Dabbs v. FOUR TEES, INC.

36 So. 3d 542, 2008 Ala. Civ. App. LEXIS 710, 2008 WL 4822975
CourtCourt of Civil Appeals of Alabama
DecidedNovember 7, 2008
Docket2070630 and 2070631 and 2070632
StatusPublished
Cited by7 cases

This text of 36 So. 3d 542 (Dabbs v. FOUR TEES, INC.) is published on Counsel Stack Legal Research, covering Court of Civil Appeals of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dabbs v. FOUR TEES, INC., 36 So. 3d 542, 2008 Ala. Civ. App. LEXIS 710, 2008 WL 4822975 (Ala. Ct. App. 2008).

Opinion

MOORE, Judge.

Clifton Dabbs, his wife, Joan Dabbs, and their son, Shane Dabbs (sometimes hereinafter referred to collectively as “the Dabbses”) contracted with Terry Graves to construct a building on their property for use as a costume store. The parties later experienced disagreements regarding the construction of the building, which resulted in the filing of a number of claims by the Dabbses, Graves, and certain other third parties. The Dabbses appeal from the Lauderdale Circuit Court’s judgment denying the Dabbses their requested relief. 1

Facts

The Dabbses owned a building in Laud-erdale County in which they operated a costume store. In 2004, the Dabbses decided that they wanted to expand their business. Shane had plans drawn up for the project; his design for the building resembled a castle and included a store and an upper-level apartment. A friend of the Dabbses recommended Graves for the project, and Joan met with Graves to dis *546 cuss the plans therefor. According to Joan, Graves’s estimate to complete the project according to the plans was too costly and they agreed not to build the apartment.

There was no written contract between Graves and the Dabbses for the construction of the building. It is undisputed that only Graves and Joan were present for the discussion of the terms of their agreement. Joan testified that Graves had told her that he was licensed and bonded as a contractor; however, he did not show her a license and he did not inform her that his license was limited to the City of Florence. Graves stated that he had told Joan that he was licensed only with the city. According to Graves, he had never possessed a county or state contracting license. The Dabbses’ project was not located within the City of Florence.

Graves was to remove the roof from the existing building on the property and expand the building to include a second floor. Graves testified that he was responsible only for constructing the outside of the building and was not responsible for any construction on the inside. Joan testified, however, that Graves was responsible for certain elements to be constructed on the inside of the building, including doors, stairs, and posts. Graves testified that they had agreed that Graves was to be paid $12 per square foot to complete the project. Joan stated that she had not agreed to pay Graves $12 per square foot but that, instead, Graves had told her that they would save a lot of money if they paid him by the hour; Joan testified that she and Graves had never agreed on an hourly rate. Both Graves and Joan testified that the Dabbses had agreed to pay for the materials for the project.

On May 19, 2004, Joan wrote a check to Graves in the amount of $1,550. According to Joan, that amount was for Graves to get started on the project and was to be applied to Graves’s labor costs. Graves testified that that money was payment for him to tear down the preexisting building on the site. 2 Also on May 19, 2004, Joan wrote a check to United True Value (“United”), a materials supplier, in the amount of $15,000 for materials for the project. 3 According to Joan, she had given that check to Graves for the purpose of starting an account in her name at United, and she had assumed that Graves had set up an account in her name. Graves testified that he had had an account with United long before he began the Dabbses’ project and that he had had a small balance on that account before he began the Dabbses’ project. According to Graves, all the materials from United that were for the Dabbses’ project were billed to Graves under his account number and he did not open a separate account for the Dabbses’ project. Graves stated that he had asked Joan for the $15,000 check for United so that he could order materials to get started on the project and that he had delivered that check to United for the Dabbses. Jim Terry, purportedly an owner of United, testified that he had first received an order for the Dabbses’ project around May 20, *547 2004. At that time, according to Terry, Graves’s account with United had a balance owing of $16,184.21, which was unrelated to the Dabbses’ project, and the $15,000 check from the Dabbses had been applied to that balance.

Graves began working on the Dabbses’ project in the first week of June 2004. Joan wrote a check for $1,733.10 to Blue Star Ready Mix USA, L.L.C., for concrete on June 4, 2004; Joan testified that Graves had begun the project approximately one day before that. 4 Graves hired Tommy Whitten, a carpenter, to work with him on the project. According to Whitten, he, Graves, and another worker, Scott, had worked on the Dabbses’ project. Graves testified that his nephew and his daughter had worked on the project on and off, and there was testimony indicating that there was another employee who had worked on the project periodically. Graves testified that he had paid each of his workers in cash and that he had expended approximately $12,000 to $14,000 in paying his workers.

United delivered the majority of the materials for the project directly to the job site. Graves testified that he recalled having a discussion with Joan in which he had told her that her balance with United was $26,605.23, that she needed to pay that sum so that he could order more lumber from United, and that, on June 23, 2004, she had given him a check, made out to United, in the amount of $26,605.23, which he had then delivered to United. Joan testified that she thought that, at that time, all the materials for the project had been paid for. Also on June 23, 2004, Joan wrote a check to Graves in the amount of $8,000. According to Joan, Graves had told her that he needed that amount for his labor and to pay his workers; Graves stated that he had not asked Joan for any more money for his labor since that time.

At some point before Graves stopped working on the Dabbses’ project, Whitten quit working for Graves. According to Whitten, he had learned that the Dabbses, rather than Graves, were paying for the materials; he had seen Graves removing materials that had been delivered to the Dabbses’ site, and he did not want to be a part of anything illegal. Specifically, Whitten testified that he had seen Graves remove “Hardie” plank, or concrete board, plywood, and chip board from the Dabbs-es’ site. Joan and Shane testified that, on one occasion, 50 pieces of Hardie plank that had been delivered in the morning were no longer at the site later that evening. Whitten stated that he knew of two other jobs from which Graves was taking materials. Graves testified, however, that he had not removed any materials from the Dabbses’ site and that the other jobs that he was working on at that time required different materials than he was using on the Dabbses’ project.

According to Joan, she and Graves had had an argument sometime in July during which she had expressed her concerns that Graves was not going to complete the project by the July 31 deadline that they had discussed. Graves left the job at the end of July. Joan testified that Graves had not completed the project at that time. According to Joan, Graves returned to the project two or three different times in August, but he did not perform any work on those occasions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Buckentin v. Suntrust Mortgage Corp.
928 F. Supp. 2d 1273 (N.D. Alabama, 2013)
Downing v. Halcyon Oaks Homeowners Ass'n
96 So. 3d 818 (Court of Civil Appeals of Alabama, 2012)
T.H. v. Jefferson County Department of Human Resources
70 So. 3d 1236 (Court of Civil Appeals of Alabama, 2010)
King v. Riedl
58 So. 3d 190 (Court of Civil Appeals of Alabama, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
36 So. 3d 542, 2008 Ala. Civ. App. LEXIS 710, 2008 WL 4822975, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dabbs-v-four-tees-inc-alacivapp-2008.