Dakota Constructors, Inc. v. Hanson County Board of Adjustment

994 N.W.2d 222, 2023 S.D. 38
South Dakota Supreme Court·Decided July 26, 2023·No. 30084·Published·Cited by 4 cases

Opinion

#30084-a-SRJ 2023 S.D. 38

IN THE SUPREME COURT

OF THE

STATE OF SOUTH DAKOTA

****

DAKOTA CONSTRUCTORS, INC., Petitioner and Appellant, v.

HANSON COUNTY BOARD OF ADJUSTMENT, Respondent and Appellee.

****

APPEAL FROM THE CIRCUIT COURT OF THE FIRST JUDICIAL CIRCUIT HANSON COUNTY, SOUTH DAKOTA

****

THE HONORABLE CHRIS S. GILES Judge

****

PAUL H. LINDE of Schaffer Law Office, Prof. LLC Sioux Falls, South Dakota Attorneys for petitioner and appellant.

JACK H. HIEB ZACHARY W. PETERSON of Richardson, Wyly, Wise Sauck & Hieb, LLP Aberdeen, South Dakota Attorneys for respondent and appellee.

****

ARGUED

APRIL 27, 2023

OPINION FILED 07/26/23

JENSEN, Chief Justice [¶1.] In 2021, Dakota Constructors, Inc. (Dakota Constructors) purchased a quarry located in Hanson County that had operated since 1986 under a state license to mine sand, gravel, and rock. The Hanson County Zoning Ordinance (Ordinance) took effect in April 2000. After the purchase, the Hanson County Zoning Administrator advised Dakota Constructors that because the quarry is located in a district that is currently zoned as agricultural, it would need a conditional use permit (CUP) under the Ordinance in order to extract sand, gravel, and rock from the site. Dakota Constructors submitted a CUP application but argued before the Hanson County Board of Adjustment (Board) that it did not need a CUP because the operation of the quarry was a continuing prior nonconforming use. The Board disagreed and determined that Dakota Constructors did need a CUP because the nonconforming use contemplated—the extraction of materials from the site—had ceased for more than one year. The Board granted the CUP application with specified conditions. Dakota Constructors petitioned for a writ of certiorari. Following a hearing, the circuit court denied the writ. Dakota Constructors appeals. We affirm.

Background

[¶2.] Fisher Sand & Gravel Co. (Fisher) initially operated a quarry at the property. 1 From and after 1986, Fisher annually renewed its mining license with

1. Except for 2004 and 2005 when the quarry was operated by Spencer Quarries, Fisher continuously leased the property from the Metz family.

Over the years, Fisher and the Metz family were in discussions on reclamation plans for the property, and the Metz family commenced a federal (continued . . .)

the South Dakota Department of Environmental and Natural Resources (now the Department of Agriculture and Natural Resources) Mineral and Mining Program, pursuant to SDCL chapter 45-6. The renewal process included filing annual reports and giving public notices of its intent to continue the operation at the site. Fisher filed an annual mine report with the Department on January 25, 2021, along with notice of intent to continue the quarry operation through 2031. After Dakota Constructors purchased the operation, the Department approved the transfer of reclamation liabilities from Fisher to Dakota Constructors for the Hanson County site. [¶3.] At the direction of the County Zoning Administrator, Dakota Constructors submitted a CUP application to Hanson County on November 15, 2021. A Board hearing on the application was initially set for December 22, 2021, but was deferred to January 26, 2022. During this time, the Board received a report from an engineering firm providing recommendations for stabilizing a portion of the quarry that was impacting the integrity of a nearby County road. The report discussed needed repairs in an area where a fence had been constructed ten feet from the highwall of the quarry and twenty feet from the guardrail. A slump undermining the fence had come within fifteen feet of the guardrail, and the ground was eroded up to the fence in four other locations. The estimated cost of the repairs was $620,500.

(. . . continued)

lawsuit involving the reclamation issues. Fisher eventually purchased the property from the Metz family before the sale to Dakota Constructors.

[¶4.] At the hearing, Dakota Constructors argued to the Board that a CUP was not required because the operation of the quarry was a continuing prior nonconforming use. The Board received voluminous documents and statements concerning the operation at the quarry dating back to 1986. These submissions showed the quarry operated as a state-licensed mining operation since 1986 and that aggregate in the form of sand, gravel, and rock had been continuously removed from the quarry since that time. Dakota Constructors presented an affidavit from Clinton Degen, former Hanson County Highway Superintendent, who stated that he hauled material from the property each year except for 2004 and 2005 when Spencer Quarries was operating and hauling aggregate from the site. [¶5.] However, the submissions also showed that since 2004 the sand, gravel, and rock removed from the quarry had come from stockpiles stored at the site that had been extracted from the ground prior to 2004. In particular, the annual mine reports required by SDCL 45-6-72 showed that zero tons of aggregate were mined from the quarry from 2004–2021. Michael G. Erickson, a scientist from the Department, explained in a February 2022 email exchange with the Zoning Administrator that “[m]ining is not defined in statute under [SDCL chapter 45-6 (addressing sand, gravel and construction aggregate mining)]. We have always gone with the extraction of sand, gravel, or rock from the ground as mining. Thus the removal of stockpiled material is not considered mining.” 2

2. Erickson had indicated in a 2003 correspondence, included in the file, that tonnage calculations are based on when materials are “mined (extracted)

from the ground.” The correspondence explained that hauling material from stockpiles on the site would not figure into the tonnage calculation because (continued . . .)

[¶6.] The Board held hearings on three dates to consider the CUP application. On February 23, the Board made findings determining that the previous operation of the quarry had ceased for more than one year and was thus not a prior nonconforming use that could continue without a CUP. After determining a CUP was necessary for Dakota Constructors to operate the quarry, the Board approved the CUP and established conditions for use of the quarry, including repair of the erosion near the road, before commencing blasting. The Board’s findings included:

1. [Dakota Constructors] presented a legal statement to the Board. Statement is on file with the Hanson County Zoning Office.

2. The requested conditional use is permitted under Article 5, Section 507 of Hanson County Zoning Ordinance.

3. The request does require a Conditional Use permit. The current owner will be expanding to occupy a greater area of land. Article 3, Section 1305, Hanson County Zoning Ordinance. 3

4. The previous operation has ceased for more than one year according to all records filed with the State of South Dakota. Article 3, Section 1305, Hanson County Zoning Ordinance.

[¶7.] Dakota Constructors filed a petition for writ of certiorari with the circuit court. The court held a hearing on the petition and issued a memorandum decision and a corresponding order denying the writ. The court concluded that the

(. . . continued)

that same material already would have been accounted for at the time it was mined.

3. In the Board’s brief, it concedes it had “essentially abandoned its position on expansion in its [arguments to the circuit court], acknowledging that the record did not address expansion of the operations. Consequently, the Board’s argument in this appeal is limited to the cessation of the nonconforming use for more than one year.”

Free access — add to your briefcase to read the full text and ask questions with AI

Dakota Constructors, Inc. v. Hanson County Board of Adjustment, 994 N.W.2d 222, 2023 S.D. 38 (S.D. 2023).

994 N.W.2d 222 (Dakota Constructors, Inc. v. Hanson County Board of Adjustment) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

State v. Albaidhani
2026 S.D. 24 (South Dakota Supreme Court, 2026)
Gonzales v. Markland
2025 S.D. 14 (South Dakota Supreme Court, 2025)
STROM TRUST v. SCS CARBON TRANSPORT, LLC
2024 S.D. 48 (South Dakota Supreme Court, 2024)
Burkard v. Burkard
2024 S.D. 38 (South Dakota Supreme Court, 2024)
Stockwell v. McCook County Board of Commissioners
2024 S.D. 2 (South Dakota Supreme Court, 2024)