CSX Transp., Inc. v. City of Sebree

924 F.3d 276
CourtCourt of Appeals for the Sixth Circuit
DecidedMay 14, 2019
Docket18-5647
StatusPublished
Cited by22 cases

This text of 924 F.3d 276 (CSX Transp., Inc. v. City of Sebree) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CSX Transp., Inc. v. City of Sebree, 924 F.3d 276 (6th Cir. 2019).

Opinion

COLE, Chief Judge.

In 1966, the City of Sebree, Kentucky (the "City") enacted an ordinance requiring CSX Transportation, Inc.'s ("CSX") predecessor to obtain approval from city council before commencing any maintenance or construction project that would result in any change in grade at any of the six railroad crossings in Sebree. After a dispute surrounding the ordinance in 1979, the predecessor railroad company and the City entered into a settlement agreement whereby the rail company agreed not to raise the height of one crossing by more than 0.4 feet and not to raise the height of another crossing at all. In 2017, CSX notified the City of its intent to perform maintenance that would result in raising four of the crossings, which led to the current lawsuit. CSX sought, and the district court granted, a permanent injunction prohibiting the City from enforcing the ordinance or settlement agreement. Because we agree with the district court that both the ordinance and settlement agreement are preempted by federal railroad statutes, we affirm.

I. BACKGROUND

An active railroad line runs through Sebree, a 1.6 square mile city in Webster County, Kentucky. The rail line, operated by CSX, crosses six streets in Sebree: Jefferson, Webster, Main, Dixon, Mill, and Sebree Springs. Each of the crossings is a "peaked" or "humped" crossing, meaning that there is a change in grade from the street to the top of the rails with the railway tracks sitting higher than the road. The height of the crossings has long been a source of concern for the City. According to the City, the elevation of the crossings creates two primary safety concerns: (1) line of sight obstructions for vehicles and pedestrians crossing the tracks, and (2) a risk that low-profile vehicles and vehicles with long wheel bases, such as trucks and buses, will become stuck or disabled. Understandably, the City does not want the height of the crossings to be raised any further.

*281 On May 11, 1966, the City enacted an Ordinance (the "Ordinance") requiring Louisville and Nashville Railroad ("L&N")-CSX's predecessor in interest-to obtain prior approval from the city council before commencing maintenance or construction that would result in any change in grade at any of the crossings in Sebree. The Ordinance imposes a fine of not less than $50.00 per day until the change is corrected.

Despite the Ordinance, L&N raised the crossings at Jefferson and Webster in 1978 without seeking prior approval from the City. The City informed L&N of its intent to enforce the Ordinance if L&N attempted to raise the crossings at Main and Dixon. L&N thereafter filed a lawsuit in the Webster County Circuit Court seeking to invalidate the Ordinance and requesting an injunction preventing the City from enforcing it. The circuit court issued an order in July of 1979, denying L&N's request for an injunction and temporarily enjoining L&N from making any repairs that would raise the elevation of the Main Street or Dixon Street crossings without the approval of Sebree's city council. In November 1979, L&N and the City resolved the litigation by entering an agreed order of dismissal (the "Agreed Order") that removed the temporary injunction against L&N. Pursuant to the Agreed Order, L&N agreed not to raise the level of the tracks at Main Street more than 0.4 feet above its then-current level, and not to raise the level of the tracks at Dixon Street at all.

Years later, CSX, as L&N's successor in interest, determined that it needed to conduct maintenance on the tracks in Sebree to correct the problem of fouled ballast. Ballast refers to the crushed rock used to support tracks and allow proper drainage. The ballast becomes fouled when smaller particles clog the space between the crushed rock, reducing the ability of water to drain freely. There are at least two maintenance methods that can be utilized to correct fouled ballast. One method, surfacing, entails lifting the track, which breaks the bottom of the ties-the supports to which railroad rails are fastened-free from the compacted fouled ballast, and then raising the track to the desired height and forcing ballast back underneath. Another method is undercutting, which is the removal of all ballast between the ties from approximately eight inches under the bottom of the ties. Surfacing results in raising the height of the crossings, but undercutting can be done while maintaining the height of the grade, or even lowering it.

In 2013, CSX began undertaking maintenance work that would result in an increase in the height of four of the railroad crossings in Sebree. Sebree police "arrived on the scene and threat[ened] CSX[ ] personnel with arrest[,]" and CSX was thus "not able to conduct the proposed maintenance that would result in raising the tracks." (Compl., R. 1, PageID 6.) In August 2017, CSX informed the City of its intent to perform track maintenance that would result in raising the crossings at Dixon, Main, Webster, and Jefferson Streets by two to three inches. CSX also informed the City of its intent to perform additional work at the Jefferson Street crossing, which would not raise the grade of the crossing. In October 2017, the Sebree city council met to discuss CSX's proposed track maintenance and voted 6-0 to deny CSX's request to perform any of the proposed maintenance work.

After the request to perform maintenance was denied, CSX brought this action for injunctive relief in the United States District Court for the Western District of Kentucky. CSX sought a preliminary injunction, seeking to prohibit the City from enforcing the Ordinance or the Agreed *282 Order, or otherwise interfering with CSX's railroad operations. The district court combined the hearing on the preliminary injunction with a trial on the merits, and the proceeding was held on March 1, 2018.

On May 24, 2018, the district court issued an opinion, holding that the Ordinance was preempted by the Interstate Commerce Commission Termination Act ("Termination Act"), and the Agreed Order was void as a matter of public policy. The court entered judgment in favor of CSX and permanently enjoined the City from "any enforcement of either the 1966 Ordinance or 1979 Agreed Order or otherwise undertaking any action which would seek to prevent CSX from raising its tracks for maintenance purposes within the City of Sebree." (J., R. 26, PageID 641.)

The City timely appealed.

II. ANALYSIS

A. Standard of Review

In reviewing a decision to grant or deny a motion for a permanent injunction, "we employ several different standards of review. 'Factual findings are reviewed under the clearly erroneous standard, legal conclusions are reviewed de novo, and the scope of injunctive relief is reviewed for an abuse of discretion.' " Sec'y of Labor, U.S. Dep't of Labor v. 3Re.com, Inc. , 317 F.3d 534 , 537 (6th Cir. 2003) (quoting S. Cent. Power Co. v. Int'l Bhd. of Elec. Workers, Local Union 2359

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
924 F.3d 276, Counsel Stack Legal Research, https://law.counselstack.com/opinion/csx-transp-inc-v-city-of-sebree-ca6-2019.