Crown Coat Front Co., Inc. v. United States

395 F.2d 160, 1968 U.S. App. LEXIS 6947
CourtCourt of Appeals for the Second Circuit
DecidedMay 14, 1968
Docket317, Docket 31915
StatusPublished
Cited by14 cases

This text of 395 F.2d 160 (Crown Coat Front Co., Inc. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crown Coat Front Co., Inc. v. United States, 395 F.2d 160, 1968 U.S. App. LEXIS 6947 (2d Cir. 1968).

Opinion

FEINBERG, Circuit Judge:

In 1956, the amount due plaintiff Crown Coat Front Co., Inc. on a contract with defendant United States was reduced by the sum of $270.01 out of a total contract price exceeding $60,000. This minor price adjustment, incredibly, has led to years of still unfinished litigation before the Armed Services Board of Contract Appeals, the United States District Court for the Southern District of New York, this court in banc, and the United States Supreme Court. 1 And now, in the latest phase of its dogged pursuit of its remedies, Crown Coat again appeals from a judgment of the United States District Court for the Southern District of New York, Walter R. Mansfield, J., dismissing as time-barred its complaint for damages against defendant United States. For reasons set forth below, we affirm.

As a prelude to further discussion of this appeal, three factors must be stressed. First, a contractor suing the Government must ordinarily do so within six years from the date his right of action accrues. Second, there is a conceptual difference between so-called “disputes clause” claims and “breach” claims growing out of a contract with the Government. Although it is frequently difficult to tell into which category a specific claim falls, 2 at least this much can be said: “Disputes clause” claims are “redressable under specific contract adjustment provisions” and therefore subject to the disputes procedure set forth in the contract; “breach” claims are not. United States v. Utah Constr. & Mining Co., 384 U.S. 394, 404 n. 6, 86 S.Ct. 1545, 16 L.Ed.2d 642 (1966). Third, the prior opinion of this court sitting in banc, Crown Coat Front Co. v. United States, 363 F.2d 407 (1966), still retains significance on certain issues decided therein even though it was reversed on other grounds.

*162 With these points in mind, we turn to the facts of this controversy, which can be related substantially as they appear in the opinion of the Supreme Court, 386 U.S. 503, 507-508, 87 S.Ct. 1177, 18 L.Ed.2d 256 (1967), but with important additions for matters the parties did not stress there. On May 14, 1956, Crown Coat contracted with the United States to supply a specified number of canteen covers which were to be lined with mildew-resistant felt of certain specifications. The Government, which was authorized to inspect materials to be used under the contract, tested and rejected certain samples of felt furnished by. Crown Coat because they allegedly did not contain the contract quantities of mildew inhibitors. Crown Coat agreed to a price reduction of one-half cent per canteen cover, a total of $270.01, and was permitted to complete the contract with the rejected felt. Final delivery, originally scheduled for October 11, 1956, was made on December 14, 1956.

In March 1959, Crown Coat allegedly first discovered the nature of the tests which the United States had performed on the felt. Objecting to the use of such tests, Crown Coat filed a claim with the government contracting officer in October 1961. Crown Coat contended that use of an improper test was a “change in contract specifications” under the “changes” clause of the contract, 3 entitling it to an equitable adjustment in the form of a refund of the price reduction and compensation for increased costs occasioned by substantial delay resulting from the Government’s rejection of the felt samples. The claim was brought before the contracting officer as a disagreement on a question of fact within the meaning of the “disputes” clause of the contract, 4 which requires that administrative relief be exhausted. On February 21, 1962, the contracting officer denied the claim which had been submitted to him; within a week, Crown Coat appealed to the Armed Services Board of Contract Appeals, a further administrative step required for assertion of a disputes clause claim. As the expiration of six years from the 1956 final delivery date approached, the Board had not yet ruled. On December 12, 1962, just two days before the end of the six-year period, Crown Coat filed a complaint in the Court of Claims under 28 U.S.C. § 1491, seeking $25,270.01 damages for breach of the contract by use of improper tests. Two months later, on February 28, 1963, the Board of Contract Appeals affirmed the contracting officer’s decision.

On July 31, 1963, Crown Coat commenced the instant action in the United States District Court for the Southern District of New York pursuant to the Tucker Act, 28 U.S.C. § 1346(a) (2). The complaint alleged that the Board of Contract Appeals decision was capricious, arbitrary and not supported by substantial evidence, and asserted that use of improper and inaccurate tests entitled Crown Coat to an equitable adjustment under the contract’s changes clause; the amount sought was $9,500. 5 At this point, therefore, there were then pending against the Government two actions growing out of the same transaction: one filed in the Court of Claims in December 1962, and the other filed in the district court in July 1963. The parties then returned to the Court of Claims. Because of the pendency of the district court proceedings, see 28 U.S.C. § 1500, Crown Coat moved to “suspend” its action in the Court of Claims, and the Government moved to dismiss. In Septem *163 ber 1963, the Court of Claims dismissed the action, without prejudice. 6

The district court action was thus left standing alone. In that action, the United States, among other things, asserted that the suit was time-barred under 28 U.S.C. § 2401(a), because it was brought more than six years after it had accrued. 7 Chief Judge Ryan agreed and dismissed the action on that ground. 8 This court, sitting in banc, affirmed that dismissal in a five-to-four decision, 363 F.2d 407 (1966) . All nine judges agreed that Crown Coat’s action accrued on December 14, 1956, the date of the final delivery of the canteen covers by Crown Coat. The issue that divided this court was whether the administrative proceeding before the contracting officer and the Board of Contract Appeals tolled the applicable six-year statute of limitations; if it did not, the district court suit in July 1963 was not timely. The majority held that the statute was not tolled; the minority thought that it was.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Phaneuf v. Tenneco, Inc.
938 F. Supp. 112 (N.D. New York, 1996)
Shochat v. Weisz
757 F. Supp. 189 (E.D. New York, 1991)
Motorola, Inc. v. United States
34 Cont. Cas. Fed. 75,380 (Court of Claims, 1987)
Hitchmon v. United States
585 F. Supp. 256 (S.D. Florida, 1984)
Robert A. Walters v. Secretary of Defense
725 F.2d 107 (D.C. Circuit, 1983)
Ippolito-Lutz, Inc. v. Harris
473 F. Supp. 255 (S.D. New York, 1979)
Matthew v. United States
471 F. Supp. 937 (S.D. New York, 1979)
Usm Corporation v. Gkn Fasteners Limited
578 F.2d 21 (First Circuit, 1978)
Holdridge v. Heyer-Schulte Corp. of Santa Barbara
440 F. Supp. 1088 (N.D. New York, 1977)
Thompson v. Dugan
427 F. Supp. 342 (E.D. Pennsylvania, 1977)
Crown Coat Front Co. v. United States
209 Ct. Cl. 653 (Court of Claims, 1976)
Wolak v. United States
366 F. Supp. 1106 (D. Connecticut, 1973)
Payne v. United States
336 F. Supp. 1008 (S.D. Texas, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
395 F.2d 160, 1968 U.S. App. LEXIS 6947, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crown-coat-front-co-inc-v-united-states-ca2-1968.