D & S Coal Co., Inc. v. USX Corp.

678 F. Supp. 1318, 100 Oil & Gas Rep. 583, 1988 U.S. Dist. LEXIS 926, 1988 WL 7539
CourtDistrict Court, E.D. Tennessee
DecidedFebruary 5, 1988
DocketCiv. 1-85-791
StatusPublished
Cited by12 cases

This text of 678 F. Supp. 1318 (D & S Coal Co., Inc. v. USX Corp.) is published on Counsel Stack Legal Research, covering District Court, E.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D & S Coal Co., Inc. v. USX Corp., 678 F. Supp. 1318, 100 Oil & Gas Rep. 583, 1988 U.S. Dist. LEXIS 926, 1988 WL 7539 (E.D. Tenn. 1988).

Opinion

MEMORANDUM

EDGAR, District Judge.

Plaintiff D & S Coal Company, Inc. (“D & S”) contended at the trial of this case that on March 14,1985, it negotiated a coal lease with defendant USX Corporation (at that time called U.S. Steel Corporation and herein referred to as “U.S. Steel”). Present at this March 14,1985 meeting, the plaintiff contends, was Melissa Marvin, representing D & S, and Buck Layne, Jr., 1 who *1319 was to contract with D & S 2 to do the mining work. Representing U.S. Steel were Messrs. Gary Sides and Dan Clark, both employees of U.S. Steel. There actually was a meeting to discuss a coal lease, However, for the reasons specified below, the Court concludes that such meeting did not occur until March 27, 1985.

Plaintiff contended that the parties orally finalized a lease on the date of the meeting (plaintiff said March 14th) and “shook” on it. Plaintiff contended that the only thing remaining to do in order to consummate the deal was to receive the full written lease from U.S. Steel and execute it. U.S. Steel denied that any lease was finalized, saying that Mr. Sides, its primary representative at the meeting, had no authority to enter into such a lease and had explained this to Ms. Marvin and to Layne. U.S. Steel, through its witnesses, says that it was in no position to enter into a coal lease with D & S because at the time no one knew, including Marvin and Layne, how much coal was on the property to be leased, and therefore there was no way that the parties could arrive at an agreement on royalties, an essential term to any mining lease. Moreover, U.S. Steel says that it had no evidence of insurance coverage from D & S and no information on the financial condition of D & S. Therefore, says U.S. Steel, it is evident that there could have been no agreement on a lease on March 27th. U.S. Steel did issue a prospecting permit to Mr. Layne dated March 25th, but not actually received by D & S until after the 27th, and on April 5, 1985, D & S filed a notice of intent to explore with the Office of Surface Mining, U.S. Department of the Interior. The plaintiff, through Mr. Layne, did some road improvement work on Jones Point Road, which led from a paved road down towards the area that plaintiff wanted to mine. The Jones Point Road was, and is, a road used by area residents and others — and was, and is, passable with four-wheel drive vehicles. At a point shortly after this road leads downward over the escarpment of the Cumberland Plateau, it crosses an area that was surfaced mined in the 1950s and continues on to a location where Mr. Layne has a hunting cabin, and further down into the Sequatchie Valley. Mr. Layne planned to mine at a location some distance from where Jones Point Road crosses the old surface mine. To reach the proposed mining location, one would be required to follow the spoil banks from the previous mining operations laterally around the edge of the escarpment away from the Jones Point Road. Layne constructed a road through these spoil banks to access the area where he was prospecting for D & S’s planned mine.

At the March 14th/27th meeting, Layne contends that he had U.S. Steel’s agreement that he could close any road in connection with his mining operation on behalf of D & S so long as the road was on U.S. Steel’s property. Mr. Sides, on the other hand, says that he told Layne that he could block roads on U.S. Steel property only so long as they were not “public” roads. Layne put a gate on the Jones Point Road over a mile from the proposed mine site and gave keys to some of his friends. He also blocked off another road, the “Rankins Lease Road,” leading into the general area by felling upwards of 100 trees across it and bulldozing dirt piles. The result was that a good many of the local inhabitants became exceedingly irate, and there were “rumors” that U.S. Steel might suffer some forest fires on its land if the roads were not unblocked. Mr. Sides of U.S. Steel told Layne to unblock the roads— which Layne did.

There is a dispute about whether Sides told Layne that he could build a gate, and thereby protect his mine site, where the new road that Layne had built to the proposed mine leaves Jones Point Road. In any event, Layne never constructed a gate at this latter location. Instead, he told U.S. Steel that if he could not block the roads as he had done, then he did not want to mine —and that he would file suit against U.S. *1320 Steel for the expenses that he had incurred in fixing up the road. Hence this lawsuit.

At various times in this case, plaintiff has traveled on differing theories. This Court sustained a statute of frauds defense to plaintiffs claim under the alleged lease. The case eventually came to trial on a theory of promissory estoppel as outlined by section 139 of the Restatement (Second) of Contracts. No Tennessee court of record has explicitly recognized section 139 of the Restatement as a means of alleviating a situation where allowing the statute of frauds defense might perpetuate a fraud. However, this Court determined that there was some authority for this viewpoint. See Price v. Tennessee Products & Chemical Corp., 53 Tenn.App. 624, 385 S.W.2d 301 (1964). 3 There is at least one Tennessee Court of Appeals case that recognizes promissory estoppel in a non-statute of frauds context to circumvent the defense of lack of consideration. Foster & Creighton Co. v. Wilson Contracting Co., Inc., 579 S.W.2d 422 (Tenn.App.1978), cert. denied, March 19, 1979. See Owen of Georgia, Inc. v. Shelby County, 648 F.2d 1084, 1095 (6th Cir.1981). However, the Tennessee Supreme Court has declined to address whether Tennessee recognizes promissory estoppel to allow enforcement of promises unsupported by consideration as embodied in Restatement of Contracts § 90. Alden v. Presley, 637 S.W.2d 862, 864 (Tenn.1982). 4

In any event, this case was submitted to the jury on a promissory estoppel theory. Section 139(1) of the Restatement (Second) of Contracts provides as follows:

A promise which the promisor should reasonably expect to induce action or forbearance on the part of the promisee or a third person and which does induce the action or forbearance is enforceable notwithstanding the statute of frauds if injustice can be avoided only by enforcement of the promise. The remedy granted for breach is to be limited as justice requires.

After a trial before a six-person jury, the Court propounded the following interrogatories to the jury:

QUESTION NO. 1:
Did defendant U.S.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Olympic Holding Co., L.L.C. v. ACE Ltd.
2009 Ohio 2057 (Ohio Supreme Court, 2009)
Chavez v. Broadway Electric Service Corp.
245 S.W.3d 398 (Court of Appeals of Tennessee, 2007)
Chrysler Corp. v. Chaplake Holdings, Ltd.
822 A.2d 1024 (Supreme Court of Delaware, 2003)
Shedd v. Gaylord Entertainment Co.
118 S.W.3d 695 (Court of Appeals of Tennessee, 2003)
Steelman v. Ford Motor Credit Co.
911 S.W.2d 720 (Court of Appeals of Tennessee, 1995)
Josephs v. Pizza Hut of America, Inc.
733 F. Supp. 222 (W.D. Pennsylvania, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
678 F. Supp. 1318, 100 Oil & Gas Rep. 583, 1988 U.S. Dist. LEXIS 926, 1988 WL 7539, Counsel Stack Legal Research, https://law.counselstack.com/opinion/d-s-coal-co-inc-v-usx-corp-tned-1988.