Danny's Const. Co., Inc. v. Birdair, Inc.

136 F. Supp. 2d 134, 2000 U.S. Dist. LEXIS 20038, 2000 WL 33278160
CourtDistrict Court, W.D. New York
DecidedSeptember 28, 2000
Docket1:00-cr-00064
StatusPublished
Cited by13 cases

This text of 136 F. Supp. 2d 134 (Danny's Const. Co., Inc. v. Birdair, Inc.) is published on Counsel Stack Legal Research, covering District Court, W.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Danny's Const. Co., Inc. v. Birdair, Inc., 136 F. Supp. 2d 134, 2000 U.S. Dist. LEXIS 20038, 2000 WL 33278160 (W.D.N.Y. 2000).

Opinion

INTRODUCTION

CURTIN, District Judge.

On January 19, 2000, plaintiff Danny’s Construction Company, Inc. (“DCCI”) commenced the present action against defendant Birdair, Inc. (“Birdair”) and asked that the court “temporarily and permanently” enjoin the arbitration that Birdair has recently demanded of DCCI. Item 1, p. 9 (Complaint). Immediately after filing its complaint, DCCI filed motions for a preliminary injunction and summary judgment. Item 2. By its motion for a preliminary injunction, DCCI seeks to prevent Birdair from proceeding with its arbitration demand. By its motion for summary judgment, DCCI seeks permanent injunctive relief regarding that same arbitration demand.

At oral argument, the court learned that a date had not yet been set for the arbitration, and that the American Association of Arbitration (“AAA”) intended to await this court’s decision before setting such a date.

On January 31, 2000, Birdair was ordered to file its responses to DCCI’s complaint and motions. Item 6. Accordingly, Birdair filed an answer on February 22, 2000, Item 9, and then filed various opposing papers on March 1, 2000. Items 10-11. DCCI has since had an opportunity to reply. Item 12. On April 14, 2000, oral argument was heard on DCCI’s motions for preliminary and permanent injunctive relief. Having considered the parties’ arguments, DCCI’s motion for a preliminary injunction and its motion for summary judgment are denied.

Facts

I. Overview

The court takes this opportunity to set forth a brief summary of the rather complicated background — both factual and legal — that surrounds the present litigation. Ultimately, this action arises out of defendant Birdair’s contract to rebuild the roof of the Montreal Olympic Stadium (“the Stadium”). For the purposes of this litigation, there are several players involved: (1) Regies de Installations Olympiques (“RIO”) (a non-party): the public agency in Canada that maintains the Montreal Olympic Stadium; (2) Birdair (the defendant here): RIO’s prime contractor on a project involving reconstruction of the Olympic Stadium’s roof; (3) DCCI (the plaintiff here): one of Birdair’s principal subcontractors on the Project, put in charge of demolishing the old roof and erecting the new one (“the Project”); 1 (4) American Metal Works (“AMW”) (a non-party): another one of Birdair’s subcontractors on the Project, made responsible for building and delivering steel trusses to the Project’s work site; (5) Montacier, Inc. (a non-party): Birdair’s sub-subcontractor and DCCI’s subcontractor, made responsible for meeting DCCI’s labor needs on the Project.

For reasons that are discussed in greater detail infra, work on the Project was delayed several times over the course of many months. DCCI and Birdair disagreed about which party was responsible for these delays. Ultimately, DCCI and Birdair had a falling-out, and Birdair dismissed DCCI as a subcontractor.

II. The Subcontract & the Project

More specifically, RIO hired Birdair to design and reconstruct the Stadium’s roof *138 in June 1997. See Item 3, Exh, C, Att. 5. As prime contractor, Birdair subcontracted with plaintiff DCCI in August of 1997 for the demolition and reconstruction of the Stadium’s roof. See Item 3, ¶ 8. The present litigation arises out of Birdair and DCCI’s subcontract (“the subcontract”). The subcontract required DCCI to “furnish all engineering, supervision, labor, equipment, small tools and temporary rigging to demolish and dispose of the existing roof and install” the various components that were needed to create the new roof. Item 3, Exh. B, fA. The subcontract also required Birdair to provide DCCI with all of the components — the “steel, cables, fabric and fabric accessories”- — that would be needed to build the new roof. Id.

Being based in Minnesota, DCCI found it necessary to sub-subcontract its labor needs to Montacier, Inc. (“Montacier”), which is a construction firm based in Montreal. Item 3, ¶ 9. Under the terms of this sub-subcontract, Montacier promised to provide DCCI with the labor needed to complete the Project. Item 3, Exh. C, Att. 7, p. 1.

. As prime contractor, Birdair developed the design for the new roof. See Item 3, ¶¶ 10-14. This design required DCCI to construct a net of interwoven steel cables, and to attach specialized fabric to those steel cables. See Item 3, Exh. C, Att. 8 (diagram of design).

In February of 1998, DCCI and Birdair reached an agreement regarding the necessary schedule for demolishing and rebuilding the Stadium’s roof. See Item 3, ¶ 25 and Exh. C, Atts. 12, 17. As a result of certain scheduling difficulties, see id. and Item 3, ¶¶ 17-21, DCCI later notified Birdair of its intent to assert claims for the costs associated with the delays and the accelerated schedule that -the delays necessitated. See id. ¶ 22 and Exh. C, Att. 14.

In addition to these apparent scheduling problems, DCCI contends that Birdair repeatedly failed to deliver the new roofs components in a timely manner. See Item 3, ¶¶ 26-27, 29 and Exh. C, Atts. 19-20. Specifically, DCCI claims that Birdair delinquently delivered the steel trusses which were to be erected around the perimeter of the stadium as support for the roof. See id. ¶ 26-27; Item 3, Exh. C, Att. 20 (detailing dates when trusses were scheduled to arrive and when they were actually received).

Birdair had entrusted American Metal Works, Inc. (“AMW”) with the job of building these steel trusses (“the AMW-made steel trusses”). See Item 3, Exh. A, pp. 4-5.

III. Birdair Declares DCCI in Default

By September of 1998, it was clear that the Project was well behind schedule. Ultimately, DCCI indicated that it would not press forward with its work unless Birdair agreed to finance the costs associated with an accelerated work schedule. See Item 3, ¶ 32. Birdair initially agreed to cover these costs. See Item 3, Exh. J, ¶¶ 11-12. However, this agreement soon fell apart. On October 30, 1998, DCCI sent Birdair a letter by facsimile in which DCCI accused Birdair of managing the prime contract incompetently and of committing several material breaches of the subcontract. See id. Exh. C, Att. 10. DCCI insisted that Birdair’s failure to uphold its end of the subcontract had caused injurious delays to DCCI. See id.

This falling-out between DCCI and Bir-dair gave rise to three separate lawsuits, which were commenced in the civil courts of Quebec. DCCI commenced the first Quebec-based action (“Action No. 1”) in early December 1998. See Item 3, ¶ 40 and Exh. C. In Action No. 1, DCCI has *139 sued Birdair over damages allegedly incurred by DCCI because of Birdair’s failure to deliver the roofs components to the work site on time and because of Birdair’s inability to coordinate work on the Project “so as not to disrupt” DCCI’s operations.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fasano v. Li
S.D. New York, 2023
Davis v. Shiekh Shoes, LLC
California Court of Appeal, 2022
Naylor Family Partnership v. Home S. & L. Co. of Youngstown
2014 Ohio 2704 (Ohio Court of Appeals, 2014)
Allstate Insurance v. Elzanaty
929 F. Supp. 2d 199 (E.D. New York, 2013)
Thi of New Mexico at Vida Encantada, LLC v. Lovato
848 F. Supp. 2d 1309 (D. New Mexico, 2012)
Lemus v. CMH Homes, Inc.
798 F. Supp. 2d 853 (S.D. Texas, 2011)
Aviation Data, Inc. v. American Express Travel Related Services Co.
62 Cal. Rptr. 3d 396 (California Court of Appeal, 2007)
Baker v. Stevens
2005 UT 32 (Utah Supreme Court, 2005)
Cason v. Conoco Pipeline Co.
280 F. Supp. 2d 1309 (N.D. Oklahoma, 2003)
Baker v. Conoco Pipeline Co.
280 F. Supp. 2d 1285 (N.D. Oklahoma, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
136 F. Supp. 2d 134, 2000 U.S. Dist. LEXIS 20038, 2000 WL 33278160, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dannys-const-co-inc-v-birdair-inc-nywd-2000.