31, 2003, and shall restore the premises . . . The Seller shall be responsible for any costs necessary for the work if in excess of the estimate of M&M Excavators Co., Inc. Said work shall be completed no later than May 1. 2004.
2. If prior to the completion of the Title V, the Seller agrees to pay for any necessary pumping of the septic system, if needed.
3. The Sum of $38,000.00 shall be held in escrow, by the Buyer’s attorney, Thomas W. Brousseau, pending completion of all necessary work as set forth above. In the event that the costs of said work are in excess of the holdback sum, the Seller shall be responsible for any extra cost. In the event that the costs are less than the holdback sum, the Seller shall be entitled to the balance, immediately upon completion of work.

David accepted the sewer tie-in proposal from M&M Excavators Co., Inc. (“M&M”) referenced in the Escrow Agreement on January 15, 2004. David had consulted the contractor around the end of December 2003. The proposal explicitly required a fifty percent payment at the start of the project and the remainder upon completion.

[263]*263In March 2004, David discovered the possibility of the Town installing the sewer line for all of Juniper Lane, after having approached the Town Administrator Robin Leal (“Leal”). David subsequently met with Leal and Sewer Superintendent Phillip Robert (“Robert”), who informed David that Town had been considering the extension of sewer service to that area. Robert also informed David that the Town would have to approve funding before the project could be undertaken.

Hubert extended the May 1,2004 deadline specified in the Escrow Agreement to allow David to raise the issue of the Town installing the sewer connection to Juniper Lane at the May 10, 2004 Town meeting.4 On May 11, 2004, the day after the Town meeting, David, through Gorski, requested an additional extension to July 1, 2004 because the Town had postponed considering the Article to install the sewer line until June 21, 2004.5 Brousseau responded to Gorski by letter dated May 11, 2004 that Hubert refused to grant a further extension and intended to proceed with the installation of the sewer connection. Brousseau also informed Gorski that he was sending M&M one-half of its estimate, namely $18,400, to begin the sewer work. Brousseau retained the remaining funds in escrow.

By letter dated May 11, 2004, David requested Leal to withhold any sewer permits for the property until the Town decided the pending Article. Leal responded on June 7, 2004 that, with the advice of the Town Counsel, the Town found no basis to withhold issuing any permits for the property. On about June 10, 2004, M&M applied for a sewer connection permit to install a main line to the Town sewer. The Town issued this permit on June 14, 2004.

At the June 21, 2004 Town meeting, the Town passed an amended Article to install a sewer connection for Juniper Lane and an adjoining street.6 Several days later, the Town issued a separate permit to M&M on June 24, 2004 to connect the property to the recently installed main sewer line. In July 2004, Brousseau made the second payment to M&M from the escrow funds.

In October 2004, David’s current attorney requested that the Town reimburse David for the sewer installation. Leal subsequently responded that the Town vote for the project did not include reimbursing “a resident who was sewering due to personal reasons.” Sometime later, David pursued the issue of reimbursement with Leal’s successor, Dana Keenan (“Keenan”).

DISCUSSION

Summary judgment is appropriate when the summary judgment record shows that “there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law." Mass.R.Civ.P. 56(c): DuPont v. Comm'r of Corr., 448 Mass. 389, 397 (2007). A fact is “material” if it would affect the outcome of the suit. Carey v. New England Organ Bank, 446 Mass. 270, 278 (2006); Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). A dispute is “genuine” where a reasonable finder of fact could return a verdict for the non-moving party. Flesr v. Technical Commc’ns Corp., 410 Mass. 805, 809 (1991), citing Anderson, 477 U.S. at 252. The moving party bears the initial burden of demonstrating the absence of a triable issue and that the summary judgment record entitles it to judgment as a matter of law. Ng Bros. Constre., Inc. v. Cranney, 436 Mass. 638, 644 (2002), citing Pederson v. Time, Inc., 404 Mass. 14, 17 (1989); Kourouvacilis v. Gen. Motors Corp., 410 Mass. 706, 716 (1991).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Revere v. Massachusetts General Hospital
463 U.S. 239 (Supreme Court, 1983)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Frontier Enterprises, Inc. v. Anchor Co. of Marblehead
536 N.E.2d 352 (Massachusetts Supreme Judicial Court, 1989)
Pederson v. Time, Inc.
532 N.E.2d 1211 (Massachusetts Supreme Judicial Court, 1989)
J. A. Sullivan Corp. v. Commonwealth
494 N.E.2d 374 (Massachusetts Supreme Judicial Court, 1986)
Dolan v. Hickey
431 N.E.2d 229 (Massachusetts Supreme Judicial Court, 1982)
Massachusetts General Hospital v. City of Revere
434 N.E.2d 185 (Massachusetts Supreme Judicial Court, 1982)
Community National Bank v. Dawes
340 N.E.2d 877 (Massachusetts Supreme Judicial Court, 1976)
Kaarela v. Birkhead
600 N.E.2d 608 (Massachusetts Appeals Court, 1992)
Kourouvacilis v. General Motors Corp.
575 N.E.2d 734 (Massachusetts Supreme Judicial Court, 1991)
Flesner v. Technical Communications Corp.
575 N.E.2d 1107 (Massachusetts Supreme Judicial Court, 1991)
Coveney v. President & Trustees of the College of the Holy Cross
445 N.E.2d 136 (Massachusetts Supreme Judicial Court, 1983)
White v. University of Massachusetts at Boston
574 N.E.2d 356 (Massachusetts Supreme Judicial Court, 1991)
USM Corp. v. Arthur D. Little Systems, Inc.
546 N.E.2d 888 (Massachusetts Appeals Court, 1989)
Adalian Bros. v. City of Boston
84 N.E.2d 35 (Massachusetts Supreme Judicial Court, 1949)
In re the Discipline of Two Attorneys
660 N.E.2d 1093 (Massachusetts Supreme Judicial Court, 1996)
Simplex Technologies, Inc. v. Liberty Mutual Insurance
706 N.E.2d 1135 (Massachusetts Supreme Judicial Court, 1999)
Miller v. Mooney
431 Mass. 57 (Massachusetts Supreme Judicial Court, 2000)
Ng Bros. Construction, Inc. v. Cranney
766 N.E.2d 864 (Massachusetts Supreme Judicial Court, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
24 Mass. L. Rptr. 262, Counsel Stack Legal Research, https://law.counselstack.com/opinion/david-v-town-of-webster-masssuperct-2008.