Dale v. HB Smith Co., Inc.

910 F. Supp. 14, 1995 U.S. Dist. LEXIS 20422, 1995 WL 783040
CourtDistrict Court, D. Massachusetts
DecidedDecember 6, 1995
DocketCiv. A. 92-30073-KPN; Docket 71 and 78
StatusPublished
Cited by11 cases

This text of 910 F. Supp. 14 (Dale v. HB Smith Co., Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dale v. HB Smith Co., Inc., 910 F. Supp. 14, 1995 U.S. Dist. LEXIS 20422, 1995 WL 783040 (D. Mass. 1995).

Opinion

MEMORANDUM ON MOTIONS FOR SUMMARY JUDGMENT BROUGHT BY DEFENDANTS H.B. SMITH COMPANY, INC. AND MESTEK, INC.

NEIMAN, United States Magistrate Judge.

I. INTRODUCTION

This action involves an alleged breach of a commercial lease. Plaintiff Martin A. Dale owns a building located on Owen District Road in Westfield, Massachusetts. The site was last occupied by one of the defendants, H.B. Smith Company, Inc. (“Smith”). Pursuant to F.R.Civ.P. 56, Smith and co-defendant Mestek, Inc. (“Mestek”) have moved for *15 summary judgment on Counts IV and V of Plaintiff’s First Amended Complaint, respectively. For the reasons set forth below, the Court allows the motion for summary judgment brought by Mestek, but denies the motion for summary judgment brought by Smith.

II. FACTUAL AND PROCEDURAL BACKGROUND 1

A FACTUAL BACKGROUND

In 1958, Plaintiff’s predecessor in title of the Owen District Road property entered into a lease with International Harvester Company. In 1969, International Harvester and Defendant PCP Realty Trust (“PCP”) entered into a written sublease, which gave PCP the option to renew the sublease for four successive five-year terms following the original five-year lease. Under those terms, PCP had sublease rights through early 1994.

In 1980, Plaintiff purchased the property for $140,000, subject to the International Harvester lease and the PCP sublease. He then commenced an action against International Harvester. As a part of the agreement settling the lawsuit, International Harvester withdrew from the lease arrangement and transferred all of its leasehold rights to the Plaintiff. The settlement was effective December 31, 1983. Plaintiff thereafter received approximately $1,500 per month from PCP in connection with the sublease.

Sometime in 1987, PCP entered into a seven year sub-sublease with Smith. The initial term of the sub-sublease was for approximately seven years, terminating in April of 1994. Due apparently to more favorable market conditions, the monthly rental payment to PCP from Smith was approximately $9,500. See Plaintiffs Opposition to Defendant H.B. Smith Company Inc.’s Motion for Summary Judgment (Docket No. 76), at 1.

In 1987 or 1988, Plaintiff visited the Owen District Road property and observed representatives of Smith — which used the facility as the primary assembly point for its residential boiler lines — occupying the premises and doing repairs and work to the building. Plaintiff spoke to Smith representatives and toured his property with them. He then drove to Smith’s main office where he met with Edwin E. Smith, its President and Chairman, and introduced himself as the owner of the property.

In September of 1989, Plaintiff filed a summary action in Westfield District Court against Smith, PCP and Defendant Theodore Peer (“Peer”), a trustee of PCP, alleging failure to comply with the provisions of the lease governing renewal. The case was heard by District Court Judge Philip A. Contant on November 3, 1989, who, on June 12, 1990, ruled in favor of Plaintiff. Judge Contant found that, due to PCP’s failure to comply with its renewal terms, the lease between PCP and Plaintiff expired on May 31, 1989 and PCP thereafter became a tenant-at-will. Plaintiffs First Amended Complaint (Docket No. 59), Exhibit C.

Smith, PCP and Peer appealed the District Court’s decision to the Hampden County Superior Court. On July 24, 1990, Judge Contant ordered, as a condition of the appeal bond, that PCP continue to make the $1,500 monthly payments to Plaintiff as required under the sublease. Judge Contant further ordered that all rental payments by Smith to PCP, approximately $8,000 per month, be placed in escrow pending resolution of the action. That portion of the order was subsequently affirmed in September of 1990 by Judge Raymond R. Cross of the Hampden County Superior Court. See Plaintiffs First Amended Complaint, Exhibits D and E. In January of 1992, the judgment of the West-field District Court in favor of Plaintiff was entered and he was able to regain possession *16 of the premises. Id., at 5. 2

Upon receiving notice of the 1989 summary process action, Smith began to execute the relocation of its boiler assembly operations at Plaintiffs property to its principal plant at 57 Main Street in Westfield. Mestek claims that Smith “moved quickly to relocate that line to ensure continued operations” and that Smith accomplished its relocation by early 1990. Although Plaintiff disputes Mestek’s “subjective assertions,” he agrees that, in March of 1990, Smith informed PCP that it was leaving the property.

Mestek claims that Smith notified PCP, in a letter dated January 9, 1991, that its right to quiet enjoyment had been breached and that Peer, as a trustee for PCP, had been provided with a key to the premises. See Mestek’s L.R. 56.1 Statement, Exhibit 8. Plaintiff claims that he never received a copy of the January 9,1991 letter. Instead, Plaintiff states that he was advised of the vacancy of the building in April of 1991.

On or about March 5, 1990, HBS Acquisition Corp. — a Delaware corporation wholly owned by Defendant Mestek — purchased 48.6% of the outstanding common stock of Smith. The acquisition was made by way of a tender offer to Smith’s shareholders. In connection with the tender offer, HBS Acquisition learned, through an audited financial statement, of a significant volume of asbestos-related suits in which Smith was named as defendant. No listing was contained in the audited financial statement which disclosed the existence of the 1989 summary process action.

A central figure in the 1990 tender offer was John E. Reed (“Reed”). In addition to being the President, CEO and Chairman of the Board of Mestek, Reed was Smith’s longest serving board member, having served on Smith’s board since 1950. Reed was also Smith’s Clerk until about 1960, the controlling shareholder in Mestek at the time of the tender offer and is currently the President of HBS Acquisition. According to Plaintiff, the shares owned by HBS Acquisition, when added to those owned or controlled by Reed, constitute a majority of Smith’s outstanding shares. 3

At the time of the tender offer, the 1989 summary process action was under consideration by Judge Contant. Edwin E. Smith testified that, in his discussions with Reed, Mestek and HBS Acquisition preceding the tender offer, he was aware of, but never mentioned, the summary process, action. Similarly, Reed testified that, despite his position on Smith’s Board of Directors and his presence at a July 24,1989 board meeting at which a possible move from the property was discussed, he has no memory of discussing with Edwin Smith the status of the then pending summary process action. Reed, however, was aware that a controversy existed involving the sublease of the property, and did recall discussions, but not details, regarding whether or not rental monies or rent being paid by Smith should be paid to an entity other than PCP. Reed also claims that he was not aware whether or not Mestek’s auditors were informed of Plaintiffs lawsuit at the time the audited financial statements were prepared.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
910 F. Supp. 14, 1995 U.S. Dist. LEXIS 20422, 1995 WL 783040, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dale-v-hb-smith-co-inc-mad-1995.